Skip Maine state header navigation
Scheduled For
Oral Argument April 17, 2003
In The United States
Court Of Appeals
For The
District Of Columbia Circuit
____________________
No. 02-1047
____________________
NSTAR Electric
& Gas Corporation
Petitioner,
v.
Federal Energy
Regulatory Commission,
Respondent.
____________________
On Petition
For Review Of Orders Of
The
Federal Energy Regulatory Commission
____________________
Initial Brief
of Intervenor
Maine Public
Utilities Commission
Lisa Fink State of Maine Public Utilities Commission 242 State Street 18 State House Station Augusta, ME 04333-0018 (207) 287-1391 (phone) DATED: November 26, 2002 |
Harvey L. Reiter John E. McCaffrey Stinson
Morrison Hecker llp 1150 18th
Street, N.W., Suite 800 Washington, DC 20036 (202) 785-9100 Counsel
for Maine Public Utilities Commission |
CERTIFICATE OF COUNSEL FOR INTERVENOR
AS TO PARTIES, RULINGS AND RELATED CASES
Pursuant to Circuit Rule 28(a), counsel for
Intervenor Maine Public Utilities
Commission (“MPUC”) hereby certifies that
the following information required by Rules 12(c) and 28(a)(1) of the rules of
this Court is true and correct to the best of counsel’s knowledge.
A. Parties and Amici
All parties, intervenors and amici appearing before the Federal Energy
Regulatory Commission (“FERC”) and in this Court are listed in the Initial
Brief of Petitioner NSTAR Electric & Gas Corporation (“NSTAR”).
B. Rulings Under Review
References to the rulings
at issue appear in the Initial Brief of NSTAR.
C. Related Cases
To the best of counsel’s
knowledge, no related cases have been or are currently before this Court or any
other court.
Respectfully submitted,
|
_________________________________ Harvey L. Reiter John E. McCaffrey Stinson
Morrison Hecker llp 1150 18th
Street, N.W., Suite 800 Washington, DC 20036 (202) 785-9100 Counsel
for Maine Public Utilities Commission |
TABLE OF CONTENTS
TABLE
OF AUTHORITIES.............................................................................. 1
GLOSSARY...................................................................................................... 1
STATEMENT OF THE ISSUES........................................................................ 2
STATUTES AND REGULATIONS................................................................... 2
STATEMENT OF THE CASE AND
STATEMENT OF THE FACTS................ 2
SUMMARY OF THE ARGUMENT................................................................... 2
ARGUMENT..................................................................................................... 4
I. FERC May Not Use its 60-Day Waiver Authority to Make The
Mitigation Agreement Rates at Issue Here Effective Prior to the Date of the
Filing of the Agreements........... 4
II. FERC’s Authority and Obligation to Approve the
Mitigation Agreement Rates As Just And Reasonable Cannot Be Delegated To
ISO-NE............................................... 12
CONCLUSION................................................................................................ 13
CERTIFICATE OF LENGTH.......................................................................... 14
FEDERAL CASES
Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 571 (1981).................................. 9
City of Piqua v. FERC, 610 F.2d 950 (D.C. Cir. 1979)................................ 10, 11
*Columbia Gas Transmission Corp. v. FERC, 895 F.2d 791 (D.C. Cir.), cert. denied, 490 U.S. 907 (1990)................................................................................... 9, 11
East Tennessee Natural Gas Co. v. FERC, 863 F.2d 932 (D.C. Cir. 1988)..... 9, 10
STATUTES
Federal Power Act, Section 205, 16 U.S.C. § 824d.............................................. 9
Federal Power Act, Section 205(d), 16 U.S.C. § 824(d)............................... passim
Natural Gas Act, Section 4, 15 U.S.C. § 717d……………………………………..9
ADMINISTRATIVE DECISIONS
Central Hudson Gas and Electric Corp., 60 FERC ¶ 61,106, reh’g denied, 61 FERC ¶ 61,089 (1992)................................................................................ 5, 6, 7, 8
Mirant Americas Energy Marketing, L.P., 97 FERC ¶ 61,108 (2001)................. 4
Mirant Americas Energy Marketing, L.P., 97 FERC ¶ 61,360 (2001)............. 4, 5
Mirant Americas Energy Marketing, L.P., 99 FERC ¶ 61,003 (2002)............... 14
NRG Power
Marketing, Inc. v. New York Ind. System Operator, Inc.,
91 FERC ¶ 61,346
(2000)…………………………………………..……………..13
Texas Gas Transmission Corporation, 56 FERC ¶ 61,409 (1991)...................... 12
*Authorities upon which we chiefly rely are marked with asterisks.
