HomeDoing BusinessDesign Build → Sidney-Waterville Bridge Replacements

Sidney-Waterville Bridge Replacements

The Project includes the design and construction of six replacement bridges located in Sidney, ME and Waterville, ME, between Exit 113 and Exit 127. The project consists of five site locations: Dinsmore Road over I-95, Lyons Road over I-95, Drummond Road over I-95, Town Farm Road over I-95, and Trafton Road over I-95.

Project Documents

Current Schedule

DateEvent
3/25/2025MaineDOT Issues RFSOI
4/8/2025 at 3:00 PM ESTDeadline for Design-Builders to Submit Questions on RFSOI
4/22/2025MaineDOT Issues Responses to Questions Received on the RFSOI
4/29/2025 at 3:00 PM EDTDeadline for Design-Builders to Submit SOI
5/6/2025MaineDOT Issues Notification of SOI Responsiveness to Design-Builders
5/13/2025Deadline for Design-Builders to Submit Cure for SOI Responsiveness (If Applicable)
5/27/2025MaineDOT Evaluates and Ranks SOIs and Notifies Design-Builders of Selection Results
6/17/2025MaineDOT Issues Draft RFP
6/30/2025 at 3:00 PM EDTDeadline for Design-Builders to submit Questions on the Draft RFP
7/30/2025MaineDOT Issues Responses to Draft RFP Questions
9/17/2025MaineDOT Issues Final RFP
One Meeting Per Team between September 22 and October 17, 2025Design-Builders Attend One-On-One Meetings with MaineDOT to Review Potential ATC Proposals (If applicable)
11/5/2025 at 3:00 PM EDTDeadline for Design-Builders to Submit ATC Proposals
1/14/2026MaineDOT Issues Responses to ATC Proposals
1/28/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit Questions on Final RFP
2/13/2026MaineDOT Issues Responses to Final RFP Questions
3/11/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit Technical and Price Proposal Packages
3/25/2026MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders
4/1/2026Deadline for Design-Builders to Submit Cure for Technical Responsiveness (If Applicable)
4/22/2026 at 11:00 AM EDTDeadline for Design-Builders to Submit Proposal Guaranty Package
4/22/2026 at 11:00 AM EDTMaineDOT Opens Price Proposals
5/1/2026MaineDOT Awards Contract
Summer 2026Design-Builder Begins Final Design & Construction
6/30/2031Design-Builder Completes Final Design & Construction