2004-2005 Rating Cycle - Project Information

Final Priority List

The Department of Education's list based on a rating of the overall needs of those school districts that submitted a Major Capital School Construction Application.

Microsoft Excel Version Adobe Acrobat Version

 

Approved Projects List

After the Final Priority List is established, the State Board of Education designates projects from that list to be placed on the Approved Projects List of projects that the State Board intends to fund for a given rating cycle. Placement on the Approved Projects List is an acknowledgement that the pupils in the rated facility have a significant need to be housed under improved circumstances. It does not assure replacement of the facility(ies) that received the rating.

Microsoft Word Version Adobe Acrobat Version

 

 

Approved Projects for Major Capital School Construction during the 2004-2005 Rating Cycle

 

Projects 1 through 6 were approved on August 10, 2005, by the State Board of Education for placement on the Approved Projects List. Projects 1 through 6 must receive Concept Approval by the State Board of Education by 12/31/2006.

 

1. Portland School Department - New K-5 Ocean Avenue Elementary School- Concept Deadline waiver granted 2/14/2007. New Concept Approval Deadline 3/31/2008.

SITE DEVELOPMENT - Approved by the State Board of Education on 1/9/2008
Site Approval Exhibit

CONCEPT DEVELOPMENT - Approved by the State Board of Education on 3/12/2008

Concept Exhibit
Concept Budget

Concept Schedule

Schedule amended by the State Board of Education on 10/15/2008.  See State Board Exhibit and Dept. of Education Press Release

DESIGN DEVELOPMENT - Approved by the State Board of Education on 3/11/2009
Design & Funding Exhibit
Design & Funding Budget

Design & Funding Schedule

Schedule amended by the State Board of Education on 10/15/2008.  See State Board Exhibit and Dept. of Education Press Release

 

 

2. RSU 6/SAD 6 Buxton - New K-5 Elementary School - Concept Deadline waiver granted 2/14/2007. New Concept Approval Deadline 3/31/2007.

SITE DEVELOPMENT - Approved by the State Board of Education on 1/10/2007
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 4/11/2007
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 2/21/2008
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

3. Peninsula CSD - Winter Harbor - New PreK-8 Elementary School in Prospect Harbor in the Town of Greensboro- Concept Approval Deadline waiver granted 2/14/2007. New Concept Approval Deadline 3/14/2007.

SITE DEVELOPMENT - Approved by the State Board of Education on 3/14/2007
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 5/9/2007
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 1/9/2008
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

4. RSU 24 (formerly Ellsworth School Department) - New PreK-5 Elementary School and an Addition to the Existing 6-8 Middle School - Concept Deadline waiver granted 2/14/2007. New Concept Approval Deadline 5/9/2007

SITE DEVELOPMENT - Approved by the State Board of Education on 3/14/2007
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 5/9/2007
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 1/9/2008
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

5. RSU 54/SAD 54 - Norridgewock - New PreK-6 Elementary School

SITE DEVELOPMENT - Approved by the State Board of Education on 8/2/2006
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 9/12/2006
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 5/9/2007
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

6. Lewiston School Department - New Raymond A. Geiger Elementary School

SITE DEVELOPMENT - Approved by the State Board of Education on 7/12/2006
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 11/15/2006
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 10/10/2007
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

Projects 7 through 13 were approved on August 10, 2005, by the State Board of Education for placement on the Approved Projects List. Projects 7 through 13 must receive Concept Approval by the State Board of Education by 12/31/2007.

 

7. RSU 32/SAD 32 - Ashland - New PreK-12 School

SITE DEVELOPMENT - Approved by the State Board of Education on 6/13/2007
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 12/12/2007
Concept Exhibit
Concept Budget
Concept Schedule

DESIGN DEVELOPMENT

Phase 1 Site Preparation ONLY - Approved by the State Board of Education on 6/11/2008

Final Design & Funding - Approved by the State Board of Education on 8/12/2008

Design & Funding Exhibit

Phase 1 Site Preparation ONLY

Design & Funding Budget a

Phase 1 Site Preparation ONLY

Design & Funding Schedule

Phase 1 Site Preparation ONLY

Design & Funding Exhibit
Adobe Acrobat
Design & Funding Budget
Design & Funding Schedule

 

 

8. Brewer High School District Trustees - New PreK-8 Elementary School

SITE DEVELOPMENT - Approved by the State Board of Education on 6/13/2007
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 10/10/2007
Concept Exhibit
Concept Budget
Concept Schedule

DESIGN DEVELOPMENT

Phase 1 Site Preparation ONLY - Approved by the State Board of Education on 8/12/2008

Final Design & Funding - Approved by the State Board of Education on 10/15/2008

Design & Funding Exhibit (Phase I Site Preparation ONLY)

Design & Funding Budget (Phase I Site Preparation ONLY)

Design & Funding Schedule (Phase I Site Preparation ONLY)

Amended by the State Board of Education on 10/15/2008.  See State Board Exhibit and Dept. of Education Press Release

Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

9. Westbrook School Department - New 6-8 Middle School

SITE DEVELOPMENT - Approved by the State Board of Education on 2/20/2007
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 4/11/2007
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 1/9/2008
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

10. Gorham School Department - New Elementary School - Concept Approval Deadline waiver granted 4/9/2008. New Concept Approval Deadline 10/31/2008

SITE DEVELOPMENT - Approved by the State Board of Education on 5/14/2008
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 6/11/2008
Concept Exhibit
Concept Budget

Concept Schedule

Amended by the State Board of Education on 10/15/2008.  See State Board Exhibit and Dept. of Education Press Release.

