Turner Center Bridge Design Build Project
Welcome to the Turner Center Bridge Design Build Project website.
Contact Information
George Macdougall , Assistant Contracts Engineer
Maine Department of Transportation
Bureau of Project Development
16 State House Station
Augusta, ME 04333-0016
E-mail: George.Macdougall@maine.gov
Facsimile: 207-624-3431
Preliminary Project Schedule
- Preliminary Public Meeting: April 14, 2010
- Informational Public Meeting: February 8, 2011
- MaineDOT Issues RFI: January 25, 2012
- Deadline for Design-Builders to Submit Questions on RFI February 1, 2012 at 3:00 PM EDT
- MaineDOT Issues Responses to Questions Received on the RFI February 15, 2012
- Deadline for Design-Builders to Submit SOI March 14, 2012 at 3:00 PM EDT
- MaineDOT Issues Notification of SOI Responsiveness of to Design-Builders March 28, 2012
- Deadline for Design-Builders to Submit Cure for SOI Responsiveness (If Applicable) March 30, 2012
- MaineDOT Evaluates and Ranks SOIs and Notifies Design-Builders of Selection Results April 18, 2012
- MaineDOT Issues Draft RFP: May 2, 2012
- Deadline for Design-Builders to submit Questions on the Draft RFP May 9, 2012 at 3:00 PM EST
- MaineDOT Issues Responses to Draft RFP Questions May 23, 2012
- MaineDOT Issues Final RFP June 6, 2012
- Begin Date for Design-Builders to Submit ATC Proposals June 7, 2012
- Begin Date for Design-Builders to Submit Questions on Final RFP June 7, 2012
- Design-Builders Attend Mandatory One-On-One Meetings with MaineDOT One Meeting Per Team between June 11 and June 15, 2012
- Deadline for Design-Builders to Submit Questions Final RFP June 20, 2012 at 3:00 PM EDT
- MaineDOT Issues Responses to RFP Questions July 5, 2012
- Final Deadline for Design-Builders to Submit ATC Proposals July 18, 2012 at 3:00 PM EDT
- MaineDOT Issues Responses to ATC Proposals August 1, 2012
- Deadline for Design-Builders to submit RFIs. August 1, 2012
- Deadline for Design-Builders to Submit Technical and Price Proposal Packages August 15, 2012 at 3:00 PM EDT
- MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders September 5, 2012
- Deadline for Design-Builders to Submit Cure for Technical Responsiveness (If Applicable) N/A
- Deadline for Design-Builders to Submit Proposal Guaranty Package September 12, 2012 at 11:00 AM EDT
- MaineDOT Opens Price Proposals September 12, 2012 at 11:00 AM EDT
- MaineDOT Awards Contract October 2012
- Design-Builder Begins Construction Fall 2012
- Design-Builder Completes Construction December 31, 2014
This page last updated on
9/5/12