Pursuant to Circuit Rule 28(a)(3), below is a list defining
abbreviations and acronyms used in this Brief.
Commission Federal
Energy Regulatory Commission
FERC Federal
Energy Regulatory Commission
FPA Federal
Power Act
ISO Independent
System Operator
ISO-NE ISO
New England Inc.
MPUC Maine
Public Utilities Commission
NEPOOL New
England Power Pool
NSTAR NSTAR
Electric & Gas Corporation
In The United States
Court Of Appeals
For The
District Of Columbia Circuit
____________________
No. 02-1047
____________________
NSTAR Electric
& Gas Corporation
Petitioner,
v.
Federal Energy
Regulatory Commission,
Respondent.
____________________
On Petition
For Review Of Orders Of
The
Federal Energy Regulatory Commission
____________________
Initial Brief Of intervenor
maine public utilities commission
Intervenor Maine Public Utilities Commission
(“MPUC”) hereby submits its Initial Brief in the captioned proceeding. The MPUC agrees with the position of
Petitioner NSTAR Electric & Gas Corporation (“NSTAR”) that the Federal
Energy Regulatory Commission (“FERC” or “Commission”) has unlawfully given
retroactive effect to unfiled rate agreements between certain power producers
and ISO New England, Inc. FERC’s orders have resulted in more than $10 million
in added power costs to consumers in Maine.
The MPUC submits this separate Intervenor Brief to elaborate on one key
issue, namely, FERC’s lack of authority
to give retroactive effect to unfiled rates where customers did not otherwise
have notice of the rate to be charged and to underscore that FERC cannot
delegate to ISO New England Inc. (“ISO-NE”) its authority under the Federal Power
Act to approve just and reasonable rates.
The MPUC concurs in the Statement of the Issues set forth in the Initial Brief of NSTAR.
All applicable statutes and regulations are contained in the addendum to the Initial Brief of NSTAR.
STATEMENT OF THE CASE AND STATEMENT OF THE FACTS
The MPUC concurs in the Statement of the Case and Facts set forth in the Initial Brief of NSTAR.
The Commission found that agreements (“Mitigation Agreements”) entered into between ISO New England Inc. (“ISO-NE”) and owners of certain electric generators pursuant to Rule 17.3 of the New England Power Pool (“NEPOOL”) Market Rules must be filed with the Commission pursuant to Section 205(d) of the Federal Power Act (“FPA”), 16 U.S.C. § 824d(d). The necessary implication of FERC’s ruling was that the existing (unfiled) Mitigation Agreements contained “rates and charges” required to be just and reasonable under the FPA and, thus, should have been filed with the Commission. Before the Mitigation Agreements were filed with FERC, the rates in those Agreements could not be legally charged, and rates charged in excess of the filed rates must be refunded to consumers.
FERC’s effort to sidestep this straightforward application of the filed rate doctrine is based entirely on its purported authority to waive the sixty-day notice requirement set out in Section 205(d) of the FPA. This Court has made clear, however, that under the filed rate doctrine FERC may not use its Section 205(d) authority to waive notice of rate filings to give effect to a rate before the rate is filed where, as here, those customers paying the rate were not on notice of it. Because the sole rationale on which FERC relies to deny refunds in this case cannot be supported, the Court should vacate the challenged orders and require that FERC comply with the requirements of the Federal Power Act by ordering ISO-NE to issue refunds for rates unlawfully collected in excess of the filed rates.
