Utility
Coordination Process
The
following outlines a typical utility coordination process as it
relates to a project development process funded with state and/or
federal dollars administered through the Maine Department of Transportation
(hereinafter “Department”). Any references to a “Utility Coordinator”
refer to the person who is responsible for assuring that proper
utility and railroad coordination occurs on a given project. This
may be a MaineDOT employee, a town/city employee, or a consultant
acting on behalf of either party. Any references to Letters #1-7
refer to standard letters that are routinely mailed out to utility
or railroad companies at a particular stage of a project. Templates
of these letters are available on the Department's Utilities Web
Site, located at the following address: http://wwwmdot/mdot/utilities/coordpage.php
General
Utility Coordinator Responsibilities:
The Utility Coordinator will participate as an active member of
the project team.
The Utility Coordinator will meet with utility and railroad (hereinafter
“RR”) contacts as necessary to identify and resolve all utility
and railroad issues and/or conflicts relating to the project and
the Department's current policies.
The Utility Coordinator will provide information to utility and
railroad contacts as early as possible to provide the maximum notice
possible.
If the Utility Coordinator is a consultant working for the Department,
the Utility Coordinator shall keep a predefined Department representative
informed of all coordination activities by:
Copying that individual on all utility/RR related project correspondence,
and
Inviting that individual to critical utility/RR coordination meetings.
This
predefined contact will be responsible for providing general oversight
of the coordination process and for the review and processing of
any necessary utility/RR agreements to be signed by the Department.
General
Utility Coordination Process:
Identify Utilities
Verify Facility Information
Preliminary Utility Comments, Conflicts, and Relocation Strategy
Identify Specific Underground Facility Locations
Final Facility Impacts, Relocation Strategy and Agreements
Prepare Utility Specification and Certification
Oversee Utility Relocation Schedule
Detailed
Utility Coordination Process
I.
Identify Utilities
Prior
to Project Kickoff:
A Property Office representative will research the
Department's utility and railroad database to obtain a list of contact
names, addresses and phone numbers for all utility and railroad
companies located in the City/Town of the proposed project. This
information may be obtained from the Department's Utilities Web
Site at the following address: http://dot0dta1asora14.mdot.w2k.state.me.us:7778/reports/rwservlet?cmdkey=ut
A Property Office representative will obtain a list
of contact names, addresses, and phone numbers for any applicable
municipal officials in the project town(s).
A Property
Office representative will mail an initial
utility contact letter (Letter #1) to all utilities, railroads and
municipalities within the City/Town of the proposed project to determine
the following:
Whether or not the addressee has existing facilities
within the project area and, if so, the type of facilities;
Whether or not the addressee intends to construct
facilities within the project area over the next five years;
The name of the individual that will be available
to mark any existing facilities prior to the project survey;
The
name of the individual with whom the project team can coordinate
throughout the project.
- A Property Office representative will input the Letter #1 information
into the Utility Database for the project for which it relates.
Project Kickoff:
- The Utility Coordinator will obtain the Letter #1 information
from the Utility Database.
Compile
Preliminary Data:
The Utility Coordinator will research the Department's
accident data for any issues relating to the location of utility
facilities. This information may be obtained from the Project Manager
or from the Department's Traffic Engineering Division (624-3620).
The Utility Coordinator will coordinate with the
project team's Right-of-Way representative to obtain any available
right-of-way information.
The Utility Coordinator will determine whether or
not there are any Department-owned traffic facilities within the
project limits and will determine how those facilities will be handled
throughout the development of the project. If the traffic facilities
will not be modified as part of the project contract, the Utility
Coordinator shall coordinate with a Department traffic representative
as though they were a separate utility throughout the project. A
list of the Department's traffic facilities is available at: http://www.maine.gov/mdot/traffic-counts/equip-loc-town.php
For any railroad crossings, the Utility Coordinator
will communicate with the Department's Multimodal Program (624-3420)
to determine if any work is planned for the crossing in concern.
If the railroad corridor is owned by the State of Maine
, similar communication shall also occur with
the Department's Office of Freight (624-3560).
Initial
Field Review:
The Utility Coordinator will make an initial site
visit to identify (with documentation and photographs as necessary)
the following:
Visible utility facilities on the project;
Typical offset of the utility poles;
Whether all of the appropriate utilities were contacted
with the initial utility contact letter (Letter #1);
Features that may affect/limit utility relocations
(i.e. buildings close to the highway, shade trees, etc…);
Major utility installations that may be costly to
relocate (i.e. substations, critical poles, telephone switching
stations, pump stations, etc…);
Utility facilities that may be located on their own
easements;
Proximity of any RR corridors to the project and
the status and condition of any RR crossings;
Overhead clearance issues around bridges or major
drainage structures;
Any other pertinent information.
Initial
Team Meeting
The Utility Coordinator will attend the Initial Team
Meeting and provide a summary of the critical issues identified
in the previous steps. If the Initial Team Meeting occurs before
the above-mentioned work, a summary of critical issues shall be
distributed to the team after-the-fact.
If applicable, the Utility Coordinator will provide
a proposed budget to complete the utility and railroad coordination
for the project within the time frame identified at the meeting.
II.
Verify Facility Information
Preliminary
Public Meeting/Survey Plan Available:
The Utility Coordinator will attend the Preliminary
Public Meeting as applicable on projects where significant utility
or railroad involvement is anticipated or when requested by the
Project Manager.
