Home > Recovery > State Fiscal Stabilization State Plans > Indicator (b)(1) 4

State Plan Indicator (b)(1) 4

Create an electronic transcript exchange between LEAs and the UMS In Progress 7/1/2010 6/30/2011   1/6/2011 - Maine Community Colleges added to postsecondary participants.
Establish requirements for transcript exchange system In Progress 7/1/2010 2/28/2011   1/10/2011 - Requirements for horizontal exchange between LEAs started with SIS vendors.
1/6/2011 - Infinite Campus delivered specifications for review by postsecondary.
Develop & Implement transcript exchange system In Progress 11/1/2010 2/28/2011    
Test electronic transcript exchange and provide training to LEAs for electronic transcript submission Not Started 2/28/2011 6/30/2011    
Create postsecondary linkage with the University of Maine System (UMS) In Progress 8/1/2010 5/31/2011   1/6/2011 - Maine Community Colleges System (MCCS) added to the component.
Establish linkage requirements and design process to link high school data with the UMS In Progress 8/1/2010 4/30/2011   1/6/2011 - Meeting with MCCS presidents held 10/27. Resources being identified.
Develop & Implement postsecondary linkage system In Progress 10/1/2010 3/31/2011   1/6/2011 - Tied to eTranscripts
Test system and evaluate its effectiveness In Progress 1/1/2011 5/31/2011