FERC’s error in relying on its “waiver authority” to give effect to a rate before the rate is filed is compounded by its failure to evaluate the justness and reasonableness of the rates in the mitigation agreement. In this regard, FERC has the sole authority and obligation to ensure just and reasonable rates and cannot delegate that core function to ISO-NE as it has done in this case.
In its October 26, 2001 Order, FERC granted a request for clarification filed by NSTAR and ruled that Mitigation Agreements must be filed with the Commission pursuant to Section 205 of the FPA. Mirant Americas Energy Marketing, L.P., 97 FERC (CCH) ¶ 61,108 at p. 61,556 (2001). The Commission later confirmed this conclusion in its December 21, 2001 Order. Mirant Americas Energy Marketing, L.P., 97 FERC (CCH) ¶ 61,360 (2001). In both orders, FERC announced that its finding was in the public interest “because it protects consumers by ensuring that all jurisdictional contracts are filed with the Commission.” See Mirant Americas, 97 FERC (CCH) at p. 61,555 and Mirant Americas, 97 FERC (CCH) at p. 62,663.
The necessary implication of the Commission’s ruling was that the Mitigation Agreements, once filed, would constitute the filed rate for sales of energy under NEPOOL Market Rule 17.3.2.2 other than those sales for which the prices set forth in Tables 1 and 2 of Market Rule 17 were applicable. A further implication of the Commission’s conclusion was that the Mitigation Agreements that established the rates and charges for past power sales should have been – but were not – filed with the Commission. See 16 U.S.C. § 824d. As NSTAR explains, because these rates were not filed with the Commission, they could not be legally charged, and rates charged in excess of the filed rate (i.e., the Table 1 and Table 2 prices) must be refunded to consumers.
The Commission’s sole rationale
for departing from this straightforward application of the filed rate doctrine
was a terse statement in the October 26 Order that, “pursuant to Central Hudson, we will grant ISO-NE a waiver of the 60-day notice
requirement.” Mirant Americas, 97 FERC (CCH) at p. 61,556 (citing Central Hudson Gas and Electric Corp., 60 FERC ¶ 61,106, reh’g denied, 61 FERC ¶ 61,089 (1992)) (footnote omitted); see also Mirant Americas, 97 FERC (CCH)
at p. 62,666 (noting
simply that “refunds will not be required with respect to mitigation agreements
. . . because the Commission granted waiver of the prior notice requirement in
the October 26 Order”). The
Commission’s orders must be vacated because, as discussed below, the Commission
lacked the authority under the FPA to allow rates to become effective prior to
the filing of the rates where the affected parties did not have prior notice of
the rate change. Specifically, the
Commission erred in relying on Central
Hudson Gas and Electric Corp., 60 FERC ¶ 61,106, reh’g denied, 61 FERC ¶ 61,089 (1992) for the authority to allow
the Mitigation Agreement rates to go into effect prior to the filing of the
rates. The Commission failed to explain
how the facts of this case warrant waiver under Central Hudson. Of
even greater significance, however, FERC simply has no authority to waive the
notice requirement, whether or not it finds good cause, if waiver would give
effect to a rate prior to the date by which affected customers had received
notice.
The Commission has failed to demonstrate how the facts of this case justify a waiver under the policy set forth in Central Hudson. Indeed the Commission’s grant of a waiver appears inconsistent with the waiver policy set forth in Central Hudson:
We will generally grant waiver of the 60-day prior notice requirement in the following instances: (1) uncontested filings that do not change rates—such as notices of cancellation when the contract expires by its own terms and the customer does not desire an extension, changes in delivery points, and changes in non-rate terms; and (2) filings that reduce rates and charges—such as rate decreases or new services that provide the customer of a utility with an opportunity to reduce its purchases of other, more expensive service from the same utility.
