Skip Maine state header navigation
I. EXECUTIVE SUMMARY
Background and Major
Findings
On February 23, 2004, the Joint Standing Committee on
Utilities and Energy sent a letter to the Public Utilities Commission directing
the Commission to examine the practices of Maine’s transmission and distribution
(T&D) utilities that affect the safety and reliability of the electric
grid. This report presents the
Commission’s findings and recommendations.
In
most respects, the Commission found that the utilities are adequately operating
and maintaining the grid. In certain
respects, however, our examination revealed signs of potential shortcomings
that warrant further and more in-depth review.
In particular, certain aspects of Central Maine Power Company's (CMP's)
distribution system and operation and maintenance practices should be
examined. Unlike Bangor Hydro-Electric
Company (BHE) and Maine Public Service Company (MPS), CMP has for the last 10
years been operating within an Alternative Rate Plan (ARP)[1]
with specified performance incentives.
In addition, unlike BHE and MPS, CMP has not in recent years been
subject to a thorough review of its distribution O&M standards and
procedures.
While
CMP has done a good job meeting the ARP’s performance measures, there is a need
to determine the effectiveness of those measures in ensuring the maintenance of
an electric utility’s distribution plant.
Thus, an examination would not only shed light on CMP’s maintenance
practices but also might provide some indication of the efficacy of the
Commission’s performance standards.
Such an examination would be especially timely with CMP’s ARP expiring
in 2007. For these reasons, CMP and the
Commission have jointly agreed to have an independent review of CMP's
distribution system as well as of its distribution maintenance practices and
procedures.
The Reliability of the
Distribution and Local Transmission System
Two indicators
form the basis for measuring overall system reliability. SAIFI, or System Average Interruption
Frequency Index, measures average frequency of sustained interruptions and is a
good indicator of the condition of a utility’s plant and the quality of a
utility’s maintenance activities.
CAIDI, or Customer Average Interruption Duration Index, represents the
average time required to restore service and is a good indicator of the quality
of a utility’s response to outages.
SAIFI and CAIDI are measured on a company-wide average basis as part of
CMP's and BHE's ARPs. Under the terms
of their respective ARPs, both CMP and BHE are subject to financial penalties
should their annual SAIFI or CAIDI levels deteriorate and fall below
pre-established standards.[2] Because it is possible to obtain reasonable
indicators on this basis while performing poorly in specific areas,
particularly those that are less densely populated, the Commission reviewed
performance on the utilities’ worst performing circuits. In addition, because SAIFI and CAIDI
indicate current performance but cannot determine whether that performance will
prevail in the future, the Commission reviewed the utilities’ maintenance and
inspection programs, capital and maintenance spending, vegetation management
programs, and planning criteria.
The Commission found that CMP, and to a lesser extent
BHE, have focused on meeting company-wide average targets required by their
Alternative Rate Plans (ARPs) to the potential detriment of service in less
densely populated areas. The Commission
will continue to monitor the performance of BHE and CMP in these areas. We will also direct these utilities to
address this issue in the next round of ARP proceedings. In addition, the Commission will closely
monitor the utilities’ inspection programs, which were not, until recently, in
full compliance with the National Electric Safety Code (NESC).
Finally,
CMP and the Commission have agreed, based on the issues that have arisen out
of this study, that an additional
examination of CMP's distribution system should be conducted by an independent
consultant to review and assess CMP's current distribution plant as well as its
distribution maintenance practices and procedures.
Central Maine Power
Company (CMP) Findings
·
CMP’s planning, design
and operation of its transmission plant are consistent with sound utility
practices, allow CMP to detect problems that could degrade reliability, and are
compliant with New England Independent System Operator (ISO-NE) and Northeast
Power Coordinating Council (NPCC) requirements.
·
Capital and O&M
spending on transmission plant appear to be
reasonable.
·
Transmission vegetation
management procedures are consistent with sound utility practices and are
within NPCC and Federal Energy Regulatory Commission (FERC) recommendations.
·
CMP’s transmission
inspection program is consistent with sound utility practice and meets all
National Electric Safety Code (NESC), NPCC, and FERC requirements.
·
CMP’s company-wide
distribution CAIDI and SAIFI performances have increased in recent years. This may be due, in part, to better
reporting.
·
The Commission is
concerned that CMP’s worst performing distribution circuits are significantly
worse than company-wide performance and are located almost entirely within less
densely populated areas; that CMP has not reported these circuits in its annual
report to the Commission; and that service on these circuits may have
deteriorated in recent years.
·
The Commission is
concerned that outages have increased and the increases appear to occur in less
densely populated areas.
·
Capital and O&M
spending for distribution raise no concerns.
·
The Commission is concerned
that CMP’s distribution vegetation management procedures are primarily
reactive, targeting areas only after a service reliability problem exists.
·
For the past five
years, CMP’s distribution line inspection program has been informal, with no
tracking of areas that have been inspected or worked on to resolve problems as
a result of identified safety issues. The Commission believes that CMP's
program did not meet NESC requirements.
CMP has revised its program and the current program now appears to satisfy
NESC requirements. The Commission is concerned, however, that a substantial
time period will elapse before CMP can formally inspect all its circuits under
its new program.
·
Distribution plant age
has increased in recent years. This
raises concern when combined with the lack of an official inspection program
and flat spending on distribution maintenance.
·
CMP’s improvement
program raises concern because CMP does not track the capacity or safety margin
on its circuits. The Commission is
concerned that CMP improves circuits based primarily on contribution to
company-wide SAIFI and may be sacrificing service quality in less densely
populated areas.
In
its comments on the Commission's Draft Report, CMP stated its belief that its
past and current inspection procedures, vegetation management procedures, and
record-keeping practices are adequate, and that it has been addressing
reliability issues on its rural circuits.
However, to address the concerns of the Commission cited above, and to
resolve any misunderstandings concerning CMP's actual distribution practices
and procedures, the Commission and CMP have agreed to have a more extensive
study of CMP's distribution system conducted by an independent party. As part of this study, the condition of
CMP's plant will be assessed and CMP's distribution practices and procedures
will be reviewed.
Bangor Hydro-Electric
Company (BHE) Findings
·
BHE’s planning, design
and operation of its transmission plant are consistent with sound industry
practices, allow BHE to detect problems that could degrade reliability, and are
compliant with ISO-NE and NPCC requirements.
On its own initiative, BHE recently conducted a 10-year transmission
planning study and maintains clear documentation on its practices. BHE has proposed upgrades to certain
transmission lines that will improve reliability.
·
Capital and O&M
spending on transmission plant are reasonable.
·
Transmission vegetation
management procedures are reasonable.
·
BHE’s transmission
inspection and preventative maintenance programs are consistent with sound
utility practice and meet all NESC requirements.
·
BHE’s company-wide
distribution CAIDI and SAIFI performance have deteriorated steadily, which may
in part be due to better record keeping.
BHE’s worst performing distribution circuits show less disparity from
the company-wide average than do CMP’s, but their service quality performance
metrics have trended downward. This is
of concern and the Commission will monitor the trend.
·
The Commission is
concerned that outages have increased.
·
BHE recently improved
its distribution vegetation management procedures by increasing the amount of
area worked and decreasing costs.
·
Capital spending for
distribution has increased while maintenance expense has declined. It appears BHE has been able to achieve
these reductions at least in part, as a result of improved efficiencies.
·
Distribution plant age
remains steady and raises no concern at this time.
·
BHE recently submitted
a new comprehensive line inspection program,
which incorporates periodic testing and meets NESC requirements for
inspection and data retention.
In
summary, the Commission found some areas of concern that we will continue to
monitor, although in many respects, BHE management has begun to resolve these
on its own. BHE has decreased costs
while attempting to improve service quality.
Although BHE’s indicators have deteriorated, improved record keeping may
account for the trend. BHE has
implemented improvements in a variety of areas, and has recently submitted a
revised comprehensive inspection program.
Maine Public Service
Company (MPS) Findings
·
MPS’s capital and
O&M spending on transmission plant are reasonable.
·
MPS’s transmission
inspection program is reasonable and meets NESC requirements.
·
MPS’s transmission
vegetation management program is reasonable. However, there are locations in
which MPS cannot obtain easements which may be resulting in tree-related
reliability problems. MPS should more
actively pursue securing easements.
·
MPS's company-wide distribution
CAIDI and SAIFI performances compare favorably with those of CMP and BHE, but
they have recently deteriorated. MPS
should monitor this situation.
·
MPS’s worst performing
distribution circuits show less disparity from the company-wide average than do
CMP’s or BHE’s, indicating that it is not focusing on maintaining reliability
in populated areas at the expense of less populated areas.
·
MPS’s weather-related
outages have increased steadily in recent years. This is likely a result of MPS’s prior vegetation management
program which MPS has revised in response to an internal investigation.
·
MPS has redesigned its
vegetation management program. While it
appears reasonable, MPS’s records do not allow assessment of
cost-effectiveness.
·
Capital spending for
distribution has increased to catch up on deferred capital improvements. Distribution pole age is high, which raises
concern about the condition of distribution plant. O&M expenses are reasonable.
·
MPS recently improved
its line inspection program. The new
program meets NESC requirements and will help MPS improve reliability and
address concerns regarding plant condition.
·
On its own initiative,
MPS recently retained a firm to assess the condition and performance of its
system. MPS has addressed immediate
safety issues and has adopted many of the recommendations regarding grid
O&M.
In
summary, as a result of a consultant’s inspection, MPS recently implemented
improvements in a variety of areas that should address concerns that the
Commission encountered during this study.
In other regards, MPS’s practices are reasonable.
Eastern Maine Electric
Cooperative (EMEC) Findings
·
The Rural Utility
Service (RUS) regularly evaluates EMEC’s conformance to RUS standards. Most recently, RUS rated EMEC as
satisfactory in all areas except service interruptions, and that category
received a rating that was an improvement over the previous rating. Considering EMEC’s rural nature, no major
concerns exist regarding its grid management.
·
EMEC’s distribution circuit
inspections do not fully comply with the NESC and should be revised
accordingly. EMEC could improve its
vegetation management program and should examine the causes of its substation
outages. Finally, EMEC should be
proactive in MPS’s transmission planning as it regards the line supplying
EMEC’s power.
The Reliability of the
Bulk Power Transmission Grid Administered by
ISO-NE
The
above sections related to the local T&D systems in Maine. Because Maine is part of a much larger
electric grid, we also examined the entities and systems that affect the
reliability of the interstate, high voltage, "bulk power" system.
The New
England Independent System Operator (ISO-NE) is primarily responsible for the
operation of the bulk power supply system in New England. Recently in New England, tight supply
conditions have occurred during peak summer hours. In winter months, the price and availability of natural gas
impacts the price and availability of electricity because a significant number
of electricity generators depend upon natural gas for fuel production. Maine has more in-state generating capacity
than necessary to meet its load.
Coupled with transmission limits on exports, this excess capacity places
Maine in a good position in terms of reliability and price. That said, even in Maine, electricity prices
are very much affected by fossil fuel prices.
ISO-NE
communicates with all relevant local entities, including government and
emergency response agencies, on a regular schedule and more often when the
system is stressed. In addition,
operating procedures are in place to address shortages.
Recent
bulk power events include:
·
Northeast blackout
of August 2003. New England and the Maritimes isolated from
the rest of the system, but voltages were depressed in some locations and one
Maine customer disconnected from the grid.
NEPOOL’s system design, communications systems, and ISO-NE procedures
helped to avoid further problems.
Actions taken nationally in response to the blackout include:
o NERC
accelerated adoption of a comprehensive set of measurable reliability
standards. However, the standards
remain voluntary and federal legislation is needed to make compliance
mandatory.
o NERC’s
readiness audit team examined whether each control area has adequate
reliability features. It determined
that ISO-NE is adequate overall and emphasizes reliability as a high priority.
·
New England cold
snap of January 2004. A unique set of circumstances during a cold snap in
January, including curtailed generation imports, a shortage of natural gas for
in-state generating facilities, and the decision of some generating facilities
to resell their gas supply into the high-price market rather than use it to
generate electricity, placed Maine at an unusually high risk of electricity
supply shortage. Government and
emergency agencies communicated throughout this period. The cold snap highlighted New England’s
vulnerability caused by its dependence on natural gas. Relevant companies and agencies subsequently
developed near-term responses to this situation, including a new ISO-NE
coordinating procedure, ISO/gas industry operating committees to address
electricity-natural gas issues, and further ongoing studies of the interplay
between gas and electricity generation.
Because
of electric restructuring, the region now depends on market forces to assure
that sufficient generating facilities are constructed to meet future regional
electricity requirements. Recently, new
gas-fired generation has provided excess capacity in most areas of New
England. To provide for the future,
FERC is conducting a long, complex proceeding to determine whether and how a
Locational Installed Capacity Market (LICAP) should be implemented. The Maine PUC has been active in the
proceeding, and is concerned that the ISO-NE proposal will be expensive and
ineffectual.
The Physical and Cyber
Security of Critical Grid Infrastructure
The utility industry, through various industry
organizations, has identified best practices for the security and protection of
critical grid infrastructure.
Compliance is voluntary.
However, in recent years, the industry has strengthened the guidelines
and reporting to federal agencies and state regulators when repeated violations
occur.
Increasing
reliance on computer-based control systems has produced challenges associated
with cyber security. NERC has issued a
high-priority security standard that ISO-NE and Maine T&D utilities are
working to implement.
As part of the
State’s homeland security planning efforts, state emergency organizations and
the PUC are conducting a review of utility security improvements implemented
since September 2001. All participants
discuss and resolve potential issues.
Both security and communication related to security are improving as a
result.
Ongoing challenges include the high visibility of utility
infrastructure, increased use of electronic control technologies, the
interdependence among utility services, and the need to minimize the release of
sensitive information. Overall, Maine’s
T&D utilities have improved their security measures, and utilities and
state emergency agencies are continuing to evaluate security needs as they
evolve.
A. Legislative
Background
During its 2003 session,
the Legislature passed an Act to Encourage Energy Efficiency and Security.[3] The Act directed the Public Utilities
Commission (Commission) to investigate regulatory mechanisms and rate designs
that provide incentives for transmission and distribution (T&D) utilities
to promote energy efficiency and the security and robustness of the electric
grid.[4] As required by the Act, the Commission
submitted a report to the Joint Standing Committee on Utilities and Energy (the
U&E Committee) on February 1, 2004.
In its Report to the U&E Committee, the Commission stated that it
believed that ensuring adequate service reliability through objective service
quality metrics backed by meaningful penalties, incorporated as part of a
utility’s alternative rate plan (ARP), along with the Commission’s ability to
use its traditional tools to ensure adequate service, was working well. Accordingly, the Commission recommended that
no legislative changes be made in this area at such time. The Commission stated that it would continue
to monitor Maine’s T&D utilities’ service quality performance and refine
the standards and penalty mechanisms in ways that improve their operation.
During the presentation
of the Commission’s Report, the U&E Committee indicated that it was
interested in the continued examination of certain issues associated with grid
reliability and security. In a letter
to the Commission dated February 23, 2004, the U&E Committee requested that
as part of this follow-up examination, the Commission specifically:
1. quantify the
safety margin of the grid system, including such indicators as maintenance
activity, and to analyze how the margin may have changed over time,
particularly as the result of alternative rate plans and restructuring;
2. assess the
adequacy of grid security in light of the events of 9/11 and the blackout of
2003;
3. examine
issues of grid adequacy in remote areas, e.g., Washington County, including
looping issues; and
4. review relevant
information including information from transmission and distribution utilities
and reports on the blackout of 2003.
The
U&E Committee requested that the Commission submit a report with its
findings and recommendations during the next legislative session.
B. Description of the Commission’s
Investigation
On
April 29, 2004, the Commission initiated an inquiry for the purpose of
conducting the study requested by the Commitee.[5] Because the Commission anticipated that it
would need to request information from the state’s three investor-owned
utilities (IOUs), Central Maine Power Company (CMP), Bangor Hydro-Electric
Company (BHE) and Maine Public Service Company (MPS), they were considered to
be parties to the process from the outset.
In addition, the Commission included Eastern Maine Electric Cooperative
(EMEC), a consumer-owned utility (COU), as a participant
because EMEC owns and operates facilities that provide service to a significant
portion of Washington County, an area of the state which the Committee
specifically requested the Commission examine.[6] The Commission also invited the
New England Independent System Operator (ISO-NE) to participate in the study
process and noted that it was likely that the Commission would be seeking input
and information from the ISO-NE during the course of the study. To assist our staff in conducting the study,
the Commission retained the services of Liberty Consulting Group (Liberty),
which has extensive experience in reviewing and auditing the reliability of
electric T&D services.
