The Project includes the design and construction of six replacement bridges located in Sidney, ME and Waterville, ME, between Exit 113 and Exit 127. The project consists of five site locations: Dinsmore Road over I-95, Lyons Road over I-95, Drummond Road over I-95, Town Farm Road over I-95, and Trafton Road over I-95.

Project Documents

Current Schedule

Date Event
3/25/2025 MaineDOT Issues RFSOI
4/8/2025 at 3:00 PM EST Deadline for Design-Builders to Submit Questions on RFSOI
4/22/2025 MaineDOT Issues Responses to Questions Received on the RFSOI
4/29/2025 at 3:00 PM EDT Deadline for Design-Builders to Submit SOI
5/6/2025 MaineDOT Issues Notification of SOI Responsiveness to Design-Builders
5/13/2025 Deadline for Design-Builders to Submit Cure for SOI Responsiveness (If Applicable)
5/27/2025 MaineDOT Evaluates and Ranks SOIs and Notifies Design-Builders of Selection Results
6/17/2025 MaineDOT Issues Draft RFP
6/30/2025 at 3:00 PM EDT Deadline for Design-Builders to submit Questions on the Draft RFP
7/30/2025 MaineDOT Issues Responses to Draft RFP Questions
9/17/2025 MaineDOT Issues Final RFP
One Meeting Per Team between September 22 and October 17, 2025 Design-Builders Attend One-On-One Meetings with MaineDOT to Review Potential ATC Proposals (If applicable)
11/5/2025 at 3:00 PM EDT Deadline for Design-Builders to Submit ATC Proposals
1/14/2026 MaineDOT Issues Responses to ATC Proposals
1/28/2026 at 3:00 PM EDT Deadline for Design-Builders to Submit Questions on Final RFP
2/13/2026 MaineDOT Issues Responses to Final RFP Questions
3/11/2026 at 3:00 PM EDT Deadline for Design-Builders to Submit Technical and Price Proposal Packages
3/25/2026 MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders
4/1/2026 Deadline for Design-Builders to Submit Cure for Technical Responsiveness (If Applicable)
4/22/2026 at 11:00 AM EDT Deadline for Design-Builders to Submit Proposal Guaranty Package
4/22/2026 at 11:00 AM EDT MaineDOT Opens Price Proposals
5/1/2026 MaineDOT Awards Contract
Summer 2026 Design-Builder Begins Final Design & Construction