Lewiston ? Crews will be performing maintenance work on the Wiseman Bridge on Chestnut Street in Lewiston beginning Monday, April 11th.
This work will necessitate a short detour for vehicular traffic utilizing Canal Street, Cedar Street, Lincoln Street and Main Street.
During the approximately four week closure, pedestrian access to the bridge will be maintained as crews work to repair the concrete on the arches of the bridge as well as repairing the sidewalk, curbing and bridge deck.
It is anticipated this $52,000 bridge work, performed by MaineDOT maintenance crews, will be completed within the first week of May, 2016.