Following the
initiation of the docket, the Commission’s staff and consultants issued written
data requests to CMP, BHE, MPS and EMEC seeking information from each of the
utilities concerning the utilities’ processes, planning, performance data,
maintenance activities and investments, as they related to the areas of
investigation. Following receipt of the
utilities’ responses, the staff and consultants conducted interviews with
utility personnel. To the extent that
utility personnel were unable to provide responses to questions during the
interviews, the staff requested that the utility provide the information in
writing. In addition to collecting
information from the subject utilities, the staff also interviewed ISO-NE
personnel and collected written information from ISO-NE as well as from the
FERC and the North American Reliability Council (NERC). The staff has also, independent of this
investigation, met on a regular basis with utility and law enforcement
personnel in the state concerning utilities’ preparedness against possible
terrorist attacks.
A draft of the
Commission's report was issued on March 28, 2005. Stakeholders were provided with an opportunity to comment on the
draft. BHE, MPS, CMP, ISO-NE and Art
Ray a former CMP employee, filed comments on the draft report. The comments are attached as Appendix
A. Based on the information collected
during the investigation, the advice and input of our consultants, and the
comments received, the Commission submits the following Report.
C. Scope of the Report
In
analyzing the areas requested to be investigated by the Committee, the
Commission has divided the request into three separate and fairly distinct
subjects:
1. the reliability of the distribution and
local transmission system;
2. the reliability of the bulk-power
transmission grid administered by ISO-NE; and
3. the security of critical grid
infrastructure.
Even with the
help of Liberty Consulting and the commitment of significant staff resources,
given the extremely broad scope of the project, the Commission necessarily
views the examination conducted here as a general review, somewhat akin to a
general physical examination by a treating physician. This general examination would then allow the Commission to
determine whether the grid is in basic good health; whether there are certain
signs or symptoms which warrant further investigation or examination; and
finally, whether certain conditions which were discovered during the general
examination, warranted immediate attention or correction. We believe that this Report makes those determinations.
For the most
part, the T&D utilities in the state are reasonably maintaining the grid
and there is a sufficient “safety margin” going forward. In certain instances, however, further
examination is warranted. The
Commission intends to initiate proceedings in the coming year to conduct these
follow-up examinations. In other
instances, we believe that certain conduct requires immediate attention and
correction and we will be taking the necessary steps in the coming months to
ensure that such deficiencies are corrected.
The Commission does not believe, however, that any legislative action is
required at this time.
The report of
the Commission's consultants is attached as Appendix B to this report. The Commission has reviewed the Liberty
Report and supports the conclusions and recommendations contained therein. This Report, provides the Commission's
conclusions, together with the Commission's findings and analysis which are in
addition to those contained in the Liberty Report. We have, to the greatest extent possible, tried to avoid
repeating the content of the Liberty Report.
Therefore, we recommend that the reader initially review the Liberty
Report before reading the Commission's findings.
Prior to providing the Commission’s findings
and recommendations, this Report provides a brief background on the regulatory
paradigm in Maine as it affects the subject areas of the study.
III. REGULATORY
PARADIGMS
A. Bulk Power System
The bulk electric power system that serves most of North
America consists of three grid networks – an interconnected network roughly
west of the Rockies, a second network serving most of Texas, and a third very
large network serving the rest of the United States and eastern Canada – with
limited ties between those networks.
Because the nation’s power grid is largely an interstate (and
international) system of interconnected networks, its oversight falls to the
federal government and the industry participants that own and operate the
largely privately-owned and operated system.
In addition, regional industry
councils set criteria and standards and have an oversight role in ensuring the
reliability of the grid. Adherence to
the rules and standards of these councils has historically been voluntary, an
issue of continuing concern. This
section of the Report describes the various oversight entities that most
directly affect Maine.
1. FERC
The Federal Energy Regulatory Commission (FERC) is a
federal agency that regulates the interstate transmission of electricity,
natural gas, and oil.[7] FERC also
regulates natural gas and hydropower projects. As part of those
responsibilities, FERC:
·
regulates the transmission and wholesale sale of electricity in
interstate commerce;
·
licenses and inspects
private, municipal, and state hydroelectric projects;
·
oversees environmental
matters related to natural gas and hydroelectricity projects and major
electricity policy initiatives;
·
regulates the
transmission and sale of natural gas for resale in interstate commerce;
·
approves the siting and abandonment of interstate natural gas
facilities, including pipelines, storage and liquefied natural gas;
·
regulates the transmission of oil by pipeline in interstate commerce;
and
·
administers accounting and financial reporting regulations and conduct
of regulated companies.
2. NERC
In
carrying out its responsibilities in the electric sector, FERC works closely
with the North American Electric Reliability Council (NERC). NERC is a
not-for-profit corporation whose mission is to ensure that the bulk electric
system in North America is reliable, adequate and secure. Formed in 1968 as a response to the 1965
northeast blackout, NERC has operated as a voluntary organization, relying on
reciprocity, peer pressure, and the mutual self-interest of all participants.[8]
In addition, NERC is involved in bulk power system security. The U.S. Department of Energy has designated NERC as the electricity sector’s information sharing and analysis center (ISAC) coordinator for critical infrastructure protection. NERC receives security data from electricity sector entities; analyzes the data with input from the Department of Homeland Security (DHS), other federal agencies, and other critical infrastructure sector ISACs; and disseminates threat indications, analyses, and warnings to sector entities.
NERC is composed of ten Regional Reliability Councils. The members of these councils come from all segments of the electric industry: investor-owned utilities; federal power agencies; rural electric cooperatives; state, municipal and provincial utilities; independent power producers; power marketers; and end-use customers.
The areas of responsibility of the ten Regional
Reliability Councils are shown on the following map.

3. NPCC
The Northeast Power Coordinating Council (NPCC) is the Regional Reliability Council for the northeastern United States and most of eastern Canada. NPCC sets reliability standards for the region and coordinates the design and operation of the bulk power supply system in Maine, New Hampshire, Vermont, Massachusetts, Rhode Island, Connecticut, New York, the Canadian Maritime Provinces, Québec, and Ontario.[9] NPCC reviews all bulk power system modifications proposed by regional entities to ensure that the integrity of the regional system is maintained.
4. ISO-NE and Maritimes
Within NPCC, five sub-regional control centers are responsible for the day-to-day operation and control of bulk power generation and transmission facilities in their areas, and related administration of the power markets in those areas. Most Maine consumers (i.e., those served by CMP and BHE) are interconnected with the New England bulk power system operated by ISO New England, Inc. (ISO-NE)[10], a not-for-profit corporation created in 1997. ISO-NE also oversees and administers the New England wholesale market and, in addition, acts as the regional reliability coordinator for the New England states and the Canadian provinces of New Brunswick, Nova Scotia, and Prince Edward Island.
Northeastern Maine (i.e., the area served by MPS and EMEC) is interconnected with the Canadian Maritimes system and is connected to the rest of Maine and New England only by transmission through New Brunswick. The Northern Maine ISA, Inc. (NMISA), headquartered in Bangor, administers the market system that serves these consumers.
Regional control area operators and administrators, including ISO-NE and the Northern Maine ISA, are regulated by FERC. The Maine PUC participates on ISO-NE committees, monitors ISO-NE developments both directly and through the New England Conference of Public Utilities Commissioners (NECPUC), and often files comments before FERC on ISO-NE proposals and other filings related to the New England wholesale electric markets.
Within
ISO-NE, there are currently four satellite local control centers (LCC's) that
monitor and perform hands-on transmission line switching functions for their
portion of the system: 1) the
Connecticut Valley exchange (CONVEX); 2) Rhode Island, eastern Massachusetts,
and Vermont (REMVEC); 3) New Hampshire; and 4) Maine.[11] CMP operates the Maine satellite control
center for ISO-NE. ISO-NE requires its
system operators to maintain professional certification to meet NERC standards. NERC certification is not mandatory,
however, for operators at the satellites.
ISO-NE
also oversees bulk system maintenance activities to ensure that adequate levels
of supply and transmission will be available.
Regional transmission operators are required to notify ISO-NE in advance
of any maintenance that may affect transmission facilities. If work is to be performed at a critical
transmission facility, the schedule is subject to approval by ISO-NE.
On
February 1, 2005, ISO-NE began operating as a Regional Transmission
Organization (RTO) under the jurisdiction of the FERC. As an RTO, ISO-NE assumes complete
responsibility for the day-to-day operations of the New England transmission
grids and has authority to direct the construction of new transmission plant as
needed. The transmission owners, such
as CMP and BHE, will continue to own, physically operate, and maintain the
transmission facilities, and be paid for the transmission services they
provide.
ISO-NE
is also responsible for regional system planning and develops a comprehensive
needs assessment of the New England bulk power system. The 2004 regional system plan (RSP)
discusses the needs of the entire six-state region, including Maine. The RSP provides signals for market
solutions (e.g. generation, conservation, merchant transmission) to address
reliability concerns and identifies transmission projects as a backstop for
reliability in the event that market responses are not adequate. The RSP is reviewed annually through an open
and ongoing stakeholder process that includes participation from transmission
companies, state government representatives and other interested parties
through the Planning Advisory Committee (PAC).[12]
B. Restructuring in Maine
For the entire twentieth
century, Maine’s utilities were vertically integrated monopolies with respect
to all aspects of providing and delivering the electricity “product.” Because of their monopoly status, the Maine
Commission regulated all aspects of the retail transactions between Maine
utilities and their ratepayers.
On March 1, 2000,
Maine’s electric industry was restructured to provide Maine consumers with the
opportunity to purchase generation services from a competitive market (retail
access). As of that date, the
generation portion of electricity service was no longer subject to rate
regulation in Maine and, perhaps more noteworthy from a reliability
perspective, was no longer the responsibility of the regulated public
utility. Instead, decisions regarding
the construction of and prices charged for generation, now occur within a
competitive market.
As a result of restructuring, the bundled electricity “product”
has been separated into four parts: (1) the generation component; (2) the
transmission component; (3) the distribution delivery component; and (4) the
stranded cost component. The unbundling
of generation costs from utility rates has resulted in FERC asserting
jurisdiction over retail transmission rates.
Currently, CMP, BHE and MPS's transmission rates are reset annually by
FERC based on the prior year's transmission sales and transmission related
costs. While FERC clearly has asserted
jurisdiction over retail transmission rates, and previously had jurisdiction
over the bulk power transmission system, FERC has not, as of this date, clearly
asserted jurisdiction over local transmission systems and the jurisdiction over
reliability matters for this portion of the grid remains somewhat unclear.
C. Alternative Regulation in Maine
In late 1993, following a
series of rate increases resulting from a number of causes, including declining
sales brought on by a downturn in the economy, introduction of a new rate
design, and increases in utility costs above the rate of inflation, the
Commission concluded that it should consider setting CMP's rates through a rate
cap approach.[13] Under the rate cap approach, a utility's
rates are reset based on an external index over a multi-year period, rather
than the "cost-plus" methodology used under traditional rate of
return regulation. The Commission
ultimately approved an alternative rate plan for CMP in 1995.[14]
CMP’s first five-year
price‑cap plan (ARP I) reset CMP’s rates annually based on an external
index calculated by inflation minus a productivity offset, plus or minus
earnings outside a deadband and/or certain costs which qualified as mandated
costs. Because cost reductions in
excess of the indexed rate change would flow directly to the utility's bottom
line under an ARP, the Commission recognized that there was an enhanced
incentive, relative to traditional regulation, for a utility to cut costs,
including ways that could damage system reliability. To address this issue, ARP I included penalties of up to $3
million if CMP failed in any year to meet the standards set forth in the ARP’s Service
Quality Index (SQI).
ARP I’s SQI measured CMP’s
performance in five areas, of which two addressed reliability and three
concerned customer service. The
reliability indices included were the System Average Interruption Frequency
Index (SAIFI), which measures the average frequency of sustained interruptions
per customer over the year[15],
and the Customer Average Interruption Duration Index (CAIDI), which is the average time required to restore service
to the average customer per sustained interruption.[16]
In approving ARP I, the
Commission concluded that the specific service quality standards of the SQI,
with automatic penalties assessed if service deteriorated beyond baseline
levels, were superior to the traditional tools of penalizing the Company for
poor service through litigated proceedings.
In the Order approving CMP’s ARP I, however, the Commission clearly and
emphatically stated that the Commission's approval of an ARP did not place the
utility on “auto-pilot” and was not tantamount to deregulation:
No one should interpret
our adoption of the Stipulation as a willingness to abandon our central
regulatory task of ensuring that CMP’s customers receive adequate service at
just and reasonable rates. Indeed, the
Stipulation explicitly preserves the full panoply of traditional regulatory
tools that would permit our intervention if it appears that the new form of
regulation is operating against this central objective, and in fact creates new
tools to help ensure that service quality and demand-side management objectives
are met.[17]
In 2000, the Commission approved a second alternative rate plan
for CMP (referred to as ARP 2000) applicable in the newly restructured
environment.[18] Because generation service was now subject
to market competition, and because FERC had asserted jurisdiction over
transmission rates following a state’s unbundling of generation from delivery
service, ARP 2000 only applies to distribution delivery rates and service. Similar to ARP I,
ARP 2000 adjusts
rates annually by a formula of inflation minus a productivity offset adjusted
for mandated costs, earnings sharing, and service quality penalties. ARP 2000’s SQI mechanism contains the same
two indices, CAIDI and SAIFI, to measure reliability. Although CMP’s distribution revenues going into ARP 2000 were
only one-third of its revenues under ARP I, the ARP 2000 plan increased the
maximum penalty level for failing to meet the SQI standards from $3.0 million
to $3.6 million. In addition to the SQI
performance metrics, under the terms of ARP 2000, CMP is required to file an
Annual Reliability Improvement Report which, among other things, contains a
service area specific analysis of reliability and which identifies CMP’s worst
performing circuits and sets forth both the planned and undertaken improvements
to address such circuits.
During 2002, the
Commission approved an ARP for BHE.[19] Similar to CMP’s ARP 2000, the BHE ARP
applies only to distribution rates, which are subject to change annually based
on an external index formula. The BHE
ARP also contains an SQI mechanism which includes CAIDI and SAIFI performance
metrics. Under the BHE ARP’s SQI
mechanism, BHE faces penalties up to $840,000 should its service not meet the
established standards.[20] Similar to
CMP’s ARP 2000,
the BHE ARP requires BHE to file an Annual Reliability Improvement Report with
the Commission at the time it submits its annual price change information.
During 2003, MPS
submitted a proposal to the Commission requesting a $1.267 million increase in
distribution revenues as a “starting point” adjustment for its proposed
seven-year ARP. The Commission approved
a stipulation which resolved the Company’s “starting point” revenue requirement
request but did not address MPS’s proposed ARP.[21] Under the terms of the stipulation, MPS was
given until the end of 2003 to determine whether it wanted to pursue its ARP
proposal. MPS informed the Commission
that it did not wish to pursue its ARP proposal at such time. MPS is therefore, the only investor-owned
utility whose distribution rates remain subject to traditional regulation.
D. Corporate Reorganizations
Consistent with trends in
the electric utility industry, both CMP and BHE have been the subject of merger
acquisitions during the past five years.
On January 4, 2000, the Commission approved the merger of CMP and Energy
East, Inc. under which CMP became a wholly owned subsidiary of Energy East, and
on January 5, 2001, the Commission approved the merger of BHE and Emera, Inc.
under which BHE became a wholly owned subsidiary of Emera, Inc.[22]
In approving the CMP
merger, the Commission recognized that service quality could deteriorate when a
Maine utility becomes part of a larger multi-state firm. The Commission concluded that such a decline
would be unacceptable and put CMP on notice that it intended to closely examine
service quality during CMP’s then upcoming ARP 2000 proceeding. In the orders approving the CMP/Energy East
merger and the BHE/Emera merger, the Commission required the utilities to file
annual capital and O&M budget information with the Commission so that it
could monitor investment activity by the utility post-merger.
IV. RELIABILITY OF THE DISTRIBUTION AND
TRANSMISSION SYSTEM
A. Assessment
Criteria
In measuring the
reliability of the distribution and local transmission system we first assess
each utility’s performance in terms of the ARP service reliability criteria,
SAIFI and CAIDI.[23] As discussed previously, SAIFI is designed
to provide information regarding the average frequency of sustained
interruptions[24] per
customer over a predefined area and period of time and is considered to be a
good indicator of the condition of a utility’s plant, as well as the quality of
the utility’s maintenance and tree trimming activities. CAIDI represents the average time required
to restore service to the average customer per sustained interruption and is
considered to be a good indicator of the quality of a utility’s response to
outages.
Both CMP and BHE are
allowed, under their respective ARPs, to exclude SAIFI and CAIDI results on
days when a significant portion of the customer base suffers an outage. This allows the removal of data incurred
during “extraordinary events” in which the utility cannot reasonably be
expected to meet its performance benchmarks.
