Kittery-Portsmouth Sarah Mildred Long Bridge Replacement Project

Home > Process and Schedule

Process and Schedule

MaineDOT plans to replace the existing Sarah Mildred Long Bridge through the alternative project delivery method known as the Construction Manager/General Contractor (CM/GC) process.

The CM/GC process allows an owner (represented by MaineDOT) to engage a contractor, known as a Construction Manager, to provide constructability input during the design process.  The intent is to form a partnership among the Owner, the Construction Manager, and the Design Consultant. The “Stakeholders Group” is also an integral partner to ensure the bridge design reflects the interests, personality and aesthetics of the community whenever practicable.

 

Preliminary Project Schedule
  • Preliminary Design Complete:  June 2013
  • Final Plans, Specifications, and Estimates Complete:  September 2014
  • Construction Begins:  Spring 2015
  • New Bridge Opens to Traffic: November, 2017
  • Construction Complete: Spring, 2018

Stakeholder Meeting and Workshop Schedules

  • Stakeholder Meeting: January 2013
  • Design Workshop: April 2013
  • Stakeholder Meeting: May 2013
  • Design Workshop: June 2013
  • Stakeholder Meeting: September 2013
  • Please Note:
    • Stakeholder Meetings are for input and information
    • Design Workshops are cross section of the community to work with design team on selecting bridge features for final aesthetics

This is a graphic showing the upcoming meeting and workshop dates

 

This page last updated on 2/1/13