Hydropower Projects in Active Consultation or Pending at FERC for Licensing Decision Sorted by River Basin

(Updated February 7, 2008 )

Clicking the FERC project number will take you to FERC's e-libary page where you can enter the project number and search for documents related to that project. You must enter the number in the format "p-xxxx"

Androscoggin River Basin

Gulf Island-Deer Rips

FERC No. P-2283
Androscoggin River Application for New License filed 12/10/1991; pending for FERC action.
1/7/93-State Motion to Intervene filed
Original license expired 12/31/1993; project currently operating under annual license.
Final EIS issued by FERC July 1996.
DEP issued WQC 09/21/2005; appeals pending.

Corriveau Hydro

FERC No. P-12629
Swift River
(Formerly Thurston Mill) Application for exemption from licensing filed 12/07/2005; pending for FERC action.

12/2/05 Filed with DEP for MWDCA and 401 WQCert. On May 5, 2006 the Maine Department of Environmental Projection issued a water quality certification for the project.

Notice of application filing issued by FERC 12/27/2005, with 02/06/2006 deadline for filing of additional study requests.
DEP action on MWDCA permit and WQC pending.

Notice of application accepted for filing and ready for environmental analysis issued by FERC 03/21/2006, with 05/19/2006 deadline for filing of motions to intervene and protests, comments, terms and conditions, recommendations, and prescriptions.

On October 24, 2006 FERC issued an Order Granting Exemption from Licensing to the Corriveau Project on the Swift River in Mexico, Maine. The project is subject to standard FERC terms and conditions of Exemption from Licensing and Mandatory section 30 (c) conditions filed by the U.S. Department of Interior on May 15, 2006 and Mandatory section 30 (c) conditions submitted by the Maine Department of Inland Fisheries and Wildlife in a letter dated Oct.27, 2005 and filed with the Commission on December 7, 2005 as part of the application.

 

Kennebec River Basin

Sandy River

FERC No. P-11433
Sandy River Application for surrender of license and dam removal filed 10/03/2005; pending for FERC action.

Notice of application filing issued by FERC 10/11/2005, with 30 day deadline. for filing of comments, protests, or motions to intervene.
11/10/05 - State Motion to Intervene filed.
DEP action on MWDCA permit and WQC pending.

 

Penobscot River Basin

Howland

FERC No. P-2721
Piscataquis River Application for New License filed 09/28/1998; pending for FERC action
3/22/99 FERC Order Amending License.
Original license expired 09/30/2000; project currently operating under annual license.
8/9/2000- State Motion to Intervene filed
Processing of application currently on hold pending implementation of July 2004 Lower Penobscot River Multiparty Settlement Agreement.

DEP action on Water Quality Certification pending.

Great Works

FERC No. P-2312
Penobscot River Application for New License filed 03/31/2000; pending for FERC action.
Original license expired 03/31/2002; project currently operating under annual license.
7/22/04 - State Motion to Intervene filed
Processing of application currently on hold pending implementation of July 2004 Lower Penobscot River Multiparty Settlement Agreement.
DEP Action on WQCert. Pending.

 

Presumpscot River Basin

Eel Weir

FERC No. P-2984
Presumpscot River Application for New License filed 03/29/2002; pending for FERC action.
9/26/02 - State Motion to Intervene filed
Original license expired 03/31/2004; project currently operating under annual license.
Final EA issued by FERC November 2005.
DEP action on WQC pending.

 

Saco River Basin

Bar Mills

FERC No. P-2194
Saco River Application for New License filed 06/30/2003; pending for FERC action.
4/22/04 - State Motion to Intervene filed
Original license expired 06/30/2005; project currently operating under annual license issued by FERC 7/7/05.

Notice of availability of EA issued by FERC 09/12/2005, with 30 day comment deadline.

10(j) dispute resolution meeting held 01/25/2006.

DEP action on WQC pending.

 

St. Croix River Basin

Forest City Storage

FERC No. P-2660
St. Croix River Original license expired 08/31/2000; project currently operating under annual license.

Orders issued by FERC in 1996 and 2000 finding that the project was subject to FERC’s licensing jurisdiction. Appeals subsequently denied by the D.C. Circuit Court of Appeals.
8/21/97-State Motion to Intervene filed on Petition for Declaratory Order
Notice soliciting the filing of applications for new license for the project issued by FERC 12/21/2005, with 90 day deadline for filing of notice of intent and pre-application document. (3/20/06)

Notice of Intent to file an application for a new license filed with FERC 03/20/2006, with 04/19/2006 deadline for filing of comments on request to use traditional licensing process. Joint consultation meeting/site visit to be held before mid-July.

West Branch Storage

FERC No. P-2618
St. Croix River Original license expired 09/30/2000; project currently operating under annual license.
Orders issued by FERC in 1996 and 2000 finding that the project was subject to FERC’s licensing jurisdiction. Appeals subsequently denied by the D.C. Circuit Court of Appeals.
6/24/97-State Motion to Intervene filed
Notice soliciting the filing of applications for new license for the project issued by FERC 12/21/2005, with 90 day deadline for filing of notice of intent and pre-application document.

Notice of Intent to file an application for a new license filed with FERC 03/20/2006, with 04/19/2006 deadline for filing of comments on request to use traditional licensing process. Joint consultation meeting/site visit to be held before mid-July.

 

A corporative effort by the Maine State Planning, Department of Environmental Protection, Inland Fisheries and Wildlife and the Department of Marine Resources.


 

Glossary for acronyms used used in this document.

EA: Environmental Assessment

EIS: Environmental Impact Statement

FERC: Federal Energy Regultory Commission

MWDCA: Maine Waterway Development and Conservation Act

WQC: Water Quality Certification