Project Schedule

  • Open House/Preliminary Public Hearing 11/17/22
  • Plan impact Complete- December 2023
  • Final Public Meeting November 2023
  • Right of way process begins
    • Final Mapping
    • Appraisals
    • Negotiations
  • Project Plans, Specs & Estimate- November 2025’
  • Project advertise- December 25’/January 2026’
  • Bid Openings- January 2026’
  • Project award- February 2026
  • Construction Begin- March/April 2026
  • Construction Complete- Fall 2028/Spring 2029