Paving Schedule for Routes 3 and 230 in Trenton

Trenton ? Crews will wrap up the paving project on Routes 3 and 230 in Trenton this week.

On Tuesday, November 20th paving on Route 3 will take place from 8 a.m. to 3 p.m. resulting in alternating one-way traffic. After 3 p.m., crews will pave the turning lane only, resulting in two- way traffic flowing again on Route 3.

On Wednesday, November 21st from 8 a.m. to 3 p.m., crews will pave Route 230 at the intersection with Route 3. Two-way traffic on Route 230 will be maintained.

While paving for the season will be completed by 3 p.m. on Wednesday, November 21st, motorists can still expect to see work crews in the area. No further delays are anticipated as two-way traffic will be maintained.