Welcome to the new MaineDOT website! 

We've recently transitioned to a new content management system to improve the MaineDOT website. We appreciate your patience while we work to update the site. If you have any questions or specific content requests in the meantime, please Contact Us.

HomeNews → Union Street Bridge Project In Bangor Schedule For Week of September 6th

Union Street Bridge Project in Bangor Schedule for Week of September 6th

Bangor ? CPM Constructors will be working on Interstate 95 during overnight hours on the Union St. Bridge project over Interstate 95.

This work involves closing one lane of traffic on the interstate to allow for construction to take place safely between the times of 7:00 p.m. and 7:00 a.m. or a full interstate closure between the times of 9:00 p.m. and 5:00 a.m. northbound and between 9:00 PM and 6:00 AM southbound.

The current closure schedule for the week of 9/6/2015 is below. Motorists are advised to follow appropriate construction signage and detour routes through the work zones and detours.

Tuesday, September 9: Full northbound interstate closure from 9:00 p.m. to 5:00 a.m. as well as the southbound on-ramp from 7:00 p.m. To 7:00 a.m.

Wednesday, September 10: Full interstate closure northbound from 9:00 p.m. to 5:00 a.m. as well as a full interstate closure southbound from 9:00 p.m. to 6:00 a.m. In addition, the southbound on-ramp will be closed from 7:00 p.m. to 7:00 a.m.