MaineDOT

News Release for September 13, 2013

For more Information:
Paul Merrill, Public Information Officer - 207-624-3355 or 207-215-9297

 

Overnight I-295 Paving Schedule for Next Week

Portland – Overnight paving continues on I-295 northbound from Scarborough to the Portland/Falmouth town line.

Next week’s schedule is as follows:

• Sunday, September 15th the Exit 2 on-ramp and acceleration lane will be closed for surface pavement removal and paving operations

• Monday, September 16th and Tuesday, September 17th the Exit 4 off-ramp and Route 1A to Veterans Bridge will be closed for surface pavement removal and paving operations

• Wednesday, September 18th and Thursday, September 19th the Exit 5 on and off-ramps (Fore River Parkway) will be closed for surface pavement removal and paving operations

All work will take place from 9 p.m. to 5 a.m., weather permitting.

###