The Project includes the design and construction of six replacement bridges located in Sidney, ME and Waterville, ME, between Exit 113 and Exit 127. The project consists of five site locations: Dinsmore Road over I-95, Lyons Road over I-95, Drummond Road over I-95, Town Farm Road over I-95, and Trafton Road over I-95.
Project Documents
Sidney-Waterville I95 RFSOI (PDF)
Civil Rights Supplemental REV & EEO (PDF)
Appendix A - Proposers General Information Form (PDF)
Sidney-Waterville Bridge Q-A (PDF)
Request for Proposals Book 1 - Design Build Low Bid General Conditions DRAFT(PDF)
Request for Proposals Book 2 - Project Requirements DRAFT (PDF)
Sidney-Waterville Final RFP Book 1 - Design Build Low Bid General Conditions (PDF)
Sidney-Waterville Final RFP Book 2 - Project Requirement (PDF)
Appendix A - Federal Wage Rates
Appendix B - Contract Forms and Exhibits
Appendix C - Public and Stakeholder Meeting Minutes
Appendix D - Existing Plans and Inspection Documents
- Existing Plans and Inspection Documents Part 1 (zip)
- Existing Plans and Inspection Documents Part 2 (zip)
- Existing Plans and Inspection Documents Part 3 (zip)
- Existing Plans and Inspection Documents Part 4 (zip)
- Existing Plans and Inspection Documents Part 5 (zip)
Appendix E - Geotechnical Data
Appendix F - Traffic and Accident Data
Appendix G - Survey Data, Wetlands Delineation, and Existing Alignments
Survey Data, Wetlands Delineation and Existing Alignments (zip)
Appendix H - Permits and Other Environmental Information
Appendix I - Supplemental Specifications and Special Provisions
Appendix J - Utilities
Sidney-Waterville Responses to Draft RFP Questions
Current Schedule
| Date | Event |
|---|---|
| 3/25/2025 | MaineDOT Issues RFSOI |
| 4/8/2025 at 3:00 PM EST | Deadline for Design-Builders to Submit Questions on RFSOI |
| 4/22/2025 | MaineDOT Issues Responses to Questions Received on the RFSOI |
| 4/29/2025 at 3:00 PM EDT | Deadline for Design-Builders to Submit SOI |
| 5/6/2025 | MaineDOT Issues Notification of SOI Responsiveness to Design-Builders |
| 5/13/2025 | Deadline for Design-Builders to Submit Cure for SOI Responsiveness (If Applicable) |
| 5/27/2025 | MaineDOT Evaluates and Ranks SOIs and Notifies Design-Builders of Selection Results |
| 7/1/2025 | MaineDOT Issues Draft RFP |
| 7/14/2025 at 3:00 PM EDT | Deadline for Design-Builders to submit Questions on the Draft RFP |
| 8/13/2025 | MaineDOT Issues Responses to Draft RFP Questions |
| 12/30/2025 | MaineDOT Issues Final RFP (Contingent on BIP Grant Agreement) |
| One meeting per team between 1/20/2026 and 2/20/2026. | Design-Builders Attend One-On-One Meetings with MaineDOT to Review Potential ATC Proposals (If applicable) |
| 3/13/2026 at 3:00 PM EDT | Deadline for Design-Builders to Submit ATC Proposals |
| 4/17/2026 | MaineDOT Issues Responses to ATC Proposals |
| 4/29/2026 at 3:00 PM EDT | Deadline for Design-Builders to Submit Questions on Final RFP |
| 5/15/2026 | MaineDOT Issues Responses to Final RFP Questions |
| 6/10/2026 at 3:00 PM EDT | Deadline for Design-Builders to Submit Technical Proposal Packages |
| 6/24/2026 | MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders |
| 7/1/2026 | Deadline for Design-Builders to Submit Cure for Technical Responsiveness (If Applicable) and Price Proposal Packages |
| 7/22/2026 at 11:00 AM EDT | Deadline for Design-Builders to Submit Proposal Guaranty Package |
| 7/22/2026 at 11:00 AM EDT | MaineDOT Opens Price Proposals |
| August 2026 | MaineDOT Awards Contract |
| Summer 2026 | Design-Builder Begins Final Design & Construction |
| 6/30/2031 | Design-Builder Completes Final Design & Construction |