2006 Construction Season Task Chart

 

DOT is currently working on 7 tasks for the 2006 Construction Season.  DOT is also working on two critical path tasks for the MSCommNet Project.  The tasks, status and expected completion dates are as follows:

 

Task

Scheduled Start Date

Scheduled

Finish Date

Actual

Finish

Date

2006 Construction Season

 

 

 

Improve Coverage for DPS in York

6/26/2006

9/1/2006

10/1/2006

Complete Cooper Hill Site

10/1/2006

12/1/2006

 

Project tasks for Ossipee Site

6/26/2006

7/1/2007

 

Project tasks for Cadillac Site

6/26/2006

7/1/2007

 

Project tasks for Granite Hill Site

6/26/2006

7/1/2007

 

Project tasks for Spruce Site

6/26/2006

7/1/2007

 

Clear Brush at designated sites

6/26/2006

TBD

 

MSCommNet Project Tasks:

 

 

 

Site Permitting

6/26/2006

TBD

 

Structural Analysis

6/26/2006

TBD