This prevents the utility from being penalized for extraordinary events,
such as hurricanes or major ice storms, that are outside its control and
outside the norm for outages.
Because the ARP's CAIDI
and SAIFI criteria are calculated on a company-wide basis, it might be possible
to achieve reasonably good average numbers (and thus avoid incurring any
penalties), by providing good service in densely populated areas while
performing poorly in more rural areas.
Therefore, in addition to reviewing overall SAIFI and CAIDI performance,
we have looked at SAIFI and CAIDI performance by circuit and compared such
performance with the worst performing circuits identified by CMP and BHE in
their ARP Annual Reliability Improvement Reports.
We also recognize that
SAIFI and CAIDI statistics provide only a snapshot of current utility
performance. Because failure to make
necessary investments in the grid or to follow reasonable maintenance practices
may not result in a deterioration of service for a number of years, it is
possible to maintain reasonable SAIFI and CAIDI numbers while sacrificing
reliability in the future, for cost savings and profits today. As a means of addressing this issue, we also
examined the utilities' maintenance and inspection programs, capital and
maintenance spending, vegetation management programs and spending, and the
utilities' planning criteria and procedures for system improvements. Because the utilities' transmission and
distribution systems are distinct, both in terms of operation and function, the
commission separately evaluated the transmission and distribution operations of
each utility. The Commission's findings
by utility are presented below.
B. CMP
1. Transmission
a. Overview
Based on the information provided
during the study process, CMP’s planning, design and operation of its
transmission plant (both bulk power and local transmission) appear to be
consistent with industry standards and good utility practices. CMP uses five specific reliability
indicators: event frequency; event duration; loss of load; expected unserved
energy; and number of customers affected, to identify and prioritize system
problems. The use of these indicators,
along with CMP's transmission inspection programs, discussed in section
IV(B)(1)(d), infra., make it likely that CMP will detect problems on the
transmission system which could degrade reliability.
CMP’s transmission and substation
system is designed to ensure that conductors, equipment and transformers do not
exceed assigned normal and emergency ratings and appears to be fully compliant
with ISO-NE and NPCC requirements for operation of the bulk transmission
system.
b. Capital and O&M Spending
CMP's
transmission spending since 1994 appears to be relatively consistent and thus,
does not by itself, raise concern.
CMP’s capital, operations, and maintenance spending on its transmission
system during the 1994-2003 time period are presented in Table I below. As noted from the information contained in
the table, CMP's capital spending increased immediately following
restructuring. CMP has explained this
increase as being related to capital projects which were planned for future
years but were accelerated to accommodate new merchant generators which came
onto CMP's system after restructuring or which were related to capital needs discovered
during the interconnection of these new generators.
Table I
CMP Transmission Spending
|
Year |
Plant Additions $ |
Operations Expenses $ |
Maintenance Expenses $ |
|
1994 |
4,337,000 |
9,569,000 |
4,440,000 |
|
1995 |
4,668,000 |
9,705,000 |
4,677,000 |
|
1996 |
2,495,000 |
11,520,000 |
3,828,000 |
|
1997 |
2,707,000 |
13,367,000 |
3,392,000 |
|
1998 |
1,433,000 |
17,743,000 |
3,383,000 |
|
1999[25] |
1,217,000 |
9,954,000 |
4,030,000 |
|
2000[26] |
9,340,000 |
15,338,000 |
5,037,000 |
|
2001 |
5,559,000 |
11,508,000 |
3,997,000 |
|
2002 |
9,066,900 |
11,702,000 |
4,419,000 |
|
2003 |
2,454,000 |
13,486,000 |
4,137,000 |
c. Vegetation Management
CMP’s
transmission vegetation management plan calls for four-year cycle aerial,
ground and side manual trimming.[27] This four-year cycle and plan is consistent
with recommendations contained in the August 2003 Blackout Report by FERC,
which noted that five-year cycles should be shortened.[28] CMP’s right-of-way management practices for
corridor widths, wire and border zone clearances on its transmission system are
reasonable, consistent with good utility standards, and well within NPCC and
FERC recommendations.
CMP’s
transmission vegetation management spending and performance (measured in terms
of brush acres) are set forth in the Table II below.
Table II
CMP Transmission Vegetation Management
Activity
|
Year |
Dollars Spent |
Brush Acres |
|
1994 |
$1,477,210 |
9304 |
|
1995 |
$1,513,033 |
7264 |
|
1996 |
$1,710,707 |
8919 |
|
1997 |
$1,449,101 |
6728 |
|
1998 |
$1,391,832 |
9304 |
|
1999 |
$1,450,759 |
7264 |
|
2000 |
$1,714,984 |
8919 |
|
2001 |
$1,689,768 |
6728 |
|
2002 |
$1,708,522 |
9304 |
|
2003 |
$1,854,881 |
7264 |
The
spending levels have increased with inflation, and, as reflected in the table,
have been adequate to maintain a consistent level of brush acres trimmed per
year.
d. Inspection Programs
CMP performs helicopter patrol of all of its
transmission sections and lines each spring or anytime that conditions may
warrant. CMP has a 10-year cycle for
transmission line foot patrol inspections with the exception of its 345 kV
lines, which are done annually. The
ten-year foot patrol inspection consists of a combination of pole and line
inspections that include ground line inspections and sounding of poles to
identify any poles that may have deteriorated and are of insufficient
strength. Poles identified as showing
deterioration are then evaluated to determine if they should be scheduled for
repairs, should be changed out based on their condition, or if a treatment
program could extend their life. CMP
visits and inspects its substations on a monthly or semi-monthly basis
depending on the type, size and voltage of the substation. During the substation inspection, the
company examines specified equipment and apparatus.
CMP
maintains a checklist that tracks all repairs and defects found on the
transmission and substation systems.
Any known problems are documented and then prioritized for repair. Emergency repairs are made immediately. CMP also infrared inspects its transmission
and substations once a year.[29]
CMP's stated goal is to complete 100% of its
scheduled maintenance work every year.
At times, a schedule may not be completed and, if so, the remaining
schedule is moved into the next year with a goal to not only complete the
original schedule but anything carried over as well. CMP reported a 100% completion rate for 2003, which appears to be
generally consistent with past practice.
We
find CMP's transmission inspection program to be well-designed and implemented
and consistent with sound utility practice.
The transmission inspection program appears to meet all requirements of
the NESC, NPCC and FERC.
2. Distribution
a. ARP Performance
Under
its first ARP, CMP was subject to a penalty if average service interruptions
per customer during the year (SAIFI), after exclusions, exceeded 2.0 and also
if its customers experienced an average greater than 3.0 hours of annual
service interruption per customer (CAIDI) during the year, after exclusions.[30] Under the Company's ARP I SQI mechanism, the
service reliability outage exclusion provision exempted all days in which
customer outage hours exceeded 0.8 times the number of CMP customer accounts in
that month.[31] This threshold was applied on a company-wide
basis.
Under
ARP 2000 as initially approved, CMP was to be penalized if its customers
experienced an average SAIFI greater than 1.80 and also if its customers
experienced an average CAIDI greater than 2.58 hours.[32] Under the Stipulation approved by the
Commission for ARP 2000, when more than 10% of the customers in one of the
company's eleven service areas were affected by outages, all outages occurring
in that service area associated with that event were excluded for the duration
of that outage from the CAIDI and SAIFI calculations.
Because some of CMP's
service areas are small, e.g. 18,000 customers, outages affecting as few as
1,800 customers were automatically being excluded from the CAIDI and SAIFI
calculations. On
December 12, 2003, as part of CMP's SQI mid-period review, the Commission
issued an Order Approving Stipulation that modified the outage exclusion
criterion to 10% of CMP's customers on a company-wide basis. At the same time, the SAIFI benchmark was
changed from 1.80 interruptions per year to 2.10 interruptions per year and the
CAIDI benchmark was decreased from 2.58 hours of interruptions per year to 2.32
hours of interruptions per year.[33] These changes in the benchmarks were
intended to reflect both the change to the exclusion criterion and improved
outage reporting by the company.[34]
During both ARP I and ARP 2000, CMP has consistently met its
company-wide annual SAIFI and CAIDI performance targets. CMP's company-wide SAIFI and CAIDI
performance, with exclusions then in effect, are presented in Table III below.
Table III
CMP Company-Wide ARP Performance - With
Exclusions
|
Year |
SAIFI Performance |
SAIFI Target |
CAIDI Performance |
CAIDI Target |
|
1995 |
1.41 |
2.00 |
2.63 |
3.00 |
|
1996 |
1.30 |
2.00 |
2.38 |
3.00 |
|
1997 |
1.29 |
2.00 |
2.01 |
3.00 |
|
1998 |
1.88 |
2.00 |
2.05 |
3.00 |
|
1999 |
1.47 |
2.00 |
1.80 |
3.00 |
|
2000[35] |
1.75 |
2.00 |
2.40 |
3.00 |
|
2001 |
1.45 |
1.80 |
2.01 |
2.58 |
|
2002 |
1.72 |
1.80 |
1.97 |
2.58 |
|
2003 |
1.72 |
1.80 |
1.82 |
2.58 |
Because CMP's exclusion criterion has changed several times during
the course of its two ARPs, to gauge CMP's performance over time, it is useful
to review CMP's performance on a pre-exclusion basis. Looking at the data on a pre-exclusion basis also enables one to
see how the utility is reacting to all types of events, including storms which
might be considered severe or extraordinary.
Table IV shows CMP's annual SAIFI and CAIDI performance since 1996
without extraordinary event exclusions.
Table IV
CMP company-wide ARP Performance Without
Exclusions
|
YEAR |
SAIFI |
CAIDI |
|
1996 |
2.27 |
3.57 |
|
1997 |
1.61 |
2.21 |
|
1998 |
4.73* |
15.22* |
|
1999 |
1.89 |
2.27 |
|
2000 |
1.98 |
2.77 |
|
2001 |
1.90 |
3.08 |
|
2002 |
2.53 |
3.56 |
|
2003 |
2.33 |
3.55 |
*Reflects outage data from 1998 Ice
storm.
As seen from the Table, over the 1996 through 2003 time period,
both CMP's SAIFI and CAIDI performance seemed to improve initially and then
deteriorate somewhat over the later years to a point at which performance in
the final year (2003) essentially equaled performance in the initial year
(1996). Improved reporting by CMP in
the later years, may in part explain the higher SAIFI numbers, and thus CMP's
2003 performance may actually be better relative to 1996 than is reflected in
the numbers.
b. Reliability
Criteria By Circuit
CMP's distribution system consists of 420 circuits, with customer
density per circuit ranging from 5,806 customers to 30 customers.[36] Because the SAIFI and CAIDI targets in CMP's
ARP are based on total customer interruptions and total customer hours of interruption,
an outage in a more densely populated circuit will have a much greater impact
on the company-wide SAIFI and CAIDI calculations than will an outage in a less
densely populated circuit. The overall
company calculations then, do not identify poor performance in particular areas
of CMP's territory. Therefore, the
Commission also examined CMP's (and BHE's) circuit by circuit performance and
worst performing circuit performance, in terms of CAIDI and SAIFI, as part of
this investigation.
The examination of CMP's "worst performing circuits", as
identified using actual circuit SAIFI and CAIDI performance (without
exclusions), shows a great disparity between the company-wide average and the
actual per circuit performance for the worst performing circuits. CMP's worst performing circuits in terms of
SAIFI and CAIDI are provided in Appendix C and Appendix D. Table V, below, compares the company's worst
SAIFI performing circuit, the average of the ten worst SAIFI performing
circuits, and the company-wide average SAIFI, along with the average number of
customers on the ten worst SAIFI circuits, for the last three years.
Table V
CMP Worst Circuit Analysis - SAIFI
(without exclusions)
|
Year |
Worst Circuit Performance |
Avg. SAIFI 10 Worst Circuits |
Company-Wide SAIFI Performance |
Avg. # Customers Per Circuit 10 Worst Circuits |
|
2001 |
55.97 |
31.21 |
1.90 |
455 |
|
2002 |
70.60 |
23.13 |
2.53 |
861 |
|
2003 |
39.18 |
20.36 |
2.33 |
713 |
As set forth above, the average number of customers on the 10
worst SAIFI performing circuits was 455 in 2001, 861 in 2002 and 713 in
2003. In 2003, the average number of
customers per circuit for CMP was 1,547.
The disparity between CMP's worst SAIFI performing circuits and its
company-wide SAIFI performance, and the fact that these worst performing circuits
are almost entirely within CMP's less densely populated areas is of concern to
the Commission.
CMP's reaction to these poorly performing circuits also raises
concerns. As part of its annual ARP
2000 filing, CMP is required to submit a list of its worst circuits and the
action taken, or planned to be taken, to improve performance on such
circuits. As noted in Appendix C, in
2001 and 2003 only one of the worst performing SAIFI circuits was identified by
CMP as a "worst performing circuit" in its Annual Reliability
Improvement Report while in 2002, none were listed.
During the interview process, CMP conceded that it concentrated
its improvement actions on those circuits which would provide the greatest
impact on overall company SAIFI performance since this is how the ARP penalty
mechanism is calculated. Consistent
with this approach, in 2003, CMP modified the method it used to calculate its
worst-performing circuits from a SAIFI by circuit calculation which we have
used here and which divides the number of customer interruptions on that
circuit by the number of customers served on that circuit, to a contribution to
overall SAIFI methodology, which divides the number of customer interruptions
on the circuit by the total number of customers, company-wide. Because the denominator, the number of
customers, remains fixed in CMP's company-wide methodology and because the
number of customer interruptions on CMP's more densely populated circuits is
likely to be greater in absolute terms than on CMP's more sparsely populated
circuits, CMP's methodology tends to give much greater weight to its more
densely populated circuits. In 2003,
for example, the average number of customers per circuit on the circuits
identified by CMP in its 2003 Annual Reliability Improvement Program as its
"worst performing circuits" was 3,400, or slightly double the average
number of customers per circuit for CMP.
In its response to the Commission's Draft Report, CMP states that
it has, as part of its ARP 2000 annual filing, been identifying its ten worst
circuitsand has identified and developed improvement plans for rural
circuits. CMP also notes that the lack
of complaints from customers is further evidence that CMP consistently delivers
high quality service to its rural customers.
The Commission is concerned by the possibility, that while CMP, on
an overall basis, is meeting the service quality standards of the ARP, its
performance in its less densely populated areas in its service territory may
have deteriorated, and in some service areas may no longer be adequate. In reaching this conclusion, we recognize
that service quality in every area of a utility's service territory will not,
and need not, be identical and that concentrating repairs or maintenance in
areas which will provide the most in the way of improved quality of service for
the most number of customers will often make sense from an economic or
efficiency perspective. It is
imperative, however, that service to all of the utility's customers, including
those in less densely populated areas, does not fall below what would generally
be considered minimum levels of adequate service.
c. Outage By Cause
Code
Appendix E provides CMP outage data from 1996 through 2003. On an overall pre-exclusion basis, CMP
outages have gone up by 36% during the period.
Tables 1 through 5 of Appendix E break down the outage data by cause
code. Of particular note, is the growth
in the number of outages due to equipment failure and
"unknowns." During the
interview process, CMP indicated that outages classified as "tree
contact", "weather" and "unknown" were essentially all
tree-related. The outage data for these
three categories combined, shows a general decline in number of outages through
the year 2000, and then a steady increase through the year 2003. The fact that CMP has been able to meet its
overall SAIFI and CAIDI targets despite the overall increase in outages
suggests that more outages are occurring on CMP's less densely populated
circuits, which would be consistent with the SAIFI by circuit data discussed
above.
Table VI
CMP Tree Related Outages since 2000
|
Year |
Tree/Weather Combined Outages |
|
2000 |
2,800 |
|
2001 |
3,848 |
|
2002 |
4,594 |
|
2003 |
4,705 |
d. Capital and
O&M Spending
While CMP's spending on distribution operations has grown significantly
since 1994, CMP's spending on distribution capital plant and distribution
maintenance has been essentially flat since 1998. Distribution spending levels since 1994 are presented in Table
VII below.
Table VII
CMP Distribution Spending Levels
|
Year |
Capital Additions $ in Thousands |
Operations $ in Thousands |
Maintenance $ in Thousands |
|
1994 |
25,394 |
23,199 |
12,746 |
|
1995 |
31,382 |
21,318 |
14,166 |
|
1996 |
28,013 |
25,006 |
17,524 |
|
1997 |
26,383 |
27,543 |
15,110 |
|
1998 |
29,850 |
25,166 |
22,314 |
|
1999 |
29,925 |
29,176 |
18,602 |
|
2000[37] |
32,633 |
33,867 |
20,103 |
|
2001[38] |
40,768 |
32,652 |
20,954 |
|
2002 |
26,156 |
37,581 |
20,721 |
|
2003 |
29,485 |
39,688 |
21,581 |
These spending levels are fairly consistent, and taken by
themselves, do not raise any significant concerns.
e. Vegetation
Management
CMP's spending on its distribution vegetation management programs
increased significantly during the period of 1994 to 1999 and has been fairly
flat since that time.
