9-22 UPDATE:

Due to expected rain, the contractor has pushed back striping operations by one day. Northbound closures are now planned between 11:00 p.m. on Wednesday, September 23rd and 5:00 a.m. on Thursday, September 24th. Southbound closures are now planned between 11:00 p.m. on Thursday, September 24th and 5:00 a.m. on Friday, September 25th.

ORIGINAL PRESS RELEASE:

BANGOR - The ongoing Ohio Street Bridge replacement project in Bangor will require full closures of the interstate next week to accommodate road striping operations. The contractor plans to close the northbound side of I-95 between 11:00 p.m. on Tuesday, September 22nd and 5:00 a.m. on Wednesday, September 23rd and close the southbound side between 11:00 p.m. on Wednesday, September 23rd and 5:00 a.m. on Thursday, September 24th. Signs will direct drivers to detour routes. Maps are also available on the project website. Like all outdoor construction work, this work is weather-dependent.

The new Ohio Street Bridge is scheduled to open to traffic in October. The new structure includes non-corrosive materials to reduce future maintenance needs. The new bridge also provides an additional 18 inches of clearance for vehicles on the interstate. This project added a turning lane on Ohio Street for vehicles turning onto the ramp to travel southbound on I-95.

The contractor on this work is T. Buck Construction, Inc. of Turner. The contract amount is $5,968,445.

For more information, visit the project website: https://www.maine.gov/mdot/projects/bangor/ohiost/.