* * *
We will also generally grant waiver of the 60-day prior notice requirement for filings that increase rates when the rate change and the effective date are prescribed by contract, such as annual rate revisions required by contract to become effective on a date specified in the contract, or a new service filed to comply with requirements of an accepted settlement if the settlement specified the effective date. In these instances, there is a contractual commitment as to the effective date which the Commission has already accepted.
* * *
On the other hand, absent a strong showing of good cause, we will deny requests for waiver of notice of rate increases that do not implement a contract requirement, such as increases in requirements, coordination or transmission rates.
* * *
Lastly, we address filings that provide for new service that is not pursuant to an accepted contract or settlement. When considering requests for waiver related to the provision of new service, we must balance the requirement that utilities promptly file their rates as embodied in the Federal Power Act and the need of utilities to transact business on short notice. Accordingly, we will grant waiver of notice if good cause is shown and the agreement is filed with the Commission prior to the commencement of service. We will continue to determine whether an agreement is filed prior to the commencement of service based on the original filing date (unless a filing is a patent nullity).
Central Hudson, 60 FERC at 61,338-61,339 (emphasis added).
Even if FERC had shown how the facts of this case warranted application of its waiver policy under Central Hudson, which as NSTAR points out, FERC failed to do, the case law in this circuit is clear. FERC simply has no authority to waive the notice requirement, whether or not it finds good cause, if waiver would give effect to a rate prior to the date by which affected customers had received notice of the rate change. Under the facts of this case, the Commission was without the authority to allow the Mitigation Agreement rates to become effective prior to filing because of the lack of notice.
While the Commission can, for good cause, grant non-consensual waivers to give effect to a filing on less than sixty days’ notice, 16 U.S.C. § 824d(d), it cannot give filings an effective date prior to the date of the filing where affected parties have no notice of the new rate. Columbia Gas Transmission Corp. v. FERC, 895 F.2d 791, 796 (D.C. Cir.), cert. denied, 490 U.S. 907 (1990). The Commission can never give a rate retroactive effect (except in exercising its refund authority under Section 205 of the FPA or Section 4 of the Natural Gas Act (“NGA”)). As this Court has explained, “[r]etroactive changes in rates violate the filed rate doctrine, by allowing the collection of rates other than the ones that were on file at the time of purchase, and, as a general rule, are not authorized by the Natural Gas Act.” East Tennessee Natural Gas Co. v. FERC, 863 F.2d 932, 941 (D.C. Cir. 1988) (citations omitted).[1] “The only statutory exception to the rule prohibiting retroactive rate changes,” the Court added, “arises in order to accommodate the realities of administrative delay. When a pipeline proposes rate changes under § 4, the Commission is authorized by the Act to suspend the rates for five months pending administrative review.” Id. at 942.
While this Court has found in certain limited circumstances that a rate may take effect prior to the date of its filing at FERC, the rate must still take effect prospectively from the date affected parties receive notice. In City of Piqua v. FERC, 610 F.2d 950 (D.C. Cir. 1979), the Court held that the Commission could use its authority to waive the notice requirements under Section 205(d) of the FPA to allow a rate increase to become effective prior to the date of filing where the parties to the contract had agreed on new rate schedules and on the effective date for the new contract. See City of Piqua, 610 F.2d at 954. The Court acknowledged the bar on retroactive ratemaking, but concluded that “[i]n this case, two parties agreed on new rate schedules and on the effective date for the new contract. The negotiated rate change was not retroactive; it was prospective from the date of the contract.” Id. at 954.
In Columbia Gas Transmission Corp., 895 F.2d at 796, the Court elaborated that a key aspect of the rates at issue in City of Piqua was that “because of pre-existing agreements between the parties and the notice that went automatically with them, those rates were not in fact retroactive.” (Emphasis added). This Court explained
Notice does not relieve the Commission from the prohibition against retroactive ratemaking. Instead, it changes what would be purely retroactive ratemaking into a functionally prospective process by placing the relevant audience on notice at the outset that the rates being promulgated are provisional only and subject to later revision. This in no way dilutes the general rule that once a rate is in place with ostensibly full legal effect and is not made provisional, it can then be changed only prospectively.
