Biddeford ? Crews will perform a paving operation (mill and fill) at two locations in Biddeford beginning on Monday, April 24th.
One location will be at the intersection of Elm Street (Route 1) and extend northerly for 0.85 of a mile to Alfred Street (Route 111) ending at the intersection of Alfred and Precourt Streets.
The other location begins at Falls Street and extends northerly for 0.44 of a mile to Maine Street.
Motorists should expect slight delays and are advised to use caution when traveling through the work zones.
It is anticipated all work will be completed by the middle of July, 2017.
Shaw Brothers Construction, Inc. of Gorham will perform this $779,000 project.