June
15, 2012 DOE application process begins
September
28, 2012 SAU deadline for applications to be
received by DOE
November
30, 2012 DOE completes review and rating process
December
28, 2012 BGS
reviews technical content and completes cost analysis
January
15, 2013 DOE prepares final priority list
February
1, 2013 DOE issues eligibility certificates
July
31, 2013 SAU deadline for MMBB loan
application process to be completed
July 31, 2014 SAU
deadline for SRRF project work completion and submission of final payment