Id. (emphasis added).
Thus, in Columbia, the Court rejected the Commission’s assertion that for good cause it could waive the filed rate doctrine and found that the Commission had failed to provide adequate notice to the purchasers that the price they would be paying for a given period would be subject to adjustment. The Court unequivocally concluded that where adequate notice of the rate change to the affected parties is lacking, the Commission cannot use its waiver authority to give retroactive effect to unfiled rates, for whatever cause. See Columbia Gas Transmission Corp. v. FERC, 895 F.2d at 795-97. The clear rule of these cases is that the Commission’s waiver authority to allow rates to become effective prior to filing turns on whether the purchasers had notice of the rate revision.[2]
Here, there was no evidence, and FERC made no finding, that the purchasers of the energy sold by suppliers pursuant to the Mitigation Agreements were given notice of the revised rates that they would be charged or an opportunity to contest these rates. While Market Rule 17.3.2.2 refers to generating resources having “special contractual arrangements to ensure their availability when needed to support system reliability and security,” purchasers received no notice of such agreements, let alone notice of the rates, terms and conditions of the energy sales made under the Agreements. Quite the contrary, ISO-NE declared in its September 25, 2001 Answer to NSTAR’s clarification request that “MRP 17 does not require the filing, or even the disclosure, of the results of the ISO’s negotiations of bid mitigation agreements.” See Mirant Americas Energy Marketing, L.P., Docket No. EL01-93-000, “Answer of ISO New England, Inc. to Request for Expedited Clarification” at 2 (September 25, 2001) R.25, J.A. _____ (emphasis added). As NSTAR avers, ISO-NE’s policy of not disclosing Mitigation Agreements led parties to assume that no such contracts existed. See NSTAR Initial Brief at 7. Moreover, as NSTAR notes, ISO-NE continued to pay rates contained in certain of the Agreements even though the Agreements had expired, calling into question whether there could even be any basis for the rate, whether filed or not. See NSTAR Initial Brief at 24-25 (citing Compliance Filing of ISO New England Inc., Docket No. EL01-93-005 (February 25, 2002)).
While ISO-NE knew and agreed to the alternate rates, it was not the real party in interest. See, e.g., NRG Power Marketing, Inc. v. New York Ind. System Operator, Inc., 91 FERC ¶ 61,346 at p. 62,165 (2000) (explaining that the New York ISO “acts as an administrator of the spot energy market. In this role, it neither purchases nor sells energy. It facilitates the sale of energy by calculating market clearing energy prices consistent with the market rules and the bids received from buyers and sellers.”). The real purchasers are the market participants that paid the increased rates through “uplift” charges that may well be higher than was justified. See NSTAR Initial Brief at 27-28. These purchasers did not have notice or an opportunity to contest the rates they would be required to pay. Thus, the filed rate doctrine prohibits prices specified in the Mitigation Agreements from becoming effective until they are filed. Accordingly, the Commission erred in concluding that it could give retroactive effect to rates and dispense with refunds by “waiving” the 60-day notice requirement under Section 205(d) of the FPA.
The Commission compounded its error of trying to waive the notice mandated by the FPA by failing to perform its statutory obligation to ensure that the rates in the Mitigation Agreements are just and reasonable. See NSTAR Initial Brief at 32-44. FERC shirked this duty in the instant case by simply pointing (in a later order that is not in the record) to the NEPOOL Market Rules, which, as noted above, permit ISO-NE to enter into Mitigation Agreements. See Mirant Americas Energy Marketing, L.P., 99 FERC (CCH) ¶ 61,003 at p. 61,019 (2002). FERC’s response is equivalent to a claim that it has delegated to ISO-NE its authority to ensure just and reasonable rates, and, as NSTAR cogently argues, the Commission has no authority to delegate that responsibility to private parties. See NSTAR Initial Brief at 41-44.[3]
Based on the foregoing, the Court should grant NSTAR’s petition for review, vacate the challenged orders and require that FERC comply with the requirements of the Federal Power Act by ordering ISO-NE to issue refunds for rates unlawfully collected in excess of the filed rates.
