Planning Studies
Funding Update
The list below identifies the projects that were delayed due to funding uncertainly and are now moving forward, following the recent funding update. Project schedules will continue to be updated as they are finalized.
- Click to Expand
Project Title and WIN
(Work ID Number)Scope Previous Advertised Date Revised Advertised Date 2026 STATEWIDE LOW-COST SAFETY VERTICAL ELEMENTS.
SAFETY IMPROVEMENTS
7/22/2026 2027 ADDISON, LOT NORTON BRIDGE #3754
BRIDGE REPLACEMENT
7/7/2026 9/2/2026 ALBANY TOWNSHIP, CROOKED RIVER BRIDGE #5079
BRIDGE PAINTING
Initial Bid Rejected 3/17/2027 ALBANY TOWNSHIP - ALBANY - BETHEL, ROUTE 5
HIGHWAY REHABILITATION
6/10/2026 Temporary Repair
Converted to LCP
ALNA, DOCK BRIDGE #3284
BRIDGE REHABILITATION
12/28/2026 12/28/2026 AUGUSTA HIGH-VISIBILITY CROSSWALKS
NEW CONSTRUCTION
6/24/2026 1/13/2027 BATH, CENTRE ST. CONNECTION BRIDGE #6142
BRIDGE PAINTING
Initial Bid Rejected 3/17/27 BELFAST, BRIER BRIDGE #1123
BRIDGE SUPERSTRUCTURE REPLACEMENT
12/23/2026 12/23/2026 BETHEL, ROUTE 2 SIDEWALK
NEW CONSTRUCTION
9/9/2026 1/27/2027 BLUE HILL, ROUTE 15
HIGHWAY REHABILITATION
Initial Advertised Date Past Temporary Repair
Converted to LCP
BRUNSWICK HEADS UP - PEDESTRIAN SAFETY IMPROVEMENTS
SAFETY IMPROVEMENTS
Initial Bid Rejected 12/2/2026 DOVER-FOXCROFT - STINCHFIELD BROOK BRIDGE #2808
BRIDGE REPLACEMENT
11/25/2026 11/25/2026 DREW PLANTATION - MATTAWAMKEAG RIVER BRIDGE #5105
BRIDGE REPLACEMENT
10/7/2026 11/18/2026 ELLSWORTH, ROUTE 1A
ULTRA-THIN BONDED WEARING COURSE
Initial Bid Rejected 9/30/2026 FORT KENT, ROUTE 1
1 1/4" OVERLAY
Initial Advertised Date Past Converted to LCP HALLOWELL HEADS UP, PED SAFETY IMPROVEMENTS AT WIN
SAFETY IMPROVEMENTS
10/14/2026 12/2/2026 HALLOWELL/AUGUSTA HEADS UP - SECOND ST. SIDEWALK C
SAFETY IMPROVEMENTS
10/14/2026 12/2/2026 HAMPDEN, ROUTE 202
SLOPE STABILIZATION/PROTECTION
Initial Advertised Date Past Late 2027 HOLDEN-DEDHAM, ROUTE 1A
ULTRA-THIN BONDED WEARING COURSE
Initial Advertised Date Past 9/16/2026 KINGFIELD, REED BROOK BRIDGE #5351
BRIDGE REPLACEMENT
11/11/2026 1/27/2027 KITTERY, I-95/PISCATAQUA RIVER BRIDGE #6330
BRIDGE PAINTING
Initial Bid Rejected 3/24/2027 LEWISTON, MTPK EXIT 13/MCRR BRIDGE #0059
BRIDGE PAINTING
3/18/2026 3/17/2027 NEWPORT - DEXTER, ROUTE 7
ULTRA-THIN BONDED WEARING COURSE
Initial Advertised Date Past 11/25/2026 NORWAY, PLEASANT STREET BRIDGE #2677
BRIDGE PAINTING
Initial Bid Rejected 3/17/2027 OXFORD, ROUTE 26
INTERSECTION RECONSTRUCTION
Initial Advertised Date Past 9/1/2026 ROCKLAND HEADS UP - RECTANGULAR RAPID FLASHING BEA
SAFETY IMPROVEMENTS
2/24/2027 9/23/2026 ROCKLAND, ROUTE 1
1 1/4" OVERLAY
Initial Bid Rejected 9/23/2026 RUMFORD, MARTINS BRIDGE #2514
BRIDGE REPLACEMENT
12/23/2026 3/17/27 RUMFORD, ROUTE 2
INSTALL OR REPLACE TRAFFIC SIGNALS
9/30/26 10/28/26 SILVER RIDGE TWP, MOLUNKUS STREAM BRIDGE #5627
BRIDGE REPLACEMENT
12/2/2026 12/2/2026 SKOWHEGAN, ROUTE 201A
NEW CONSTRUCTION
Initial Bid Rejected 1/13/2027 STATEWIDE, RWIS ITS
INTELLIGENT TRANSPORTATION SYSTEMS
12/2/2026 12/2/2026 STRONG, STEVENS BRIDGE #3364
BRIDGE REPLACEMENT
12/30/2026 12/30/2026 TOPSHAM, ROUTE 196/I-295 BRIDGE #6307
BRIDGE JOINT REPLACEMENT
Initial Bid Rejected 3/17/2027 TRESCOTT TWP, RICE BRIDGE #2714
BRIDGE REPLACEMENT
Initial Advertised Date Past 8/12/2026 VANCEBORO, INTERNATIONAL BRIDGE #2401
BRIDGE REHABILITATION
Initial Advertised Date Past 9/9/2026 WEST BATH, NEW MEADOWS ROAD BRIDGE #6145
BRIDGE PAINTING
Initial Bid Rejected 3/17/2027 WINDHAM, LOVEITT BRIDGE #3018
BRIDGE REPLACEMENT
10/28/2026 10/28/2026 WYMAN TOWNSHIP, STONEY BROOK BRIDGE #5342
BRIDGE REPLACEMENT
12/16/2026 8/18/2027 MULTIMODAL TRANSIT SUPPORT
(Coming Soon)
TRANSIT INNOVATION
n/a n/a