Windham Route 302 Reconstruction - Schedule and Documents

Detailed Sections of the plan sets:

Open House - June 18th, 2025

Preliminary Public Hearing- June 4th, 2024

Up Coming Project Milestones

  • Draft Horizontal Vertical Alignment- June 4th, 2024
  • Final Horizontal Vertical Alignment - November 2024
  • Draft Preliminary Design Report - September 2025
  • Final preliminary Design Report - January 2026
  • Final Public Hearing - February 2026
  • Plan Impact Complete - August 2026
  • Plans, Specifications, Estimate Complete - June 2027
  • Project Advertise - July 2027
  • Construction Begin - October 2027
  • Construction Complete - June 2030