PUBLIC UTILITIES COMMISSION                                     Docket No. 2003-370

 

                                                                                                June 26, 2003

 

BANGOR HYDRO-ELECTRIC COMPANY                      

CENTRAL MAINE POWER COMPANY                           

Request for Approval of Standard Form                           

Contracts (Revisions to Agreement)

 

ORDER APPROVING REVISIONS

TO STANDARD OFFER STANDARD

FORM CONTRACT

 

WELCH, Chairman; NUGENT and DIAMOND, Commissioners

 

 

            On May 21, 2003, Central Maine Power Company (CMP) filed proposed revisions to the Standard Offer Standard Form Contract and to its exhibits.  CMP indicated that the proposed revisions are of a housekeeping nature, such as changing dates and providing correct references to NEPOOL requirements.

 

            On May 30, 2003, Bangor Hydro-Electric Company (BHE) filed proposed revisions to its exhibits to the Standard Form Contract.  Except for a proposed change to the uncollectible amounts, BHE’s revisions are also of a housekeeping nature.  BHE proposes to reduce the uncollectible amount for the large class from 0.21% to 0.02% to reflect more recent experience.

 

            I have reviewed the proposed changes to the language of the contract and exhibits and find them to be reasonable.  I also conclude that BHE’s proposed change to the uncollectible amount for the large class is generally consistent with recent write-off levels for the class.  Accordingly, I approve revisions proposed by CMP and BHE.

 

BY ORDER OF THE DIRECTOR OF TECHNICAL ANALYSIS

 

 

 

____________________________________

Faith Huntington

Acting Director