Photo Gallery

July 2023

Sargent continued to move excavation when weather allowed. They installed the waterproofing membrane on Snow Scooter Box Culvert and then began and completed placing lightweight fill over culvert. They completed backfilling Clewleyville Road Bridge abutment 2 up to approach slab grade and continued installing riprap drainage through clay dam. They also built and cast in place 4 (four) spread footing lighting foundations. T Buck: Clewleyville Road Bridge: Continued setting safety hardware and began forming deck. Eastern Avenue Bridge: Began forming and placing rebar for Abutment 2 breastwall. East Coast Signals continued installing conduit with excavating and backfilling assistance from Sargent. HB Flemming completed pile work on Eaton Brook West (abutment 1).

June 2023

Sargent continued box culvert backfilling and applied membrane at Snow Scooter Box Culvert, they also prepped area to receive and began installing Lightweight Fill. Sargent continued installing RCP’s and began removing soil overburden on Ramps E & F to prepare for Lightweight Fill in that area. T Buck worked on Clewleyville Road Bridge: Completed placing forms and rebar for Abutment 2 east wingwall and west wingwall section 1, placed concrete in both areas and Eastern Avenue Bridge: Completed placing forms and rebar for Abutment 1 breastwall and placed concrete. East Coast Signals continued installing the ITS conduit (with digging and backfilling assistance from Sargent). HB Fleming completed driving piles at Eaton Brook East and has moved to Eaton Brook West.

May 2023

Sargent has continued to work throughout the winter. They currently have closed Clewleyville Road and Eastern Avenue. Excavation has been removed from both of these roads and bridge abutment footers have been started on both. Sargent has also begun installing four box culverts between Levenseller Road and the Route 9 end of the project. T Buck has worked on the Clewleyville Road Bridge to include placing concrete for both abutment footers and abutment 1 breastwall and east wingwall section 2 and they have also placed concrete for abutment 2 at the Eastern Avenue Bridge and have begun form work for abutment 1. Heath Hathaway Blasting has continued drilling and blasting.