Home > Recovery > State Fiscal Stabilization State Plans > Indicator (b)(1) 11
State Plan Indicator (b)(1) 11
| College Readiness Assessment System |
In Progress |
3/1/2009 |
4/30/2011 |
|
|
| Determine definition and design |
Operational |
3/16/2009 |
12/15/2010 |
|
12/2/2010 - Maine Community College System looking to leverage At-Risk datamart. MEPRI researchers will assist with design. |
| Development and deployment of College Readiness Assessment System |
In Progress |
1/25/2010 |
3/31/2011 |
|
1/10/2011 - The MDOE and Mitchell Institute NSC contracts are being integrated to share resources along with the MEPRI researchers. The initial PSAT data tied to State Student IDs from College Board is due in January.
12/2/2010 - NESSC consortium working with National Student Clearinghouse. |
| Testing and documentation of College Readiness Assessment System |
In Progress |
7/1/2010 |
4/15/2011 |
|
1/10/2011 - Testing of the integration with PSAT data is scheduled for January.
12/2/2010 - Evaluation by MEPRI researchers |
| Training |
In Progress |
9/1/2010 |
4/30/2011 |
|
|
|