In August of 2022, the City of Sanford, and the Maine Department of Transportation (MaineDOT) received a Federal RAISE Grant for infrastructure improvement projects in the Downtown area. The project will make complete streets improvements on approximately 0.7 miles on Cottage Street (Route 202), approximately 0.5 miles on William Oscar Emery Drive, approximately 0.5 miles of Main Street (Route 109), approximately 0.2 miles on Washington Street, and approximately 0.2 miles on School Street in downtown Sanford.

This project will replace and/or construct the street, sidewalks, crosswalk, underground utility ducts, streetlights, upgrade traffic signals, parking spaces, drainage areas, a multi-use pathway, and a Park & Ride facility on Emerson Street serving the Navy base; improve safety aspects of downtown for pedestrians, motorists, and all road users; modernize infrastructure to attract potential employers and commercial and residential development; and meet ADA and MaineDOT standards.

Project Schedule

  • Open House/Preliminary Public Hearing 11/17/22
  • Plan impact Complete- August 2024
  • Formal Public Meeting September 2024
  • Right of way process begins
    • Final Mapping
    • Appraisals
    • Negotiations
  • Project Plans, Specs & Estimate- November 2025
  • Project advertise- June/July 2026
  • Bid Openings- January 2026
  • Project award- February 2026
  • Construction Begin- March/April 2026
  • Construction Complete- Fall 2028/Spring 2029

 

Project Updates and Resources