Table VIII
CMP Distribution Vegetation Management
Spending
|
Year |
Maintenance |
Hot Spot |
Hazard Tree Program |
Total |
|
1994 |
$3,755,471 |
$1,962,522 |
N/A |
$5,717,993 |
|
1995 |
$3,754,924 |
$1,882,956 |
N/A |
$5,637,880 |
|
1996 |
$6,488,674 |
$2,338,406 |
N/A |
$8,827,080 |
|
1997 |
$7,286,159 |
$1,518,157 |
N/A |
$8,804,316 |
|
1998 |
$6,453,765 |
$1,385,477 |
N/A |
$7,839,242 |
|
1999 |
$7,899,510 |
$1,193,222 |
N/A |
$9,092,732 |
|
2000 |
$7,902,244 |
$1,150,025 |
N/A |
$9,052,269 |
|
2001 |
$8,116,898 |
$ 819,725 |
$ 209,000 |
$9,145,623 |
|
2002 |
$6,647,058 |
$ 900,002 |
$ 329,211 |
$7,876,271 |
|
2003 |
$7,876,355 |
$ 596,770 |
$ 440,380 |
$8,913,505 |
CMP tracks the amount of vegetation management work performed on
its distribution system by the number of spans worked on. The work activity tracks fairly closely with
the expenditures and is presented in Table IX.
Table IX
CMP Distribution Vegetation Management
Activity
|
Year |
Total Maintenance Spans Worked |
Hot Spot Spans Worked |
Hazard Tree Spans Worked |
Total Spans Worked |
|
1994 |
28,632 |
14,402 |
- |
43,034 |
|
1995 |
25,424 |
13,716 |
- |
39,140 |
|
1996 |
56,850 |
20,781 |
- |
77,631 |
|
1997 |
62,393 |
12,132 |
- |
79,525 |
|
1998 |
42,118 |
10,716 |
- |
52,834 |
|
1999 |
56,220 |
8,805 |
- |
65,025 |
|
2000 |
50,205 |
7,449 |
- |
57,654 |
|
2001 |
48,793 |
4,976 |
1,048 |
59,817 |
|
2002 |
39,365 |
4,988 |
1,294 |
45,647 |
|
2003 |
60,591 |
3,452 |
1,639 |
65,682 |
During the early 1990's to 1995, CMP's operating procedures called
for five-year cycle trimming. According
to CMP, this program was not consistently followed and the lack of resources
prevented a completion of the cycle. In
1995, CMP migrated to what might be termed a "trouble-based" system
of vegetation management. At the
present time, CMP currently uses a variety of criteria to plan its distribution
vegetation work. The primary parameter
considered is the SAIFI for each circuit.
The other major areas of consideration include the prior year's SAIFI,
the number of tree-caused power outages, visual inspection of tree and brush
conditions by a qualified CMP arborist, a review of power quality issues,
distance of circuits from service center, and coordination with CMP betterments
or MDOT projects. Based on the above
criteria and resources allocated, CMP develops an annual work plan that targets
particular segments or spans of a circuit.
During the interview process, CMP representatives were asked if they
could identify what particular spans were last worked on. CMP stated that the information was included
in its GIS mapping system but could not be readily retrieved.
The Commission finds that CMP's shift from a cycle-based trimming
program to a more targeted type program is not, in itself, unreasonable. Indeed, in looking at BHE's targeted
program, see section IV(C)(2)(d), it appears that such a program can actually
increase the program's productivity.
The Commission is concerned, however, with the design of CMP's program,
in that it appears to be primarily reactive, and targets areas only after a
service reliability problem exists.
In its comments, CMP asserts that its vegetation management
program is the same as BHE's program which the Commission found to be
adequate. CMP states that its
vegetation management staff use a matrix approach to plan the maintenance work
for several years. As outage data has
improved and with the implementation of the ARP, the SAIFI component is
weighted more heavily, while other factors composing the matrix continue to be
used to make the final selection of circuits to be worked on. The factors reviewed are overall SAIFI, tree
SAIFI, total customers served on the circuit, number of tree-caused power
outages, tree condition as observed by arborists in the field, power quality
issues reported by CMP's customers, location of circuit from service center
office, and years since last pruned. As
part of its comments, CMP provided a map of one of its circuits that identified
when particular areas of that circuit were last worked on.
Based on the information collected to date, it appears that CMP’s
vegetation management program is not identical to BHE’s program and that CMP’s
approach to vegetation management seems to be more reactive in nature than
BHE’s program. We will attempt to
resolve any inconsistencies between the Commission’s view of CMP’s vegetation
management program based on the information we collected during this study and
the information presented by CMP in its comments, in our follow-up review
discussed in section IV(B)(3).
f. Inspection and
Maintenance
During this investigation, our staff asked CMP to provide a copy
or description of its distribution pole line inspection and treatment
program. CMP stated that it did not
have a formal pole line inspection program; rather it had an "informal"
inspection program, which it believed complied with the NESC. According to CMP, under its informal
inspection program, distribution poles and conductors are inspected by the
company's line workers and meter readers during the normal course of those
employees' duties. CMP could not state with
certainty when, or if, any particular circuit was inspected or what work orders
were generated as a result of the informal inspections. CMP stated that it performed annual infrared
inspections on the polyphase portion of its distribution system.[39] CMP's polyphase circuits comprise about 21%
of CMP's entire distribution system.
During the interview process, our staff expressed concern about
the effectiveness of CMP's informal inspection program and expressed its belief
that CMP appeared to be in violation of the NESC. In December, 2004 CMP indicated that, based on its further review
and participation in the Commission's investigation, it was revising its
distribution line inspection program effective January, 2005. Under CMP's revised distribution line
inspection procedure, CMP will be inspecting 10% of its distribution circuits
in each of its service centers on a 10-year cycle. Under CMP's new program, inspection will include both a safety
inspection and a plant condition inspection.
The information from the inspection will be entered into a distribution
inspection database.
CMP's revised inspection process is a significant improvement over
its past practice and satisfies the NESC's requirement for periodic
inspections. However, the Commission is
concerned about the length of time that it might take CMP to inspect all of its
circuits given the 10-year inspection cycle and the substantial time period
during which CMP had no formal inspection process. CMP suspended its prior formal inspection program in 1999. Since CMP was on a five-year cycle at that
time, it is possible that a circuit that was inspected near the beginning of
the last inspection cycle will go without inspection for 20 years.[40]
In its comments to the Commission's Draft Report, CMP argues that
it, in fact, has had formal inspection procedures since 1999 and that while it
did modify its line inspection procedures in 1999, it never suspended its
inspection activities. According to
CMP, since 1999, CMP has employed a variety of inspection techniques including
the following: (i) CMP annually inspects via infrared technology 100% of its
3-phase distribution system, which is equivalent to 18% of the circuit miles of
the distribution system; (ii) CMP annually inspects approximately 7.5% of its
circuit miles related to its ten worst performing circuits, while implementing
mitigation plans for its under-performing circuits from the previous year;
(iii) CMP's vegetation management team also annually inspects approximately 10%
of its circuit miles and reports issues spotted; (iv) in the course of
responding to outage calls, CMP inspects a portion of its circuit miles each
year; (v) CMP annually checks loads and counters on every distribution recloser
on nearly all of its distribution circuits and takes measurements of the
electrical loads at the substation on nearly all of its distribution circuits
each year; and (vi) in accordance with CMP's inspection policy (Field Operating
Procedure 409), all field employees (e.g. line-workers, line inspectors,
substation technicians, etc.) routinely inspect CMP's distribution equipment
during the performance of their jobs, including visual roadside
inspections. CMP argues that its
program is thus compliant with NESC requirements.
The adequacy of CMP's current inspection program in light of CMP's
prior practices and the possible effect of the prior program on grid
reliability will be one of the areas reviewed as part of the more detailed
study to be conducted following the issuance of this Report.
g. Age of Plant
CMP's average age of its distribution plant since 1999 is depicted
in Appendix F. CMP's average age of
plant has generally increased since 1999.
As pointed out by Liberty in its report to the Commission, age of plant
alone does not indicate a worsening condition of the grid because a utility,
through effective maintenance, can offset the effects that aging might have on
its plant. However, the aging of CMP's
plant is of some concern to us when combined with the suspension of its
inspection program and fairly flat level of spending on its distribution
maintenance program,.
h. Improvement
Programs
CMP's overall spending levels for system improvements are
established by Energy East with particular budgetary requests coming from the
field. If a project request is
rejected, it is sent back to its proponent, who has the option of resubmitting
the request during the next cycle. CMP
does not centrally track or retain records of unfunded projects.
During the interview process, CMP was asked to provide a list of
circuits currently above 90% of capacity, and a list of those above 100%
capacity, and for those circuits above 100% capacity, the time period that they
have been above 100% capacity.[41] In its response, CMP provided a list of "2005 System Improvement Projects with
Circuits Operating at 90% or Greater of Rated Capacity". See Appendix G. CMP has stated that it could not, beyond the
list of betterment projects, identify what circuits were above 90% or 100% and
how long such circuits were above such ratings. In its comments, CMP provided an updated list of the actions CMP
has taken or will take on such circuits.
During the interview process CMP stated that its reliability
improvement plan for its distribution system is set out in its Annual Reliability
Improvement Program Report filed with the Commission as part of the Company’s
annual ARP filing. As part of its
Report, CMP identifies its ten worst performing circuits for improvement during
the upcoming year. As noted previously,
at the present time the primary factor that CMP uses in determining what
circuit will make its list is the circuit’s contribution to the company-wide
SAIFI metric. CMP stated during the
interview that it will often go beyond the 10 circuits and work on its top 20
underperforming circuits. CMP could
not, however, produce any plans or written documentation of the improvement
program beyond the initial 10 circuits.
A review of CMP’s annual ARP Reliability Improvement Reports
demonstrates that it improved performance by taking corrective action on the
circuits identified. CMP currently has
420 circuits on its system. The
circuits identified annually by CMP for improvement therefore represent
approximately less than 2.5% of CMP's distribution system in terms of total circuits.[42]
CMP's distribution planning record-keeping, or lack of
record-keeping, is of concern to us.
Specifically, it appears that CMP is not aware of the capacity or margin
of safety on its circuits, or does not systematically track needed betterments
which were unfunded during a particular year.
This lack of record-keeping also impairs the Commission's ability to
verify that CMP's circuits have adequate capacity and that CMP is taking
appropriate actions to address any inadequacies. We are also concerned about the amount of time that circuits have
been allowed to remain at the 100% or more loading level before the situation
on such circuits was resolved through a system improvement.
Given the size of CMP’s territory, we are concerned that the scope
of CMP’s Reliability Program appears to extend only to the circuits identified
in CMP's Annual Reliability Report to the Commission. In addition, we are also concerned that by selecting the circuits
to work on as part of its Reliability Improvement Program primarily based on a
circuit's contribution to the overall SAIFI, CMP may be sacrificing service
quality in less densely populated areas as a means of ensuring that the overall
ARP targets are met. We believe that
these concerns can best be addressed through the more detailed review which
will be conducted in the upcoming months as discussed below.
3. Conclusions and
Recommendations
Based on the
results of the study, all aspects of CMP's operation of its transmission system
appear to be of high quality. On an
overall basis, the Commission finds that CMP is maintaining its distribution
system to meet the requirements of the ARP and therefore, on a system level,
CMP's distribution system is adequate.
However, the Commission is concerned by the disparity between CMP's
worst performing circuits and its overall SAIFI and CAIDI performance, and the
nature and scope of CMP's improvement program.
This concern is heightened by CMP's previous suspension of its distribution
inspection program, the aging of CMP's plant, the increase in the number of
outages, and what appears to be inadequate record-keeping in CMP's distribution
planning and maintenance operations.
As noted in section III(C), CMP has now operated under an ARP for
the past ten years. The Commission and
CMP have come to an agreement that this is an appropriate time to further
review CMP's distribution system as a means of addressing the areas of concern
raised during this general review, assessing the effectiveness of the ARP's
current reliability mechanism, and clarifying any areas of misunderstanding
between CMP and the Commission which may have arisen as a result of the general
examination conducted here. We envision
that this more detailed study of CMP's system will be done on a collaborative
basis and will be similar to the study that was commissioned by Maine Public
Service Company and which is discussed in section IV(D)(2)(g). This more detailed study will be conducted
in the coming months and will review the physical state of CMP's distribution
plant as well as its distribution planning and maintenance procedures.
C. BHE
1. Transmission
System
a. Overview
As a general matter, BHE’s transmission and substation systems
appear to be adequately designed and maintained, and BHE's transmission-related
practices are consistent with reasonable utility practices. BHE maintains clear documented standards for
transmission planning and construction.
BHE recently completed a 10-year transmission planning study which will
serve as a blueprint for system additions and modifications.
Under BHE’s current planning criteria, its system is designed to
prevent any loss of load over 50 MW for a single contingency.[43] Loss of load of 25 MW or higher as a result
of a single contingency is to be restored within two hours and load loss of 25
MW or less is to be restored within 24 hours.
The Liberty Report indicates that a 50 MW single contingency loss of
load criterion may be too high for a utility the size of BHE (300 MW). Liberty notes that lowering the 50 MW
criterion may require increased transmission looping and would improve system
reliability. Because these changes
would likely increase costs to the company, and ultimately its ratepayers, we
will request that BHE study the issue further and provide a cost/benefit
analysis of lowering the criterion as part of its Annual ARP Reliability
Improvement Report in March 2006.
In response to the U&E Committee's request, as part of the
study, we reviewed BHE's plans for increased looping in its system as a means
of enhancing its reliability, particularly in Washington County. BHE's Washington County customers are
supplied by a single radial feed,[44] "Line 66," which runs from the
company's Rebel Hill substation outside of Bangor to the Epping substation,
then on to the Washington County
substation. Line 66 is for the most
part located in a remote right-of-way, making access difficult and repairs time
consuming, ultimately resulting in extended outages for customers served by the
line. BHE has developed plans to build
a new transmission line which would run from Ellsworth to Harrington and would
provide looped service into Washington County.
In addition, the new transmission line would address voltage issues
caused by load growth in the Hancock County area. The company's
preliminary estimate of the cost of this project is in the $20 million range,[45]
which the company has proposed be included by ISO-NE in the overall New England
transmission tariff, thereby "socializing" the costs among all New
England ratepayers. The Company has
indicated that the transmission enhancements in both Hancock and Washington
County have begun, and from beginning to end, can be completed in five-years.
Based on our review of the information provided by BHE, it appears
that BHE's proposed Ellsworth to Harrington line would improve reliability to
the company's Downeast customers. We
will monitor BHE's proposal as it goes through the ISO-NE project approval
process. We note that in addition to
BHE's proposed Ellsworth to Harrington line, BHE has begun an improvement
project on Lines 66 and 67, which should independently improve reliability in
Hancock and Washington Counties. b. Capital and O&M Spending
BHE’s transmission related capital and O&M spending since 1999
is shown in the table below.
Table X
BHE Transmission Spending Levels
Year |
Plant Additions $ |
Operations Expenses $ |
Maintenance Expenses $ |
|
1999[46] |
7,345,463 |
511,905 |
1,040,385 |
|
2000 |
3,480,779 |
670,473 |
1,187,373 |
|
2001 |
1,778,750 |
662,410 |
1,120,359 |
|
2002 |
412,614 |
567,968 |
586,283 |
|
2003 |
1,096,245 |
704,951 |
1,102,085 |
Capital
spending was significantly higher in 1999 than during the remainder of the
period and reflects the completion of several major transmission projects (e.g.
Orrington to Ellsworth transmission line).
There was a significant reduction in both capital and maintenance
spending in 2002. According to BHE,
this occurred because, following its merger with Emera, BHE significantly cut
back on its spending programs to assess and review current practices and explore
opportunities for efficiency. In 2003,
spending returned to levels that are close to historical levels.
c. Vegetation Management
BHE’s recent vegetation management spending and activity on its
transmission lines is set forth below:
Table XI
BHE Transmission Vegetation Management
Activity
Year |
Acres Sprayed and Trimmed |
Expenditures $ |
|
1999 |
1374 |
220,024 |
|
2000 |
748 |
302,686 |
|
2001 |
919 |
358,014 |
|
2002 |
0 |
81,000 |
|
2003 |
994 |
345,818 |
There was a significant reduction in vegetation management activity
when, in 2002 following the BHE/Emera merger, BHE suspended its transmission
line right-of-way spraying program as part of its review of all company
expenses. BHE stated that in 2004, it
planned to increase its spraying program in addition to conducting its regular
trim and reclamation activities.
d. Inspection Programs
BHE
inspects its transmission system right-of-ways and lines twice a year. These inspections are designed to detect
problems or defects associated with poles, structures, equipment, conductors,
encroachments or vegetation conditions.
