Home > Recovery > State Fiscal Stabilization State Plans > Indicator (b)(1) 4
State Plan Indicator (b)(1) 4
| Create an electronic transcript exchange between LEAs and the UMS |
In Progress |
7/1/2010 |
6/30/2011 |
|
1/6/2011 - Maine Community Colleges added to postsecondary participants. |
| Establish requirements for transcript exchange system |
In Progress |
7/1/2010 |
2/28/2011 |
|
1/10/2011 - Requirements for horizontal exchange between LEAs started with SIS vendors.
1/6/2011 - Infinite Campus delivered specifications for review by postsecondary. |
| Develop & Implement transcript exchange system |
In Progress |
11/1/2010 |
2/28/2011 |
|
|
| Test electronic transcript exchange and provide training to LEAs for electronic transcript submission |
Not Started |
2/28/2011 |
6/30/2011 |
|
|
|
|
|
|
|
|
| Create postsecondary linkage with the University of Maine System (UMS) |
In Progress |
8/1/2010 |
5/31/2011 |
|
1/6/2011 - Maine Community Colleges System (MCCS) added to the component. |
| Establish linkage requirements and design process to link high school data with the UMS |
In Progress |
8/1/2010 |
4/30/2011 |
|
1/6/2011 - Meeting with MCCS presidents held 10/27. Resources being identified. |
| Develop & Implement postsecondary linkage system |
In Progress |
10/1/2010 |
3/31/2011 |
|
1/6/2011 - Tied to eTranscripts |
| Test system and evaluate its effectiveness |
In Progress |
1/1/2011 |
5/31/2011 |
|
|
|