The project includes the design and construction of three bridge replacements and three bridge rehabilitations along the I-395 corridor between Bangor and Brewer, beginning near Exit 3 and ending near the Green Point Road Bridge. The six bridges include I-395 over Main Street in Bangor, Veterans Remembrance Bridge over the Penobscot River, I-395 over MCRR in Brewer, Robertson Blvd over I-395 in Brewer, Parkway South over I-395 in Brewer, and Green Point Road over I-395 in Brewer.
Project Documents
Bangor-Brewer I-395 Bridges RFSOI (PDF)
Current Schedule
| Date | Event |
|---|---|
| 3/04/2026 | MaineDOT Issues RFSOI |
| 3/18/26 at 3:00 PM EST | Deadline for Design-Builders to Submit Questions on RFSOI |
| 4/01/2026 | MaineDOT Issues Responses to Questions Received on the RFSOI |
| 4/14/2026 at 3:00 PM EDT | Deadline for Design-Builders to Submit SOI |
| 4/22/2026 | MaineDOT Issues Notification of SOI Responsiveness to Design-Builders |
| 4/29/2026 | Deadline for Design-Builders to Submit Cure for SOI Responsiveness (If Applicable) |
| 5/13/2026 | MaineDOT Evaluates and Ranks SOIs and Notifies Design-Builders of Selection Results |
| 5/20/2026 | MaineDOT Issues Draft RFP |
| 6/03/2026 at 3:00 PM EDT | Deadline for Design-Builders to submit Questions on the Draft RFP |
| 6/17/2026 | MaineDOT Issues Responses to Draft RFP Questions |
| 7/08/2026 | MaineDOT Issues Final RFP |
| One meeting per team between 7/15 and 8/05/2026. | Design-Builders Attend One-On-One Meetings with MaineDOT (If applicable) |
| 8/26/2026 at 3:00 PM EDT | Deadline for Design-Builders to Submit ATC Proposals |
| 9/16/2026 | MaineDOT Issues Responses to ATC Proposals |
| 10/14/2026 at 3:00 PM EDT | Deadline for Design-Builders to Submit Questions Final RFP |
| 10/28/2026 | MaineDOT Issues Responses to Final RFP Questions |
| 11/25/2026 at 3:00 PM EDT | Deadline for Design-Builders to Submit Technical and Price Proposal Packages |
| 12/09/2026 | MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders |
| 12/16/2026 | Deadline for Design-Builders to Submit Cure for Technical Responsiveness (If Applicable) |
| 1/20/2027 at 11:00 AM EDT | Deadline for Design-Builders to Submit Proposal Guaranty Package |
| 1/20/2027 at 11:00 AM EDT | MaineDOT Opens Price Proposals |
| Winter 2027 | MaineDOT Awards Contract |
| Winter 2027 | Design-Builder Begins Final Design & Construction |
| 6/30/2031 | Design-Builder Completes Final Design & Construction |