Bangor – Brewer I-395 Bridges

The project includes the design and construction of three bridge replacements and three bridge rehabilitations along the I-395 corridor between Bangor and Brewer, beginning near Exit 3 and ending near the Green Point Road Bridge. The six bridges include I-395 over Main Street in Bangor, Veterans Remembrance Bridge over the Penobscot River, I-395 over MCRR in Brewer, Robertson Blvd over I-395 in Brewer, Parkway South over I-395 in Brewer, and Green Point Road over I-395 in Brewer.

Project Documents

Bangor-Brewer I-395 Bridges RFSOI (PDF)

Current Schedule

DateEvent
3/04/2026MaineDOT Issues RFSOI
3/18/26 at 3:00 PM ESTDeadline for Design-Builders to Submit Questions on RFSOI
4/01/2026MaineDOT Issues Responses to Questions Received on the RFSOI
4/14/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit SOI
4/22/2026MaineDOT Issues Notification of SOI Responsiveness to Design-Builders
4/29/2026Deadline for Design-Builders to Submit Cure for SOI Responsiveness (If Applicable)
5/13/2026MaineDOT Evaluates and Ranks SOIs and Notifies Design-Builders of Selection Results
5/20/2026MaineDOT Issues Draft RFP
6/03/2026 at 3:00 PM EDTDeadline for Design-Builders to submit Questions on the Draft RFP
6/17/2026MaineDOT Issues Responses to Draft RFP Questions
7/08/2026MaineDOT Issues Final RFP
One meeting per team between 7/15 and 8/05/2026.Design-Builders Attend One-On-One Meetings with MaineDOT (If applicable)
8/26/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit ATC Proposals
9/16/2026MaineDOT Issues Responses to ATC Proposals
10/14/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit Questions Final RFP
10/28/2026MaineDOT Issues Responses to Final RFP Questions
11/25/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit Technical and Price Proposal Packages
12/09/2026MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders
12/16/2026Deadline for Design-Builders to Submit Cure for Technical Responsiveness (If Applicable)
1/20/2027 at 11:00 AM EDTDeadline for Design-Builders to Submit Proposal Guaranty Package
1/20/2027 at 11:00 AM EDTMaineDOT Opens Price Proposals
Winter 2027MaineDOT Awards Contract
Winter 2027Design-Builder Begins Final Design & Construction
6/30/2031Design-Builder Completes Final Design & Construction