Respectfully submitted,
Lisa
Fink State
of Maine Public Utilities Commission 242
State Street 18
State House Station Augusta,
ME 04333-0018 (207)
287-1391 (phone) DATED:
November 26, 2002 |
_____________________________ Harvey
L. Reiter John
E. McCaffrey Stinson Morrison Hecker llp 1150
18th Street, N.W., Suite 800 Washington,
DC 20036 (202)
785-9100 Counsel for Maine Public Utilities Commission |
In accordance with Rule 32(a)(7)(C) of the Federal Rules of Appellate
Procedure and D.C. Circuit Rule 32(a)(3)(C), I hereby certify that the
foregoing Initial Brief of Intervenor Maine Public Utilities Commission
contains 3,094 words (including headings, citations and footnotes).
Respectfully submitted,
__________________________________
Harvey L. Reiter
Stinson
Morrison Hecker llp
1150 18th Street,
N.W. Suite 800
Washington, DC 20036
(202) 785-9100
Counsel for Maine Public
Utilities Commission
CERTIFICATE OF SERVICE
I hereby certify that I have this day
served a copy of the foregoing document via first-class United States Mail on
all parties to these proceedings, as listed below.
Dated at Washington, D.C., this 26th
day of November, 2002.
|
___________________________ |
|
Harvey
L. Reiter Stinson Morrison Hecker llp 1150
18th Street, N.W. Suite
800 Washington,
DC 20036 (202)
785-9100 (phone) (202)
785-9163 (fax) |
Federal Energy Regulatory Commission Richard P. Bress
Solicitor of the Federal Energy Regulatory Latham & Watkins
Commission 555 Eleventh Street, N.W.
Attn: Lona T. Perry Suite 1000
888 First Street, N.E. Washington, DC 20004-1304
Washington, DC 20426
John N. Estes III Howard Haswell Shafferman
Skadden, Arps, Slate, Meagher & Flom LLP Ballard Spahr Andrews & Ingersoll
1440 New York Avenue, N.W. 601 Thirteenth Street, N.W.
Washington, DC 20005-2111 Suite 1000 South
Washington, DC 20005-3807
Stephen L. Teichler Joseph Edward Stubbs
Duane Morris LLP Steptoe & Johnson
1667 K Street, N.W. 1330 Connecticut Avenue, N.W.
Suite 700 Washington, DC 20036-1795
Washington, DC 20006
Frederic Lee Klein Robert Y. Hirasuna
Northeast Utilities Service Company Leonard, Street & Deinard
107 Selden Street 1701 Pennsylvania Avenue, N.W.
Berlin, CT 06037 Suite 1045
WDCDOCS
51268v1
Washington,
DC 20002
[1] The Supreme Court has noted that cases analyzing the equivalent provisions, including notice provisions, of the FPA and NGA may be cited interchangeably. Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 571, 577 (1981).
[2] FERC followed this Court’s holding in Texas Gas Transmission Corporation, 56 FERC ¶ 61,409 (1991) (affirming on rehearing that allowing utility’s proposed rates to be placed into effect as of a date prior to the filing of the rates would violate the filed rate doctrine and finding that the Commission had not provided notice that the rates might be changed retroactively.)
[3] NSTAR’s brief refers to ISO-NE as a “participant” in the New England energy markets (NSTAR Br. at 32-34), but it is more accurately characterized as an independent operator of those markets. MPUC wholly agrees with NSTAR’s central contention, however, that FERC cannot delegate its core responsibility to determine the reasonableness of jurisdictional rates to any private party, even to an independent entity such as the ISO.