Veranda Street Bridge Replacement Project Schedule

The Veranda Street Bridge Project is currently in design. Following is a summary of the project schedule.

Project Summary

Project Schedule Summary.

Click on the image above to view the full size.

Design

December 2017 – Alternatives Analysis Study Completed

December 2018 – Draft Preliminary Design Report Completed

April 30, 2019 – Community Design Workshop

Spring 2019 – Formal Public Meeting

January 2020 – Final Design Complete / Project Advertisement for Construction

Construction

April 2020 to November 2021 - Bridge and Roadway Construction Start

April 2021 - Anticipated Roadway Closure and Bridge Lateral Slide