BHE has corrected all high priority conditions discovered during its
last four years of inspections.
BHE
has a formal 10-year cycle program for inspecting, testing, and treating or
replacing its transmission poles. Any
transmission pole that is found not to be within NESC strength requirements is
scheduled for immediate replacement.
Any pole that is found to be deteriorating but still adequate for
service, is re-inspected in five years. BHE reported that over the past five years it has inspected and
treated 50% of its transmission poles located within a right-of-way. With its ten-year inspection and treatment
program, it is expected that over the next five years all remaining poles will
be examined. BHE records and maintains
by paper and electronic database, all inspections completed, treatment
progress, and findings on its transmission system.
BHE’s
transmission pole inspection process appears to be well within the requirements
of the NESC. In addition, BHE's
preventative maintenance practices appear reasonable and consistent with good
utility practice.
2. Distribution
a. Performance Metrics
Under
the terms of the BHE ARP, as originally approved by the Commission, BHE’s CAIDI
benchmark was 2.13 hours per customer per year and the SAIFI benchmark was 1.43
interruptions per year. Similar to
CMP's initial ARP 2000 exclusion criterion, the BHE ARP allowed BHE to exclude
outages experienced by 10% or more of its customers in one of its service
areas.[47]
On September 24, 2003, BHE filed a petition requesting that the
Commission modify the CAIDI and SAIFI metrics.
In its request, BHE claimed that the data used to establish the initial
SAIFI and CAIDI baselines were flawed and that as a result of improved
reporting methods, BHE was reporting an increased number outages, which under
the ARP, would be perceived as a decline in reliability performance. During the course of this proceeding, the
staff also raised the issue that the initial exclusion criterion was improperly
excluding a number of small outages. On
April 15, 2004, the Commission issued an Order approving a stipulation entered
into by BHE and the Public Advocate, and supported by our staff, that modified
the SAIFI benchmark from 1.43 interruptions per year to 2.35 interruptions per
year and also modified the exclusion criterion to exclude only outages
experienced by 10% of the Company's customers company-wide.[48] BHE's CAIDI target was not modified as part
of this process and thus remains at 2.13 hours.
In 2002, BHE's SAIFI performance, with ARP exclusions, was 1.91
and its CAIDI performance with exclusions, was 2.35, both above the ARP target
levels. Under the terms of the ARP,
however, SQI penalties were not applicable for BHE's performance in 2002. In
2003, BHE met the ARP target levels with a SAIFI performance of 1.41 and a
CAIDI performance of 1.92, with applicable exclusions.
Table XII presents BHE's SAIFI and CAIDI performance without
exclusions since 1999.
Table XII
BHE Performance Metrics Without
Exclusions
|
Year |
SAIFI |
CAIDI |
|
1999 |
1.23 |
1.86 |
|
2000 |
2.39 |
4.82 |
|
2001 |
1.81 |
2.71 |
|
2002 |
2.95 |
4.15 |
|
2003 |
3.73 |
3.55 |
As can be seen from the above data, SAIFI and CAIDI during the
1999-2003 time period have trended up which, on its face, would indicate a
worsening level of performance. BHE has
recognized this trend and provided the following response:
As seen in the above table, the increase in customers affected by
outages (both pre and post exclusions) might suggest to some that the
reliability of the Company's power system has worsened over time. However, the reality is that the Company
implemented a new computer-based outage management system in 2001 in an effort
to improve outage prediction, management and data gathering functions. This new and more automated system replaced
the paper-based method used by the Company prior to this change. After an extensive study the Company concluded
that the old way of gathering outage impact data tended to under report outages
by failing to capture them in the first place.
This finding was reported to and acknowledged by the Commission's Staff
in case proceedings last fall (see record for docket 2003-706) and was a
primary reason why the Company's ARP SAIFI target was changed from 1.43 to 2.35
by Stipulation agreement on April 15, 2004.
BHE's explanation appears to be correct and, at least in part,
explains the higher numbers.
Nonetheless, the increase in CAIDI and SAIFI numbers over the past five
years warrants close monitoring.
b. Worst
Performing Circuits
During the 2001-2003 time period, BHE's average SAIFI for its 15
worst performing circuits went from 4.24 in 2001 to 5.36 in 2002 and to 6.68 in
2003. BHE's single worst circuit had a
SAIFI of 11.33 in 2001 and 2002 and 8.06 in 2003. (BHE's 15 worst performing SAIFI and CAIDI circuits are listed in
Appendices H and I.) In its 2002 Annual
Reliability Improvement Report, BHE listed 4 of these 15 circuits for
improvement.[49] In 2003, 6 of the 15 circuits listed in Appendix
G were identified by BHE for improvement.
While the disparity between the BHE's worst circuits and its
company-wide SAIFI levels is significantly less than CMP's, the trend in BHE's
numbers seems to be going in the wrong direction. While some of the growth in the worst circuit averages may be
explained by BHE's better reporting, the growth in the worst circuit SAIFI
average warrants monitoring during BHE's ARP and is addressed in section IV(F).
c. Outages by
Cause Code
Appendix J summarizes BHE's outages during the 1999-2003 period on
a pre-exclusion basis. Consistent with
the SAIFI data presented above, overall outages during the time period
increased by 36%. Of particular note is
the increase in weather-related outages which increased by 72%. While these increases may be explained by
better reporting, as discussed above, and by an increase in the number of
weather-related events, the statistics warrant monitoring by the Commission.
d. Vegetation
Management
In the past, BHE utilized a seven-year distribution vegetation
management cycle for its distribution circuits. In 2002, BHE elected to go to a customized trimming program that
identified sections to be trimmed based on an evaluation of predicted tree
growth done during BHE's inspection program.
As shown in Table XIII, since 1999 BHE spending on vegetation management
has declined by approximately 40%.
However, during the same period BHE's actual trimming activities
increased by almost 45%.
Table XIII
BHE DISTRIBUTION VEGETATION MANAGEMENT
PROGRAM
|
Year |
Expenditures |
Circuit Miles Trimmed |
|
1999 |
$1,638,138 |
612.8 |
|
2000 |
$1,793,104 |
540.8 |
|
2001 |
$1,873,892 |
596.0 |
|
2002 |
$1,880,800 |
1120.6 |
|
2003 |
$1,252,019 |
1159.4 |
The above data would seem to confirm BHE's claim that its new
customized vegetation management program is much more cost-effective than its
previous approach, and that through its customized program the company has been
able to enhance reliability while at the same time reducing costs.
e. Capital and
O&M Spending
BHE's capital and operations and maintenance spending levels since
1999 are provided in Table XIV below.
Table XIV
BHE DISTRIBUTION CAPITAL AND O&M
SPENDING
|
Year |
Plant Additions $ |
Operations Expense $ |
Maintenance Expense $ |
|
1999 |
8,073,941 |
4,802,139 |
7,773,318 |
|
2000 |
7,076,374 |
4,986,063 |
8,149,991 |
|
2001 |
9,888,158 |
5,119,606 |
8,246,324 |
|
2002 |
7,700,240 |
4,362,881 |
6,537094 |
|
2003 |
9,777,527 |
3,717,911 |
5,480,890 |
BHE's distribution capital spending has generally grown during the
period and does not raise any concerns.
BHE's operations and maintenance expense spending have declined since
BHE's merger with Emera. Taken in
isolation, these reductions would be a source of concern. However, as evidenced by the operation of
its vegetation management program and its Reliability Recovery Program
discussed in section IV(C)(2)(g), it appears that BHE has been able to achieve
these reductions while at the same time improving the operation of its
distribution system.
f. Age of Plant
The average age of BHE's distribution plant is set forth in Table
XV. The data does not seem to indicate
any general aging of plant and is not a cause of concern at this time.
Table XV
BHE Age of Distribution Plant
|
Year |
2000 |
2001 |
2002 |
2003 |
|
Distribution Poles |
22.01 |
22.75 |
22.91 |
22.40 |
|
Distribution Conductors |
30.42 |
31.19 |
31.93 |
33.00 |
|
Distribution Transformers |
19.09 |
18.13 |
20.76 |
20.50 |
|
Distribution Reclosers |
14.21 |
14.68 |
15.68 |
11.00 |
|
Distribution Regulators |
17.40 |
21.01 |
22.01 |
19.60 |
g. Inspection and
Improvement Programs
BHE inspects each of its distribution substations monthly. Corrective maintenance items are recorded in BHE's comprehensive computerized data management system, which allows engineers and managers to manage company resources better. In 2003, BHE completed 100% of its identified and scheduled maintenance work on its distribution system. BHE’s substation and distribution equipment testing and routine maintenance programs appear to be adequate.
BHE
had no formal distribution line or pole inspection program prior to 2002. Instead, BHE relied on division personnel’s
first hand knowledge of problems and conditions of the system. Line crews were assigned to chosen circuits
to perform any corrective action or repairs they deemed necessary. Line superintendents and area managers
typically inspected the circuits to determine where any system improvements were
needed to replace poles, conductors or associated hardware. There was no formal process to track or
record any findings, results of inspections, or completion rates. Consequently, although the Commission did
not review BHE's inspection process at the time, it is likely that we would
have found such a program not to comply with NESC codes as required by the
Commission had we conducted such a review.
In
August of 2002, BHE implemented a distribution circuit inspection program as
part of its new Reliability Recovery Program (RRP). The program consisted of a visual inspection of the distribution
plant and vegetation encroachment on 10 selected circuits. These inspections were completed to
prioritize any required improvements along with vegetation management
needs. BHE increased the number of
circuits under the RRP in 2003 by 20, bringing the total circuits inspected and
targeted for improvement to 30. In
2004, the number of circuits was again increased by an additional 20. Therefore, by the end of 2004 a total of 50
circuits, out of the company's 179 circuits, had been visually inspected by
foot or vehicle patrols and all vegetation management abnormalities or imminent
hazards due to plant or equipment condition were recorded as part of such
inspections.[50]
At the
beginning of the RRP, BHE did not inspect every segment of the target
circuit. BHE believed that at the
initial stage of the program it was important to concentrate on inspecting the
segments with higher
customer density and inferior
performance. However, BHE has affirmed
that, starting in 2004, each circuit will be inspected in its entirety. BHE has built an application into its
Geographical Information System (GIS) that will assist the inspection program
in maintaining adequate records, tracking defects and recording results, as
well as assisting its engineers in analyzing and prioritizing the data. Vegetation management work generated from
the inspection process is printed on GIS based trim maps indicating the
segments identified and approved for trim.
While BHE's revised inspection process appeared to meet most of the NESC requirements for inspections by providing a thorough inspection mechanism along with a process for retaining data, during the interview process, the staff and Liberty indicated to BHE that the revised plan still appeared to fall short of NESC's requirement that a plan for periodic testing be established to ensure that the company's plant meets all required strength codes. BHE acknowledged that its process was mostly reactive in that it was based on historical reliability performance, and that it should develop a program that was more proactive.
In February, 2005, BHE submitted a new comprehensive inspection program. Under the terms of its new program:
· Distribution circuits will be inspected every six years.
· Distribution line segments serving more than 1000 customers will be designated as "special consideration" and inspected every three years.
· An unknown quantity of distribution and transmission lines will be inspected annually based upon poor performance. A pre-established procedure that takes into account a distribution or transmission circuit's percent change in SAIFI (this year compared to last), 3-year SAIFI trend and SAIFI performance for the current review period was developed by Planners and will be used to identify assets that require further outage data analysis and field examination.
· Transmission lines located in right-of-ways (ROW) will be inspected once every five years. (Note: This activity is in addition to the Company's regular annual helicopter patrols and groundline inspection and treatment program of poles in right-of-ways.)
· Transmission lines located along roads with a distribution circuit underneath will be inspected once every six years and at the same time as its adjacent distribution circuit is examined.
· Transmission lines located along roads without a distribution circuit underneath will be inspected once every six years and at the same time that the closest distribution circuit is examined.[51]
· Transmission and distribution spans crossing highways, interstates and rivers will be inspected once every three years.
BHE's new program appears to take a much more proactive approach
to the inspection process and also appears to satisfy the NESC's requirement
for periodic testing. The Commission
will monitor BHE's performance under the new program to ensure compliance with
NESC requirements.
3. Conclusions and
Recommendations
On an overall
basis, we have not found any "red flags" that indicate that BHE's
service quality has degraded under the ARP or as a result of the BHE/Emera
merger. We find that BHE management's
approach to decreasing costs while actively and systematically attempting to
improve service quality appears to be reasonable and effective. While BHE's SAIFI and CAIDI performance
numbers have increased recently, much of this increase appears to be related to
improved reporting systems. Going
forward, BHE, through its aggressive Reliability Recovery Program and improved
inspection programs, should be able to meet its ARP targets on a company-wide
basis and improve performance on the company's worst circuits. BHE's new
inspection program appears to be a significant improvement over past
practices and appears to meet NESC's requirements for periodic testing .
D. MPS
1. Transmission
System
a. Overview
MPS
is not directly tied to New England's transmission system or part of the ISO-NE
region. Instead, northern Maine and
MPS, electrically speaking, are part of the Canadian Maritimes region, which
also includes the electric loads and generation of New Brunswick, Nova Scotia
and Prince Edward Island. The
transmission system in the northern Maine region is administered by the
Northern Maine Independent System Administrator (NMISA).
Pursuant to the requirements of 35-A M.R.S.A. § 3204, MPS sold its
generating assets to WPS in April 1999.
Since that time, WPS has continued to own and operate those
facilities. MPS remains a party to a
power contract with Wheelabrator-Sherman, an 18 MW biomass plant located in
MPS's service territory, which expires at the end of 2006. System reliability, capacity adequacy, and
market competitiveness in northern Maine have arisen as issues following the
passage of the Electric Industry Restructuring Act and MPS's divestiture of its
generation assets.
In 2002, we opened an inquiry to obtain information about the
adequacy of existing market structures, rules and laws in light of the number of
supplier/generation participants in the region.[52] During 2003, the Legislature enacted Resolve
2003, ch. 5, Resolve Regarding the Reduction of Barriers to the Transmission of
Electricity, which directed the Commission to work with the government of New Brunswick
to study ways to reduce costs and barriers to the flow of electricity between
Maine and Atlantic Canada. As part of
our inquiry, and in response to the Legislature's study resolve, we met with
and sought the input of the stakeholders in the northern Maine market. During this process, several approaches were
suggested on the issues of whether there is sufficient generation on the
northern Maine system and whether the physical interconnections with New Brunswick
are sufficient to provide northern Maine with the energy needed to provide
system reliability. The construction of
a second tie-line between the ISO-NE system in Maine and New Brunswick,
increasing the amount of generation with northern Maine, and increasing the
strength of the transmission links between northern Maine and New Brunswick
were suggested.
In our 2003 Electric Restructuring report to the Legislature on
this matter, we concluded:
In light of the new standard offer for
MPS, most customers in Northern Maine are largely protected from market
failures through December of 2006. This
provides, in our view, a degree of "breathing space" to enable the
Commission and the parties to work through the options described above. It may not be coincidental that at least
some of the projects (e.g. the tie line and some of the generation projects)
are targeted to come on line roughly during that period which also coincides
with the termination of the supply contract with Wheelabrator-Sherman. The Commission approach in the near term,
therefore, is to continue to meet with the relevant parties (including through
annual or even more frequent meetings in Northern Maine or New Brunswick) to
review their progress, while ensuring that the regulatory processes that may be
necessary to bring helpful projects to fruition are conducted
expeditiously. We expect, in the near
future, filings relating both to generation projects in Northern Maine and the
second tie line (and/or upgrades to the existing MEPCO line).
Subsequently, during the past calendar year, the Commission has
received filings requesting approval to construct an additional tie-line
between MPS's service territory and New Brunswick, the subject of Docket No.
2004-538; a request from BHE to construct a second tie-line between New
Brunswick and the New England-ISO system, the subject of Docket No. 2004-771;
and proposals from MPS and Eastern Maine Electric Cooperative to purchase
reservations on the proposed second New Brunswick tie-line, the subject of
Docket Nos. 2004-775 and 2005-17. In
addition, as part of the proceedings in Docket No. 2004-538, Loring Bio-Energy,
LLC (LBE), the developer of a 55 MW combined-cycle natural gas power plant to
be located at the Loring Commerce Center in Limestone, Maine, filed a request
that the Commission issue an order requiring MPS to execute a purchase power
agreement with LBE as a means of addressing both the reliability and market
issues in Northern Maine.