DESIGN DEVELOPMENT - Approved by the State Board of Education on 8/18/2009
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

11. RSU 05 (formerly Durham School Department) - New PreK-8 Elementary School

SITE DEVELOPMENT - Approved by the State Board of Education on 8/9/2006
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 9/12/2007
Concept Exhibit
Concept Budget

Concept Schedule

Amended by the State Board of Education on 10/15/2008.  See State Board Exhibit and Dept. of Education Press Release

DESIGN DEVELOPMENT - Approved by the State Board of Education on 11/12/2008
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

12. Machias School Department - New High School - FAILED TO MEET REQUIRED DEADLINES - REMOVED FROM APPROVED PROJECTS LISTS ON 4/9/2008.

 

 

13. Brunswick School Department - New Elementary School

SITE DEVELOPMENT - Approved by the State Board of Education on 2/21/2008
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 4/9/2008
Concept Exhibit08
Concept Budget

Concept Schedule

Amended by the State Board of Education on 10/15/2008.  See State Board Exhibit and Dept. of Education Press Release

DESIGN DEVELOPMENT - Approved by the State Board of Education on 7/15/2009

Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

Projects 14 through 20 were approved on July 12, 2006, by the State Board of Education for placement on the Approved Projects List. Projects 14 through 20 must receive Concept Approval by the State Board of Education by 12/31/08.

 

14. AOS 93 CLCSS (formerly Jefferson School Department) - New PreK-8 Elementary School

SITE DEVELOPMENT

Approved by the State Board of Education on 10/15/2008

Amendment approved by the State Board of Education on 3/11/2009

Site Exhibit
Amended Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 4/15/2009
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 4/14/2010
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

15. RSU 12 (formerly Chelsea School Department) - New PreK-8 Elementary School

SITE DEVELOPMENT - Approved by the State Board of Education on 9/10/2008
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 1/14/2009
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 3/10/2010
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

16. RSU #1 - New PreK-8 School in Woolwich

SITE DEVELOPMENT - Approved by the State Board of Education on 9/10/2008
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 2/11/2009
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 4/14/2010
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

17. RSU 22/SAD 22 Hampden - New High School

SITE DEVELOPMENT - Approved by the State Board of Education on 7/9/2008
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 8/12/2008
Concept Exhibit
Concept Budget

Concept Schedule

Amended by the State Board of Education on 10/15/2008.  See State Board Exhibit and Dept. of Education Press Release

DESIGN DEVELOPMENT - PHASE 1 (site preparation) - Approved by the State Board of Education on 7/15/2009
Phase 1 Design & Funding Exhibit
Phase 1 Design & Funding Budget
Phase 1 Design & Funding Schedule
FINAL DESIGN DEVELOPMENT - Approved by the State Board of Education on 1/13/2010
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 

18. RSU 09/Mt. Blue Regional School District (formerly SAD #9) Farmington - High School and Vocational Center

SITE DEVELOPMENT
Site Approval - Approved by the State Board of Education 1/14/2009
CONCEPT DEVELOPMENT
Concept Approval - Approved by the State Board of Education 7/15/2009
Concept Budget - Approved by the State Board of Education 7/15/2009
Concept Schedule - Approved by the State Board of Education 7/15/2009
DESIGN DEVELOPMENT
Design & Funding Approval - Approved by the State Board of Education 8-10-2010
Design & Funding Budget - Approved by the State Board of Education 8-10-2010
Design & Funding Schedule - Approved by the State Board of Education 8-10-2010

 

 

19 Falmouth School Department - Elementary School

SITE DEVELOPMENT - Approved by the State Board of Education on 4/9/2008
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 8/12/2008
Concept Exhibit
Concept Budget

Concept Schedule

Amended by the State Board of Education on 10/15/2008.  See State Board Exhibit and Dept. of Education Press Release

DESIGN DEVELOPMENT

Phase I Site Preparation ONLY - Approved by the State Board of Education on 4/15/2009

Final Design Development - Approved by the State Board of Education on 8/18/2009

Phase I Design & Funding Exhibit
Phase I Design & Funding Budget
Phase I Design & Funding Schedule
Final Design & Funding Exhibit
Final Design & Funding Budget
Final Design & Funding Schedule

 

 

20. RSU 09/Mt. Blue Regional School District (formerly SAD #9) Farmington - New PreK-3 Elementary School

SITE DEVELOPMENT - Approved by the State Board of Education on 9/10/2008
Site Exhibit
CONCEPT DEVELOPMENT - Approved by the State Board of Education on 11/12/2008
Concept Exhibit
Concept Budget
Concept Schedule
DESIGN DEVELOPMENT - Approved by the State Board of Education on 12/21/2009
Design & Funding Exhibit
Design & Funding Budget
Design & Funding Schedule

 

 