May 2023

Sargent has continued to work throughout the winter. They currently have closed Clewleyville Road and Eastern Avenue. Excavation has been removed from both of these roads and bridge abutment footers have been started on both. Sargent has also begun installing four box culverts between Levenseller Road and the Route 9 end of the project. T Buck has worked on the Clewleyville Road Bridge to include placing concrete for both abutment footers and abutment 1 breastwall and east wingwall section 2 and they have also placed concrete for abutment 2 at the Eastern Avenue Bridge and have begun form work for abutment 1. Heath Hathaway Blasting has continued drilling and blasting.