Turner Center Bridge Design Build Project

Welcome to the Turner Center Bridge Design Build Project website.

Contact Information

Scott Bickford, Contracts and Specifications Engineer
Maine Department of Transportation
Bureau of Project Development
16 State House Station
Augusta, ME 04333-0016

E-mail: scott.bickford@maine.gov
Facsimile: 207-624-3431

Preliminary Project Schedule

  • Preliminary Public Meeting: April 14, 2010
  • Informational Public Meeting: February 8, 2011
  • MaineDOT Issues RFI: January 25, 2012
  • Deadline for Design-Builders to Submit Questions on RFI February 1, 2012 at 3:00 PM EDT
  • MaineDOT Issues Responses to Questions Received on the RFI February 15, 2012
  • Deadline for Design-Builders to Submit SOI March 14, 2012 at 3:00 PM EDT
  • MaineDOT Issues Notification of SOI Responsiveness of to Design-Builders March 28, 2012
  • Deadline for Design-Builders to Submit Cure for SOI Responsiveness (If Applicable) March 30, 2012
  • MaineDOT Evaluates and Ranks SOIs and Notifies Design-Builders of Selection Results April 18, 2012
  • MaineDOT Issues Draft RFP: May 2, 2012
  • Deadline for Design-Builders to submit Questions on the Draft RFP May 9, 2012 at 3:00 PM EST
  • MaineDOT Issues Responses to Draft RFP Questions May 23, 2012
  • MaineDOT Issues Final RFP June 6, 2012
  • Begin Date for Design-Builders to Submit ATC Proposals June 7, 2012
  • Begin Date for Design-Builders to Submit Questions on Final RFP June 7, 2012
  • Design-Builders Attend Mandatory One-On-One Meetings with MaineDOT One Meeting Per Team between June 11 and June 15, 2012
  • Deadline for Design-Builders to Submit Questions Final RFP June 20, 2012 at 3:00 PM EDT
  • MaineDOT Issues Responses to RFP Questions July 5, 2012
  • Final Deadline for Design-Builders to Submit ATC Proposals July 18, 2012 at 3:00 PM EDT
  • MaineDOT Issues Responses to ATC Proposals August 1, 2012
  • Deadline for Design-Builders to submit RFIs. July 25, 2012
  • Deadline for Design-Builders to Submit Technical and Price Proposal Packages August 15, 2012 at 3:00 PM EDT
  • MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders September 5, 2012
  • Deadline for Design-Builders to Submit Cure for Technical Responsiveness (If Applicable) September 12, 2012
  • Deadline for Design-Builders to Submit Proposal Guaranty Package September 19, 2012 at 11:00 AM EDT
  • MaineDOT Opens Price Proposals September 19, 2012 at 11:00 AM EDT
  • MaineDOT Awards Contract October 2012
  • Design-Builder Begins Construction Fall 2012
  • Design-Builder Completes Construction July 10, 2015


This page last updated on 5/2/12