As we noted in a recent order denying a request for an emergency
rulemaking proposal submitted by LBE, we believe the Commission, through these
various proceedings, has the appropriate vehicles to address northern Maine
reliability and market issues to the extent that such issues in fact exist.[53] Thus, these issues have not been included as
part of this Report. We have, however,
reviewed MPS's general operation and maintenance of its transmission system and
address these issues below.
b. Spending Levels
MPS's
spending for transmission the 1999-2003 period is presented below.
Table XVI
MPS Transmission Spending
|
Year |
Capital Plant $ |
Operations $ |
Maintenance $ |
|
1999 |
1,624,684 |
359,652 |
505,772 |
|
2000 |
474,193 |
590,329 |
392,700 |
|
2001 |
1,516,075 |
581,705 |
588,005 |
|
2002 |
1,445,066 |
643,281 |
400,152 |
|
2003 |
299,175 |
732,772 |
233,923 |
In 2003, MPS significantly reduced transmission capital and
maintenance spending. MPS stated that
such reductions were temporary because of significant financial constraints at
the time and that spending would be restored to normal levels in 2004 and
beyond.[54] We will monitor MPS's performance to ensure
any past and possible future cutbacks in spending do not result in unacceptable
levels of reliability.
c. Inspection
Programs
From 1999 to 2003, MPS used contractors to perform a five-year
cycle inspection that included testing and treatment of its pole plant. Documentation provided during the study,
demonstrated that MPS has routinely been completing the inspections and
treatment programs along with all repairs and replacements identified through
the inspection process. In 2003, MPS
began using in-house crews for this work.
Recognizing the need to undertake a more comprehensive process, MPS
elected to engage in a very aggressive plan to inspect its entire transmission
system within two years.
MPS inspects its transmission substations on a bi-monthly basis
documenting all equipment conditions for review by engineering and
management. Based on this information,
MPS schedules any necessary repairs.
MPS also conducts infra-red inspections on all substation and
transmission connections and switches.
MPS's transmission inspection programs appear to meet NESC
requirements and ensure reasonable reliability of its transmission and
substation systems.
d. Vegetation
Management
MPS
has a five-year vegetation management cycle program for most of its
transmission system. MPS also follows a
five-year cycle on its roadside transmission plant except in areas where
easements cannot be secured or where a more frequent program is necessary
because of clearance inadequacy. This process may be resulting in tree-connected problems
within the areas for which MPS cannot obtain required clearances. MPS should
more actively pursue securing the required easements to help eliminate this
condition.
MPS's
transmission related vegetation management spending and activity since 1999 are
provided in Table XVII.
Table XVII
MPS Transmission Vegetation Management Activity
|
Year |
Spending $ |
Right of Way Acres Treated |
|
1999 |
$231,750 |
1,072 |
|
2000 |
$143,098 |
575 |
|
2001 |
$178,953 |
919 |
|
2002 |
$137,471 |
608 |
|
2003 |
-0- |
-0- |
|
2004 |
$123,237 |
852 |
MPS's
spending and vegetation management activity in 2004 are consistent with the
company's statements that it intended to restore spending and activity to
historic levels after 2003.
2. Distribution System
a. Performance Metrics
Although MPS is not operating under an ARP, it nonetheless tracks
its SAIFI and CAIDI performance, which is shown since 1999, without exclusions,
in Table XVIII below.
Table XVIII
MPS SAIFI and CAIDI
|
Year |
SAIFI |
CAIDI |
|
1999 |
1.51 |
1.21 |
|
2000 |
2.79 |
1.24 |
|
2001 |
2.05 |
1.19 |
|
2002 |
2.11 |
1.05 |
|
2003 |
2.52 |
1.85 |
MPS's performance metrics generally compare quite favorably with
the two other larger utilities in the state (CMP and BHE). However, both the CAIDI and SAIFI metrics
increased significantly in 2003, which warrants further monitoring.
b. Worst Performing Circuits
MPS's ten worst performing circuits for the past three years in
terms of SAIFI and CAIDI are presented in Appendix K. The average for these 10 worst performing circuits over the
three-year period is presented in Table XIX below.
Table XIX
MPS Worst Performing Circuits
|
Year |
SAIFI |
CAIDI |
|
2001 |
4.63 |
3.89 |
|
2002 |
7.18 |
2.67 |
|
2003 |
5.66 |
5.66 |
The above information shows significantly less disparity between
MPS's overall SAIFI and CAIDI and its worst performing circuits than we
observed for both CMP and (to a lesser extent) BHE.
c. Outage by Cause
Code
MPS's outage by cause code information is presented in Appendix
L. MPS's equipment related outages have
increased steadily from 17 in 1999 to 101 in 2004. During that same time period, MPS's weather related outages have
also steadily increased. This increase
in outages may reflect the equipment issues which were raised in the recent
report by MPS's consultant and issues surrounding MPS's prior vegetation management
program which apparently have been addressed by the company. See sections IV(D)(2)(f) and
IV(D)(2)(h).
d. Distribution
Spending
MPS's spending levels on distribution plant and operations and
maintenance for the years 1999 through 2003 are presented in Table XX. Plant additions during this time period have
grown significantly and apparently reflect the company's catching up on
deferred capital improvements. See section
IV(D)(2)(h). Operations and maintenance
expenses have been fairly consistent over the time period and do not raise any
major concerns.
Table XX
MPS Distribution Spending
|
Year |
Plant Additions $ |
Operations Expenses $ |
Maintenance Expenses $ |
|
1999 |
$2,239,340 |
$696,659 |
$1,453,888 |
|
2000 |
$2,474,765 |
$860,238 |
$1,375,444 |
|
2001 |
$2,903,365 |
$715,954 |
$1,537,548 |
|
2002 |
$3,991,750 |
$751,631 |
$1,538,220 |
|
2003 |
$3,404,661 |
$804,423 |
$1,343,582 |
e. Age of Plant
MPS's average age of its distribution plant, as of July 1, 2004,
is presented in Table XXI.
Table XXI
MPS AVG. AGE OF DISTRIBUTION
PLANT-IN-SERVICE
(In Years)
|
Distribution Plant-In-Service |
7-1-04 |
|
Poles |
33.5 |
|
Conductors |
33.5 |
|
Sub
Transformers |
28.0 |
|
Line
Transformers |
30.0 |
|
Reclosers |
18.1 |
|
Regulators |
15.5 |
MPS could not produce records of the average of plant for prior
years so we cannot draw any conclusions regarding trends. In comparison with the other investor-owned
utilities, MPS's pole plant age appears to be significantly higher, which
raises some concern about the condition of MPS's distribution plant. See Appendix M.
f. Vegetation Management
MPS's
past trimming program for its distribution system appeared to be reactive and
geared towards attacking “hot spots”.[55] The line clearance maintenance plan utilized
from 1999 to 2002 assigned and prioritized circuits based on two factors: 1) distribution
line clearances completed; and 2) outage statistics compiled by a technical
services engineer.
In
2003, MPS reevaluated and redesigned its vegetation management program to place
greater emphasis on prevention and cost-effectiveness. A significant change was MPS's decision to
use in-house vegetation management crews and equipment. MPS determined that it could achieve more
flexibility by using its own line crews to perform vegetation management work
in combination with routine line construction work, maintenance and
trouble-shooting. MPS's goal is to
track circuit clearance inadequacies through the inspection process and to
institute a five-year cycle for trimming on its distribution circuits.
MPS's
spending on its distribution vegetation management program is set forth in
Table XXII.
Table XXII
MPS Distribution Vegetation Management
|
Year |
Budgeted Amount |
Expenditure |
|
1999 |
$574,000 |
$556,834 |
|
2000 |
$470,000 |
$472,906 |
|
2001 |
$560,500 |
$554,092 |
|
2002 |
$540,000 |
$475,694 |
|
2003 |
$481,575 |
$415,059 |
The reductions in 2003 expenditures reflect savings realized from
MPS's revised vegetation management program.
MPS does not track its distribution vegetation management by miles
worked or spans worked, so we cannot assess the cost-effectiveness of MPS's new
program.
g. Inspection
Programs
Distribution line and pole inspections from 1999 to 2003 were performed pursuant to MPS's five-year Distribution Circuit Improvement Plan funded through the capital budget. MPS Area Managers managed this plan by assigning line personnel to inspection patrols during off-peak construction periods of the year. Based on an internally generated investigation done by an outside firm, see section IV(D)(2)(h), MPS recognized the need to develop a more detailed and formal inspection program with better reporting capabilities for its distribution utility inspection process.
Starting in 2003, MPS instituted a more detailed and formal distribution line pole inspection process that uses an asset management system. Pole plant age, the type of product and treatment, and outage history performance determine the circuits selected and scheduled for inspection. Under this new process, primary distribution poles are all sounded with a hammer to detect any potential hollow areas, rot or loose shell that would compromise the integrity and strength of the structure. Poles are then evaluated and classified for required action. All information collected in the field is recorded in a computer database.
At this point, MPS has not determined whether it will use either a three-year or five-year cycle standard for its new distribution inspection program. However, at least initially, MPS expects to complete a full inspection within a three-year period, after which it will evaluate which cycle length to adopt.
MPS's new inspection process is a significant improvement over past practice and should assist it in analyzing and managing its plant condition and also produce greater overall reliability. The adoption of more formal record keeping has allowed MPS to track the work identified through the inspection process better. During 2003, approximately 90% of the work identified through the inspection process was completed or was the subject of a work order. MPS's new inspection plan appears to be in compliance with the NESC.
h. Improvement Programs
In 2002, MPS retained the firm of R.W. Beck, Inc. (Beck) to assess the condition and performance of MPS’s system, the adequacy of projected budgets for capital improvements and system maintenance and the organizational infrastructure to support the system. Beck’s report (the Beck Study) was issued in May 2003. In its review, Beck provided the following findings regarding MPS’s system:
·
Overall,
transmission lines and poles appear to be in good condition and reasonably
maintained. On a relative basis, some
of the lines are older but still in good condition with the exception of some
of the oldest pole lines and areas where woodpecker damage is a problem. A significant number of lines may require
higher maintenance cost in the future due to age, type, and life expectancy.
·
Climbing
inspections are not currently part of MPS’s transmission maintenance
program. Climbing inspections should be
done on a five-year cycle to ensure that the condition of crossarms and pole
tops are known.
·
Thermal
(infrared) aerial or ground inspections should be scheduled during the yearly
ground pole inspections; this would result in a five-year cycle to cover the
transmission facilities.
·
All of the
substations were visited and were classified to be in poor, poor-fair, fair, or
good condition. Individual assessments
ranged from poor to good. On average,
MPS substation facilities are in poor-fair condition, primarily due to the age
of transformers. MPS's Substation
Priority Report seems to adequately capture problem areas that need correction;
however, MPS needs to develop a mechanism to ensure corrective action is taken
in a timely manner.
·
A
significant number of possible NESC code violations were observed at many
substation sites. It is recommended
that all code violations be given the highest attention and priority in
correcting.
·
There are
many miles of older three-phase distribution lines that are in poor condition
and will require attention in the immediate future.
·
Urban
distribution facilities are generally in poor to very poor condition and
require a higher priority to upgrade.
·
Rural
distribution facilities are generally in good condition except for older 12.5
kV lines and single phase lines.
·
Single-phase
rural facilities reviewed were found to be in poor condition.
·
Implementing
a right-of-way or vegetation management program for the distribution line is a
critical component to maintain reliability.
A three to five year cycle to cover the distribution system is
recommended.
Based on these findings, the Beck Study made the following
conclusions and recommendations:
·
System
planning must be improved to reflect current industry planning practices
including developing an engineering model, coordinated development of planning
methodology and assumptions, and evaluation of alternatives based on sound
cost/benefit economic analysis.
·
Application
of new technology within the organization is minimal. Technology solutions that result in increased efficiencies and
cost savings in customer care, purchasing, material handling, operations,
maintenance, and construction, should be sought.
·
System
reliability for the distribution system in certain areas may be at risk. Implementation of a more aggressive
distribution right-of-way or vegetation management program, as well as upgrades
to certain urban systems in high load density areas, are critical.
·
The
reliability of the transmission system may be at risk because a climbing
inspection to inspect the condition of the pole top and crossarms is not
used. The inspection program needs
improvement.
As confirmed during the course of investigation, MPS has already
addressed the immediate safety issues raised by the Beck Study, and has also
adopted many of the recommendations of Beck with regards to its inspection and
maintenance programs. While the
findings and conclusions contained in the Beck Study were not all positive,
MPS's initiation of the Beck Study and its response thus far are commendable. The Beck Study's objective assessment
provides MPS with an excellent blueprint for future improvements in system
reliability.
4. Conclusions and
Recommendations
Several criteria we examined during the course of this
investigation (i.e. increase in equipment outages, increase in tree-related
outages, age of plant) raised questions about the direction of the reliability
of MPS's distribution system. MPS,
through its initiation of the Beck Study and its subsequent follow-through,
appears to have acknowledged the problem
and appears to be taking appropriate steps to address the issues. For example, MPS has adopted improved
vegetation management and inspection programs that should enhance the
reliability of its system over time.
E. EMEC
Please see pages
24-27 of the Liberty Report.
F. Overall
Findings and Recommendations
Based on the available information, the Commission believes that
alternative rate plans (ARPs) have not, to date, compromised the overall
reliability of the grid in Maine.
However, CMP and, to a lesser extent, BHE have perhaps been influenced
by the operation of the ARPs' Service Quality Index penalty mechanism, by
focusing on meeting the overall company-wide targets to the detriment of
service in the utilities' less densely populated areas. It appears that BHE, through its reliability
recovery program, should be able to ensure that service to all of its circuits
is reasonable and adequate. A closer
look at CMP's grid will be necessary using an approach similar to the Beck Study
recently carried out by MPS. The Commission
and CMP have agreed to conduct such a study on a collaborative basis.
On a going-forward basis, the Commission will monitor the
performance of both BHE and CMP in less densely populated areas to ensure that
service issues in such areas are being appropriately addressed. In addition, at the time we next consider a
Alternative Rate Plan proposal for a utility, we will direct the parties to
address the issue of reliability of service in the subject utility's less
densely populated areas and will strongly consider how the Commission can
ensure adequate service to such areas.
The Commission will also take additional steps to keep itself
apprised of the utilities' inspection programs. None of the subject utilities' inspection programs was, at least until
recently, in full compliance with the NESC.
During the coming months, the Commission will monitor the inspection
programs of each of the subject utilities.
The Commission may also establish a mechanism, either through an
amendment to the Commission's rules or annual reporting requirements, which
will ensure that the Commission has sufficient current information about all
utilities' inspection practices.
A. Operational Overview
The
operation of the bulk power supply system in New England is primarily the
responsibility of ISO-NE in coordination with local control centers (LCCs) and
generators. This section of the study
outlines the current operational status of the New England regional grid, and
the procedures designed to address abnormal grid conditions that could occur
under extraordinary circumstances.
1. Status
Regional demand for electric power peaks
during the summer season in New England, due primarily to air conditioning
loads. In past years, the regional bulk
power grids that provide electric power to Maine consumers have experienced
very tight supply conditions during peak hours in the summer months. In the summer of 2004, however, supplies
were sufficient to meet demand.
For winter 2004-2005, NERC concluded that on a national level,
"generating and transmission resources will be adequate to meet the demand
for electricity." NERC identified as a problem, however, "the
potential for curtailment of natural gas supplies for electric generation"
during cold weather periods, "particularly in ERCOT [Texas] and New
England":
Natural gas supply and delivery is a growing concern
in New England during the winter. Although natural gas supplies within New
England are projected to be adequate during winter 2004/2005, extreme weather
can impact the regional supply and delivery infrastructures. As New England
experienced during the January 14-16, 2004, cold snap, extreme winter weather
can drive up demand for natural gas. This increase in demand caused an abnormal
number of gas units to report gas and unit availability problems. If this
occurs in New England during the upcoming winter, emergency operating
procedures may be needed to remediate any possible deficiencies. [56]
Steps being taken to address
this situation are described in a subsequent section of this Report.
In
contrast to the rest of the New England bulk power system, Maine’s demand for
electric power has typically peaked during the winter season, when the regional
grid is less stressed than during the summer season. In addition, Maine has more than enough in-state generation
capacity for the state’s needs which, when coupled with transmission limits on
exports, tends to place Maine in a better position than other New England
states in terms of reliability as well as price. For example, Maine’s peak load was approximately 1,900 MW this
past summer, when about 3,600 MW of generation capacity was available within
the State’s borders, and at times some of this generation was not available to
the rest of the region because of transmission constraints. This past winter, supplies were adequate to
meet regional demand.