The Utility Coordinator will mail copies of the existing
topographic survey plans (which may or may not include an initial
proposed horizontal and vertical alignment) to all utility and railroad
contacts for their review and comment. A letter shall accompany
the survey plans requesting verification of the existing facilities
indicated on the plan and any concerns that may exist (Letter #2).
The Utility Coordinator will coordinate with the
project team's Survey representative for any additional survey identified
from the Letter #2 mailing.
III.
Prelim. Utility Comments, Conflicts, and Relocation Strategy
Horizontal/Vertical
Alignment Available:
When the centerline of the highway is to be modified,
the Utility Coordinator will distribute plans indicating the proposed
horizontal and vertical alignment to all affected utilities and
railroads within the proposed project for their comments (if not
addressed with the survey plan distribution).
If the RR or utilities express alignment concerns,
the Utility Coordinator shall provide a written summary of those
concerns to the Project Manager and other team members as applicable.
The Utility Coordinator is responsible for assuring that all concerns
are addressed to a conclusion and that all parties are aware of
what the conclusion is.
Preliminary
Plan Available/ Formal Public Contact:
The Utility Coordinator will write a summary of the
utility and railroad issues associated with the proposed project
and submit them to the Project Manager for inclusion in the Preliminary
Design Report (PDR).
Depending upon the extent of the utility and/or RR
work, the Utility Coordinator will meet with
or, at least, communicate with the utilities to identify how utility
work will generally be undertaken. Discussions shall include the
right-of-way needs to accommodate the utility facilities.
The Utility Coordinator will work with the project
team to determine the proposed right-of-way limits/needs.
The Utility Coordinator will attend the Preliminary
Public Meeting as required. (Factors that will require the Utility
Coordinator's attendance at the preliminary public meeting include:
extensive utility relocation, significant trimming or shade tree
removal necessitated by the utilities, utility impacts on a controversial
right-of-way width, or requests by the Project Manager for utility
representation).
The Utility Coordinator will distribute preliminary
plans to the utilities & railroads for a more detailed determination
of impacts (Letter #3). As a result of the preliminary plan distribution,
the Utility Coordinator will determine the need for any agreements
with the railroad(s) or utilities.
IV.
Identify Specific Underground Facility Locations
Drainage
Plans Available
The Utility Coordinator shall identify locations
where utility test pits are required to obtain the specific depth
of underground facilities that may conflict with the proposed design.
The Utility Coordinator shall review the proposed test pit locations
with the project team and then coordinate with the utilities and
Survey for the work to be accomplished .
V.
Final Facility Impacts, Relocation Strategy and Agreements
75%-80%
Plans Available/Precoordination Meeting:
The Utility Coordinator will provide all affected
utility and railroad companies with 75% - 80% plans for review and
comment (Letter #4).
The Utility Coordinator will hold and moderate a
Utility Precoordination Meeting to review utility and railroad impacts
and relocations in the field and to discuss proposed schedules for
the relocations (Letter #4).
Following the Precoordination Meeting, the Utility
Coordinator will prepare and distribute written minutes from the
Precoordination Meeting, including any significant comments from
the affected utility or railroad companies.
The Utility Coordinator will prepare and distribute
the draft railroad and utility Special Provisions (Letter #5).
The Utility Coordinator will prepare any draft agreements
and initiate the agreement approval process.
VI.
Prepare Utility Specification and Certification
Project
to Contracts:
The Utility Coordinator will provide the final railroad
and utility Special Provisions to the Project Manager with a certification
that all necessary arrangements have been made. A template certification
form is available at: http://www.maine.gov/mdot/utilities/coordination/certification.pdf
The Utility Coordinator will fill out a “Location
Permit for Projects” form to document the approved utility locations
resulting from the utility coordination process. This form may be
found at http://www.maine.gov/mdot/utilities/coordination/projperm.doc
and is to be sent to the address indicated on the form with all
associated attachments .
If the Utility Coordinator needs to authorize utilities
to relocate facilities well before project advertising, the Utility
Coordinator should consult with the Utility & Railroad Services
Manager to see if the Department should issue a “Letter of Premature
Investment” (LOPI) to all affected utilities.
Advertise
and Award:
The Utility Coordinator will provide guidance to
the Project Manager to resolve questions from contractors relating
to railroads and utilities during the bidding phase of the project.
VII.
Oversee Utility Relocation Schedule
Preconstruction:
Upon notification from the Department's Construction
Resident of a Preconstruction Meeting, the Utility Coordinator shall
schedule a joint Preconstruction Utility Meeting with the affected
utilities and railroad(s) (Letter #6).
The Utility Coordinator will attend the Preconstruction
Meeting and chair the joint Preconstruction Utility Meeting to coordinate
the utility schedules with the Contractor's schedule.
Following the Preconstruction Utility Meeting, the
Utility Coordinator shall prepare and distribute written minutes
to all utilities and railroads on the project, the Contractor, and
the Construction Resident (Letter #7).
Construction:
The Utility Coordinator will work directly with the
Construction Manager to resolve any utility or railroad issues that
arise during construction.
The Utility Coordinator shall work with the Construction
Manager to work out an understanding of how the utility work schedule
will be tracked to assure that work does not slip beyond anticipated
dates.
|