Pavement Milling, Hot Mix Asphalt Overlay, Cyclical Pavement Resurfacing, with Drainage and Safety Improvements:
- 024881.00 is located on Route 104 in Sidney, beginning 0.30 of a mile north of the Augusta city line & extending north 5.21 miles.
- 024883.00 is located in Augusta on the Leighton Road, beginning at Old Winthrop Road & extending north 2.77 miles to Route 8.
- 024885.00 is in Augusta on Route 105, beginning 0.28 of a mile west of Church Hill Road & extending east 2.33 miles.
Bid Date:
Documents
- Notice to Contractors
- Notice to Contractors - Federal Projects
- Schedule of Items
- Bid Amendment
- Plan Holder
Plan Holder List Registration
Plan Holder List Registration:
RFI - Request for Information
RFI - Request for Information:
Awarded to
All States Construction, Inc. of Sunderland, MA.
Date Awarded
Status