Brunswick/Freeport Closure Continues

Brunswick, Maine ? Route 1 in Brunswick continues to have unanticipated issues with a pipe failure running beneath the roadway. Crews have initiated single lane traffic through today, with night work beginning at 8pm, closing the road except for local traffic on either side of the project.

On Sunday, October 30, full road closure will take place to change the pipe and repave the area. It is anticipated work will be completed Monday morning, October 31, 2011.