ISO-NE
communicates regularly with power generators, transmission owners, brokers,
electric distribution companies, and state and federal government officials on
regional power system conditions.
During peak periods, the New England Governors’ Conference coordinates
weekly conference calls among the ISOs in New England and New York, the
Northeast Gas Association, Department of Energy, representatives of all New
England state governments, and other organizations as appropriate, to provide
updated status information on regional energy situation developments. Representatives of the Maine PUC and State
Planning Office routinely participate in those briefings. When the regional system is stressed, other
procedures and communications mechanisms are also employed, as described in the
following three sections.
2. Capacity Deficiency
When available supplies are not expected to meet
forecast demand, the ISO-NE implements pre-existing procedures to maintain the
reliability of the regional power grid.
These include: ISO-NE Operating Procedure 4 (OP4), ISO-NE Operating
Procedure 7 (OP7), and ISO-NE Operating Procedure 6 (OP6). The procedures would normally be implemented
in that sequence, although under certain circumstances portions of all of the
procedures could be implemented simultaneously without advance notice.
OP4
includes separate actions that dispatch all available generation, curtail
service to interruptible consumers, reduce voltage, share operating reserves,
purchase emergency power from resources outside of New England, and make public
appeals for voluntary conservation.
Utilities in New England experience various low-level OP4 actions almost
every year.
Maine
is better situated than other parts of the region from the perspective of the
bulk power supply system. Because under
tight power supply situations, the transmission lines connecting Maine’s
generators to the rest of the region are often filled to capacity, Maine would
not likely have the same power problems as other parts of New England. Capacity warnings and curtailment requests
are generally implemented only where they are beneficial to the overall
system. Accordingly, ISO-NE typically
exempts Maine from most OP4 declarations.
If
a power shortage or emergency were to occur on the New England grid due to
unforeseen circumstances, Maine government (including the Governor’s Office,
Maine Emergency Management Agency, and the PUC) would receive alerts regarding
the status of the electric system from the ISO-NE and CMP. Due to local circumstances elsewhere in the
region, ISO-NE could be faced with implementing OP4 measures in some areas of
New England where the bulk power supply system may be less robust than in
Maine. In that event, ISO-NE media
advisories would clearly state the areas affected by OP4 advisories, and those
areas that would be exempt. The same
exemption would typically apply to ISO-NE implementation of OP7.
In OP7, utilities are directed to interrupt
power to blocks of consumers, and the utilities may implement these
interruptions in a rotation to minimize the effect of the interruption to any
single group of consumers (“rotating blackouts”). The customers interrupted are designated by distribution circuit,
and include residential, commercial, and industrial consumers. At this time, no priority is given to any
specific class of consumers, although utility rotating blackout plans attempt
to move highly-critical facilities such as hospitals to the end of the rotation
list. New England has never experienced
a system-wide rotating blackout situation.
OP6 would reflect a widespread electric system
blackout, where utilities stabilize and restore the power grid. Large portions of the power grid could
experience extended outages for several hours, and depending on local
conditions, perhaps longer.
Further details about these ISO-NE operating
procedures are contained in Appendix N.
On August 14, 2003, large portions of the
Midwest and Northeast United States and Ontario, Canada, experienced an
electric power system blackout. The
blackout began in Ohio a few minutes after 4:00 pm Eastern Daylight Savings
Time and, over a period of about eight minutes, spread across the Midwest, New
York, Ontario, and into parts of New England.
Although most of New England and the Maritimes avoided a blackout by
separating from the rest of the Northeast, voltages were depressed across
portions of New England and some large customers (including one in Maine)
disconnected from the grid automatically.
An ISO-NE report of the event describes the regional impact as
follows:[57]
The effects on Massachusetts were confined to small areas in
Springfield and the Berkshires, which are directly connected to New York, where
the power disturbance had serious impacts. In the rest of New England, the
effects were confined primarily to southwest Connecticut and northwest Vermont,
which have been identified as weaker links in the New England bulk power
system.
Most of New England escaped from a potentially devastating impact
due to a number of factors:
• Automatic relays that appropriately shut down “the
border” between New York and New England, effectively shielding us from the
cascade effect;
• The work of system operators to stabilize
the system and keep the lights on;
•
A healthy supply of
generation resources that enabled New England to produce enough power to be
self-sufficient once the region was isolated from the rest of the Eastern
Interconnection,...; and
• Close coordination between ISO New England and local
utilities to restore power as quickly as possible in the affected areas.
The outage affected an
area with an estimated population of 50 million people and 61,800 MW of
electric load in the states of Ohio, Michigan, Pennsylvania, New York, Vermont,
Massachusetts, Connecticut, and New Jersey, and the Canadian province of
Ontario. Power was not restored for four
days in some parts of the United States.
Parts of Ontario suffered rolling blackouts for more than a week before
full power was restored. Estimates of
total costs in the United States range between $4 billion and $10 billion. In Canada, where gross domestic product was
down 0.7% that month, there was a net loss of 18.9 million work hours, and
manufacturing shipments in Ontario were down C$2.3 billion. During the event, the New England system
remained largely intact as a result of the New England system’s design,
communications, and ISO-NE operating procedures. A review of the event by NPCC found that “the restoration process
following the unprecedented loss of load on August 14th was effectively and
successfully carried out by system operators well trained to cope with such an
event.”[58]
The August 14 blackout
challenged NERC and the electric power supply industry to demonstrate that
established reliability standards are unambiguous and measurable, and that they
are being properly followed. As described
earlier in this report, compliance with NERC standards and guidelines is
voluntary on the part of industry participants. The U.S./Canada Power System Outage Task Force final report of
April 5, 2004 found that improvement was needed in that area, and stated in
Recommendation 25: “NERC should reevaluate its existing reliability standards
development process and accelerate the adoption of enforceable standards.” In response, on April 14, 2004, FERC issued
an order including a policy objective addressing “the need to expeditiously
modify [NERC] reliability standards in order to make these standards clear and
enforceable.” Accordingly, NERC decided
to accelerate the transition from existing operating policies and planning
standards to a single set of reliability standards under a process accredited
by the American National Standards Institute (ANSI).[59]
On February 8, 2005, NERC
adopted a comprehensive set of reliability standards for the bulk electric
system. The new reliability standards
incorporate existing NERC operating policies, planning standards, and
compliance requirements into an integrated and comprehensive set of measurable
reliability standards. The new
standards, which apply to all entities that play a role in maintaining the
reliability of the bulk electric system in the United States and Canada, took
effect on April 1, 2005. NERC has
expressed concern, however, that federal legislation is needed to make
compliance with reliability standards mandatory, but to date Congress has not
taken action on such legislation.[60]
In
response to the August 14, 2003 blackout, NERC committed to take other
immediate actions to strengthen the reliability of the North American bulk
electric system. Specifically, NERC created readiness audit teams and tasked
them with assessing the degree to which individual Control Areas and
Reliability Councils have met their responsibilities. The NERC audit team reviewed ISO-NE practices in May 2004, and
identified several improvements that ISO-NE could make to internal systems and
processes, but found that ISO-NE had adequately addressed reliability issues
overall:
The New
England region has tightly integrated reliability requirements into the design
of the wholesale electricity market. This has led to a consistent set of market
rules and operating procedures that prescribe the way the market operates and
clearly identifies the responsibilities and obligations of all market
participants. Having the reliability requirements clearly identified allows
ISO-NE to focus on reliability issues and to ensure that the market can operate
efficiently in all timeframes. The New England market approach, with its
reliability-first philosophy, has led ISO-NE staff to develop a strong and
well-developed culture of reliability. Everyone the audit team interviewed
exhibited the reliability-first philosophy. [61]
The U.S./Canada Power System Outage Task Force final report
on the blackout found that operator performance was an important root cause of
the blackout. FERC noted that failures
included “lack of situational awareness, failure of personnel to declare an
emergency, and failure to take appropriate action” to keep the bulk electric
system stable. On December 15, 2004,
FERC directed power grid operators and transmission providers to report back to
that commission on their training practices.
FERC plans to analyze the results of that survey, and submit a report to
Congress on the issue.
FERC also noted that reactive power[62] issues contributed to the August 2003 blackout. In December 2004, FERC staff presented a
report to that commission on the role of reactive power in establishing
reliable power systems. In this ongoing
inquiry, FERC held a technical conference on March 8, 2005, and is soliciting
comments on the related FERC staff report.
In summary, NERC and its
regional reliability councils have taken positive action in response to the
August 14, 2003 regional blackout. NERC
reliability standards recently adopted using ANSI processes took effect in
April 2005, and upgraded NERC cyber security[63]
standards will follow. While it appears
that these standards will have a beneficial effect on the reliability of the
bulk power system, because compliance with them is voluntary at this time, it
is premature to conclude that these actions will provide all necessary
reliability improvements identified in the wake of the 2003 blackout. The Commission will continue to participate
in the standards review process and to monitor the degree of reliability
provided by regional utilities.
Maine is in a better position than other parts of the region because of
ample generation and import capacity, and transmission constraints between
Maine and the rest of New England. As a
consequence, ISO-NE generally excludes Maine from capacity deficiency
declarations unless there is a capacity deficiency in Maine. One exception to that practice occurred in
mid-January 2004.
The
coldest winter period in the New England region in 25 years and very high
demand for electricity, combined with tight conditions in the natural gas
markets, stressed the region’s bulk power system.[64] Despite a record winter peak electricity
demand of 22,818 MW, numerous unexpected generator outages, and projected
capacity deficiencies, ISO-NE was able to avoid interruptions of electrical
supply. A unique set of circumstances
resulted in ISO-NE requests to satellite control centers, including the Maine
dispatch facility at CMP, “to prepare contingency plans in anticipation of NOP
4 and possible NOP 7 actions.”
Atypically, Maine was not excluded from that ISO-NE
advisory. The PUC immediately notified
numerous stakeholders throughout the state, including Governor Baldacci.
Among
the circumstances that affected that situation were the severe curtailment of
electricity imports from New Brunswick and Québec due to low temperatures and
the resulting record demand in those locations, low-temperature induced high
efficiencies on transmission lines between Maine and New Hampshire thereby
increasing the north-to-south flow of energy, and milder temperatures in New
York that allowed New York to export additional energy to New England,
mitigating the usual high north-to-south demand on those lines.
Another
significant factor was the unavailability of gas-fired generation in the
region. As a result of the addition of
more than 9,000 MW of gas-fired combined cycle generating plant capacity in New
England, the region has become more dependent on natural gas than in the past. During the January 2004 cold snap, some of
New England’s gas generators, including some in Maine, took advantage of high
natural gas prices by curtailing generation and selling their gas back into the
market. Of the 9,000 MW of generation
that was unavailable to meet electric load in the region during the Cold Snap,
gas fired-units were responsible for 7,000 MW.[65]
The
January 2004 Cold Snap highlighted vulnerabilities of the New England bulk
power system, including limitations of the natural gas pipeline network. New England’s dependence on natural gas for
electric power generation can cause problems during extreme winter conditions,
which increase natural gas demand for both heating and electric power
generation. NERC identifies this issue
as “a growing concern in New England during the winter season” because extreme
weather can affect supply and delivery infrastructures while driving up demand
for natural gas.[66]
ISO-NE,
the Northeast Gas Association, regional utilities and regulatory agencies have
examined that situation and developed near-term responses. Among remedies already deployed, is a new
ISO-NE Market
Rule for Cold Weather Event Operations (Market Rule 1, Appendix H) to improve coordination
of operations between the power generation and natural gas sectors in New
England during cold weather events. A
NEPOOL/ISO Cold Snap Task Force and an Electric and Gas Operating Committee
have been established to address these electric-natural gas issues, and further
studies have been commissioned into related factors, including assessment of dual
fuel capabilities of generating units in the region.
ISO-NE, NEPOOL participants, state utility
and environmental regulators, gas industry representatives, and the New England
Governors’ Conference Power Planning Committee have collaborated on specific
remedial steps for both short-term and long-term applicability.[67] ISO-NE
expects short-term actions to increase supply-side resource availability in New
England by at least 2,000 MW over the capacity available during the Cold
Snap. These actions include:
·
Adjusting wholesale
market timing to enhance generators’ ability to secure scarce fuel supplies.
·
Denying generator
requests for economic outages during extreme winter conditions.
·
Requesting plants to
use alternative fuels during weather events where possible.
·
Advising demand
response resources to reduce consumption on notice.
·
Improving
communications between electric and natural gas entities.
·
Closely coordinating
with neighboring systems to manage power exports and imports during shortages.
Stakeholders
also identified longer-term actions to improve import capabilities with
neighboring systems, to develop electric market incentives to encourage more
dual-fuel generating capacity in New England, and to create incentives for the
use of firm-gas transportation arrangements for gas-only generating units. Maine PUC Commissioners and staff are
monitoring those activities and participating in them as appropriate, and will
continue to work with ISO-NE and other stakeholders.
Prior to restructuring
the electric industry in the late 1990’s, integrated utilities were responsible
for building or contracting for enough capacity to assure that there was
adequate generation to reliably supply customers' needs. Their planning criterion was to have
adequate generation capacity such that the probability of disconnecting
non-interruptible customers due to resource deficiency, on average, would be no
more than once in ten years – the “one in ten” criterion.[68]
In the restructured
environment, however, firms invest in new generation when they expect it will
be profitable, without regard to whether the one in ten reliability level will
be achieved. Furthermore, electric
restructuring resulted in the divestiture of generation from T&D utilities,
and thus the T&D utilities no longer have the obligation to develop or
purchase generation resources. This
raises the question of whether some mechanism is needed to ensure that we will
have adequate generation capacity in the restructured wholesale electric
market.
When restructuring was
beginning in New England, a number of firms decided to construct new, mostly
natural gas-fired, facilities in Maine and throughout much of the rest of New
England. As a result, the region has
enjoyed surplus capacity for the past few years. The only significant reliability problems have been in areas of
Connecticut and Massachusetts where the transmission system does not allow
sufficient imports from elsewhere in New England and siting new generation has
proved problematic. Most of the region,
including Maine, has more than adequate generation to meet the installed
capacity requirements in the near term.
As a result of concerns that over the coming years new investment in generation may not occur as needed to maintain reliability, there has been a long and complex proceeding before the FERC regarding whether some form of Locational Installed Capacity Market (LICAP) should be instituted to maintain existing generation capacity and attract new generation capacity in locations where the generation is needed, in time to meet future deficiencies. The Maine PUC has been very active in this case, including sponsoring the testimony of staff and outside consultant witnesses. Our position has been that some form of capacity adequacy is desirable, but that the specific proposal of ISO-NE is likely to be both expensive and ineffectual.
VI. SECURITY OF CRITICAL GRID INFRASTRUCTURE
The term “security” as used
in the electric sector has at least two different meanings: NERC defines “security” as “the ability of
the electric system to withstand sudden disturbances such as electric short
circuits or unanticipated loss of system facilities.” We address these issues in a more general sense in the
reliability discussions elsewhere in this report. In this section, we address the adequacy of grid security more
from the perspective of the physical and cyber protection of critical grid
infrastructure.
Significant sectors of the
‘critical infrastructures’ identified nationally for special protection fall
within the Commission’s intrastate jurisdiction: electric power, natural gas,
telecommunications, and drinking water.
Public utilities that provide those services are required by Maine law
to provide safe, reasonable and adequate facilities and service.[69] To satisfy that requirement, utility
facilities must be secure. Public
utilities have the primary responsibility to secure their own infrastructure.
The utility industry,
through NERC, NPCC, and related utility industry organizations, has identified
best practices and guidelines for the security and protection of critical grid
infrastructure. While compliance with
those measures is voluntary on the part of industry members, since the terrorist
attacks of September 11, 2001, the utility industry has strengthened those
standards and provided additional incentives for industry compliance, including
notification of federal and state utility regulators in the event that repeated
violations of industry standards are observed in private industry security
audits. Those standards include
traditional security issues related to the physical protection of facilities,
and are evolving to address cyber security issues as well.
Cyber security has arisen as a new challenge for the electricity sector. Utilities are increasingly reliant on computer-based Energy Management Systems (EMSs) to control their power systems, and are increasingly monitoring and operating system devices using Supervisory Control and Data Acquisition (SCADA) systems that in some circumstances could be vulnerable to outside interference, possibly through the Internet. These vulnerabilities have been recognized as a national issue. According to the U.S. General Accountability Office,[70] the control systems community faces several challenges to securing control systems against cyber threats. These challenges include: the limitations of current security technologies in securing control systems, the perception that securing control systems may not be economically justifiable, and the conflicting priorities within organizations regarding the security of control systems.[71]
ISO-NE
conducts compliance and internal controls reviews of its own facilities and the
local control centers (LCC)[72]
in New England under a FERC-approved Transmission Operating Agreement. ISO-NE conducted reviews of the LCCs in 2004
and 2005, including a 2004 review of the LCC operated by CMP. These reviews include the security of the
Energy Management System, with a comprehensive review of cyber security
policies and procedures for electronic and physical security, personnel and
training, system security management, and incident reporting and response
planning. Internet vulnerability
assessments were performed in 2004 at all LCCs and SCADA centers, which are the
primary data centers supplying real-time information to the ISO.
NERC has issued an interim cyber security standard that addresses some of these vulnerabilities on an “Urgent Action” basis, and plans to replace that interim standard upon its expiration in August 2005 with a high-level industry-wide cyber security standard. Maine T&D utilities are currently working to comply with the interim NERC standard. As in the case of vegetation management standards and practices, however, a one-size-fits-all industry consensus standard, which may represent the lowest common denominator of industry interests, may not be the most effective method of elevating cyber security within the industry, particularly because effective enforcement mechanisms may not be in place.
While utilities have the
primary responsibility to secure their own infrastructure, the Commission
provides support and encouragement to utilities, and collaborates on security
issues with utilities, industry organizations, federal agencies, and other state
agencies such as the Maine Emergency Management Agency (MEMA) in the Department
of Defense, Veterans & Emergency Management. As part of the State’s homeland security
planning efforts, the Commission participates on a State security team that
includes the Chair of the State Homeland Security Council, MEMA’s homeland
security coordinator, and the officer in charge of the Maine State Police
intelligence and special services unit.
That team is conducting an ongoing review of utility security
improvements implemented since September 2001. Those reviews are being
conducted with utility security and management teams at individual utilities,
beginning with a review of CMP during the summer of 2004.[73] Reviews have been initiated with BHE and
MPS, with follow-up underway. The team
will review security arrangements at other key utilities during the next
several months. Dialogues related to
issues discussed among participants continue until potential issues and
concerns have been resolved to the mutual satisfaction of the
participants. A principal outcome of
this process is the improvement of communications among these entities related
to security issues.
The Commission has
exchanged 24x7 contact information with all major utilities for both
operational status and security purposes to assist State and utility interests
in communicating issues related to infrastructure security. Commission staff have assisted the Adjutant
General, State Police, National Guard, MEMA, and emergency managers in
providing alert and advisory information to utilities whose infrastructure may
be threatened. In addition, the
Commission has designated staff members to serve on the State’s Emergency
Response Team (ERT) to advise the Governor and MEMA on utility-related issues,
and is developing the capability to use detailed geographic information system
(GIS) maps and data about key utility infrastructure to support the Governor,
MEMA, and ERT during events that involve utility systems. In addition to information
forwarded to the Commission staff by MEMA, the Commission staff also receive
threat advisories from DHS, the FBI, the U.S. Attorney’s Office, NERC, the
national Electric Sector Information Sharing and Advisory Center (ES-ISAC), and
the Multi-State ISAC, to enable the Commission to support Maine utilities, law
enforcement, and emergency management organizations as may be needed.
MEMA
conducted a comprehensive energy emergency exercise on February 17, 2005,
involving the ERT, the Governor's Office, key utilities, selected county and local
governments, and other organizations.
The exercise was designed to identify areas where the State may need to
improve its ability to manage extreme power system emergencies. Reviews of exercise issues and lessons
learned are ongoing.
On a national level, the Commission staff actively
participates on a committee chartered by national utility regulators[74]
to identify best practices and roles for utility regulatory commissions to
protect critical infrastructure nationally.
That committee works to improve communications among federal and state
agencies and utilities on utility-related critical infrastructure issues, and
to represent the interests of Maine and similarly-situated states in the
evolution of utility-related homeland security practices by federal
agencies.
In summary, Maine T&D utilities have taken positive
steps to improve the security of their key infrastructure in the aftermath of
the September 11, 2001 terrorist attacks and subsequent events that have
attempted to challenge the integrity of the bulk power system. These improvements are ongoing, and due to
the evolving nature of potential threats to critical infrastructure Maine
utilities must continue to evaluate their effectiveness and ensure that
protection of their key infrastructure addresses the changing environment that
may pose new and different threats over time.
The Commission continues to address utility infrastructure security issues, including the following factors that make utility infrastructure security particularly challenging:
· Utility
infrastructure is usually highly visible and thus not a hidden target.
· Utilities increasingly use modern technology, including the
internet, to monitor and control their facilities, and the internet is far from
secure and is accessible globally.
· High-tech approaches are increasing the interdependence
among utility services.
· To minimize the inadvertent or unnecessary release of
sensitive information about critical infrastructure, some Federal agencies and
utilities restrict information flow to States, complicating State and local
roles as the levels of government that would provide initial response to an
incident that affects local infrastructure.
The Commission's goal remains that, even in times of an extreme or unanticipated emergency, utility facilities and services will continue to be safe, reasonable, and adequate to meet Maine's needs. The Commission will continue to coordinate with State homeland security, emergency management, and law enforcement personnel to monitor and support utilities' progress in these areas.
[1] Under the
terms of an ARP, a utility's rates are adjusted annually based on changes to an
external index and not based on changes in costs used as part of traditional
"cost plus" regulation.
[2] For both
the CAIDI and SAIFI metrics, an increase in the indices represents a
deterioration or worsening in performance.
[3]P.L. 2003,
ch. 219.
[4]For
purposes of this investigation, the Commission interpreted the term “security
and robustness” to mean reliability of the system rather than protection
against terrorist attacks.
[5]The
Commission inquiry was docketed as Maine Public Utilities Commission,
Inquiry into the Adequacy of the Electric Grid in Maine, Docket No.
2004-248.
[6]Given the issues requested to be investigated, and the time
period allotted for the investigation, the Commission did not investigate the
reliability of service of the state’s seven other COUs as part of this
investigation.
[11] The
ISO-NE satellite structure may change over time, based on circumstances that
affect NEPOOL participants and wholesale market issues. For example, VELCO will begin operation as
an LCC in July, and additional satellite centers may be established within the
New England region as markets evolve.
[12] For a full
discussion of the reliability of the New England power system, including Maine,
please refer to the full RSP report. A
summary of the 2004 plan (RTEP04) and the PAC stakeholder meeting materials
related to the development of the 2005 plan are available online at :
http://wwwiso-ne.com/committees/planning_advisory_committee/. For access to the full RTEP04 report,
contact ISO-NE Customer Service at (413) 540-4220.
[13] Central
Maine Power, Proposed Increase in Rates, Docket No. 92-345, (Dec. 14 1993).
[14] Central
Maine Power Company, Proposed Increase in Rates, Docket No. 92‑345(II)
(Jan. 10, 1995).
[15] The SAIFI formula is:
SAIFI = Total number of customer interruptions
Total number of customers
served
[16] The CAIDI formula is:
CAIDI = ∑ customer
durations_______________
Total number of customer
interruptions
[17] Central
Maine Power Company, Proposed Increase in Rates, Docket No.
92-345 (II) Detailed Opinion and Subsidiary Findings at 2 (Jan. 10, 1995)
[18] Central
Maine Power Company, Request for Approval of Alternative Rate Plan
(Post-Merger), “ARP 2000,” Docket No. 99-666 (Nov. 16, 2000).
[19] Bangor
Hydro-Electric Company, Request for Approval of Alternative Rate Plan, Docket
No. 2001-410 (June 11, 2002).
[20]BHE’s
penalty level of $840,000 represents approximately 1.5% of BHE’s distribution
delivery revenue requirement and is, thus, comparable in scale to CMP’s ARP
maximum penalty level.
[21] Maine
Public Service Company, Request for Approval of Alternative Rate Plan, Docket
No. 2003-085 (Sept. 3, 2003).
[22]CMP Group,
Inc., et. al., Request for Approval of Reorganization and of Affiliated
Interest Transactions, Docket No. 99-411, Order (Jan. 4, 2000); and Bangor
Hydro Electric Company, et. al., Request for Approval of Reorganization (Joint
Petition), Docket No. 2000-663, Order Rejecting Revised Stipulation and
Approving Original Stipulation (Jan. 5, 2001).
[23] Although
MPS and EMEC are not operating under alternative rate plans, both calculate
SAIFI and CAIDI performance.
[24] Pursuant
to the Institute of Electrical and Electronics Engineers, Inc. Standards Board
(IEEE) standard 1366, a “sustained interruption” is “any interruption not
classified as a momentary event. Any
interruption longer than 5 minutes.”
[25]
Operations Expenses after 1999 do not include congestion expenses and costs
assessed for regional services by ISO-NE.
Congestion expenses refer to increased
generation costs caused by congested transmission points (e.g. Boston,
Southwest Connecticut) and until March 2003 were spread over all transmission
owners in the region based on the utilities' load share.
[26] Plant
additions for 2000, 2001 and 2002 are less amounts for capital projects to
interconnect new merchant generators.
[27] Cycle
trimming refers to the practice of trimming particular areas of the system at
designated intervals so that the entire system would have been completely
trimmed at the end of the predetermined period or cycle.
[28]
Vegetation Management and Bulk Electric Reliability Report From the Federal
Energy Regulatory Commission (FERC) December 7, 2004.
[29] Infra-red
inspections refer to the process of using thermovision equipment to thermally
scan the system to locate hot spots on conductors and equipment caused by loose
connections or hardware and other defects.
[30] See
Central Maine Power Company, Proposed Increase in Rates, Docket No.
92-345(II), Order Approving Stipulation
(Dec. 30, 1994), and Detailed Opinion and Subsidiary Findings
(Jan. 10, 1995).
[31] See Central Maine Power Company, Proposed
Increase in Rates, Docket No. 92-345, (Jan. 10, 1995) Order Approving
Stipulation, Appendix Attachment G at 2.
For example, for a hypothetical base of 500,000 customer accounts, any
day with over 400,000 customer-hours of outage would be excluded from the SQI
calculation under this mechanism.
[32] See Central Maine Power Company,
Request for Approval of Alternative Rate Plan (Post Merger) “ARP 2000,” Order
Approving Stipulation, Docket No. 99‑666, (Nov. 16, 2000).
[33] See
Maine Public Utilities Commission Investigation, Mid Period Review of CMP's
ARP 2000 Service Quality Indices, Docket No. 2002-445, Order Approving
Stipulation (Dec. 12, 2003).
[34] According
to CMP, the company automated its outage reporting process in 2002. This has resulted in more small scale
outages being reported which results in higher SAIFI numbers but due to the
small scale nature of the outages actually tends to decrease the time per
outage or CAIDI calculation.
[35] CMP's ARP
I expired at the end of 1999 and no ARP metrics were in effect for 2000. However, by way of our order approving the
CMP/Energy East merger, we extended the ARP I SQI standards until CMP's next
ARP was put in place.
[36] CMP does
have one circuit with only one customer on it.
For our purposes here, we have assumed that this circuit to be a
dedicated private line type circuit.
[37] Maintenance
costs for 2000-2003 do not include the amortization of restoration costs
incurred during the Ice Storm of 1998.
[38] 2001 plant
additions include approximately $10-11 million related to the reversal of
accounting entries for plant not actually retired.
[39] One phase
of polyphase distribution plant refers to those portions of circuit where more
than current is actually being carried on a structure.
[40] The
hypothetical circuit would have been inspected in 1994 under the old program
and would be inspected in 2015 under CMP's new program.
[41] Long term
exposure to overloads of designed equipment ratings will shorten equipment life
resulting in equipment damage or failure causing power quality issues and
interruption of service.
[42] In its
comments, CMP notes that in its 2005 Reliability Improvement, the circuits
identified represented 7% of CMP's system in terms of circuits miles.
[43] Single
contingency refers to an event that results in the loss of a single important
generator source or transmission facility within a transmission system.
[44] A radial
feed is a stand-alone single transmission line or distribution circuit feed
into an area with no connection to an alternative source or back-up feed
through the use of a tie or switching.
[45] In its
comments, BHE noted that this estimate is very preliminary and that detailed
estimates of permitting costs, right-of-way acquisition costs, and line and
substation construction costs have not been completed.
[46] Plant
additions for 1999 and 2003 were adjusted to exclude costs associated with
merchant generation plant interconnections.
[47] For
purposes of BHE's ARP SQI calculations, four service areas were identified.
[48] Bangor
Hydro-Electric Company, Request for Commission Investigation into BHE's ARP
Service Quality Indices, Docket No. 2003-707, Order Approving Stipulation
(April 15, 2004).
[49] In its
comments, BHE noted that it did include a list of the individual circuit SAIFI
and CAIDI performance with its 2002 Annual Reliability Improvement Report but
did not sort the list by performance.
[50] BHE noted
in its comments that while the 50 circuits inspected under the RRP represented
only 28% of the total number of circuits, the circuits inspected serve almost
60% of BHE's customers and cover over 60% of BHE's territory in terms of
circuit miles.
[51] In its
comments filed with the Commission on April 11, 2005, BHE stated that, after
reviewing the suggestions made on pages 7 and 18 of the Liberty Consulting
Group Report that the company should consider separating its roadside
transmission plant from its distribution plant when conducting its reliability
programs, BHE has decided to designate all roadside transmission plant as
special consideration lines which will be inspected every three years instead
of every six years.
[52] Public
Utilities Commission, Inquiry into the Status of the Competitive Market in
Northern Maine, Docket No. 2002-82.
[53] Loring
Bio-Energy, LLC, Request for Emergency Rulemaking to Amend chapter 301, Docket
No. 2004-793, Order Denying Request for Emergency Rulemaking (Jan. 21, 2005).
[54] MPS
requested and was, in part, granted a rate increase in the fall of 2003 in Maine
Public Service Company, Request for Approval of Alternative Rate Plan, Docket
No. 2003-85, Order Approving Stipulation (Part One), (Sept. 3, 2003).
[55] Trees identified as either burning or within 4 feet of
conductors on circuits that were considered as critical or worst
performing.
[56]
“2004/2005 Winter Assessment – Reliability of the Bulk Electricity Supply in
North America,” NERC, November 2004
[57] “Blackout 2003 – Performance of the New England and Maritimes
Power Systems During the August 14, 2003 Blackout,” ISO-NE, February, 2004.
[58] “Restoration of the NPCC Areas Following the Power
System Collapse of August 14, 2003,” NPCC Inter-Control Area Restoration
Coordination Working Group (CO-11), 2004.
[60] Statement
by Dave Hilt, NERC Vice President, Compliance, NERC Regulatory Webcast
Briefing, October 28, 2004.
[61] “Control Area Readiness Audit Report -ISO New England,” NERC,
July 29, 2004.
[62] Reactive
power supports the voltages that must be controlled for system
reliability. Sources of reactive power
include generators, capacitors and static var compensators (SVCs). One market issue related to reactive power
is that although such power must be generated to maintain system reliability,
it is often not treated in market transactions equally with power generated for
wholesale or retail sale.
[63] Cyber
security relates to the actual or potential compromise of the electronic or
physical security perimeter or the operation of a programmable electronic
device or communications network, including hardware, software, and data,
associated with bulk electric system assets.
[64] This
event is described in detail in the “Final Report on Electricity Supply
Conditions in New England During the January 14 – 15, 2004 ‘Cold Snap’,” ISO-NE
Market Monitoring Department, October 12, 2004.
[65] “Cold Snap Response – Actions
Taken To Protect Reliability In New England”,
Stephen G. Whitley, ISO-NE Senior Vice President & COO
presentation to ISO-NE Fuel Diversity Working Group, November 3, 2004.
[66]
“2004/2005 Winter Assessment – Reliability of the Bulk Electricity Supply in
North America,” NERC, November 2004.
[67] “ISO
New England’s Management Response to the October 12, 2004 publication entitled Final
Report on Electricity Supply Conditions in New England during the January 14 -
16, 2004 ‘Cold Snap’,” ISO-NE, October 12, 2004.
[68] ISO-NE
Planning Procedure No. 3 - Reliability Standards for the New England Area Bulk
Power Supply System.
[69] 35-A
M.R.S.A. § 301(1).
[70] The U.S.
General Accountability Office (GAO), recently changed its name from the
U.S. General Accounting Office.
[71] “Critical
Infrastructure Protection – Challenges and Efforts to Secure Control Systems,” GAO-04-354,
U.S. General Accountability Office, March 2004
[72] LCCs were
previously known as satellite control centers.
[73] Because
of the highly sensitive nature of specific security measures to protect key
utility critical infrastructure and systems, this report addresses only the
process undertaken by the State to review those measures, and not the specific
details of actions taken by utilities or law enforcement agencies to enhance
the security of that infrastructure.
[74] The
National Association of Regulatory Utility Commissioners (NARUC) Ad Hoc
Committee on Critical Infrastructure.