Falmouth-Portland Martin's Point Bridge Replacement Project

The Contract for this project was awarded to CPM Constructors on June 8, 2012


This project is the replacement of Martin's Point Bridge located on US Route 1 between Falmouth and Portland, Maine, and it will be delivered using the Best Value Design-Build procurement process.

Leanne Timberlake, P.E.
Project Manager
Maine Department of Transportation
Bureau of Project Development
16 State House Station
Augusta, ME 04333-0016

E-mail: leanne.timberlake@maine.gov


Preliminary Project Schedule

  • Preliminary Public Meeting: February 25, 2010
  • Informational Public Meeting: July 2011
  • MaineDOT Issues RFQ: July 20, 2011
  • MaineDOT Issues Draft RFP: September 15, 2011
  • Deadline for Design-Builders to Submit Draft RFP Questions and/or Comments: September 22, 2011 at 3:00 PM (EDT)
  • Deadline for Design-Builders to Submit Supplemental Boring Requests: September 22, 2011 at 3:00 PM (EDT)
  • MaineDOT Issues Responses to Draft RFP Questions and/or Comments: September 30, 2011
  • MaineDOT Issues Final RFP: October 14, 2011
  • Begin Date for Design-Builders to Submit ATC Proposals: October 17, 2011
  • Design-Builders Attend Mandatory One-On-One Meetings with MaineDOT: One Meeting Per Team Between October 17-21, 2011
  • Deadline for Design-Builders to Submit Final RFP Questions and/or Comments: October 26, 2011 at 3:00 PM (EDT)
  • MaineDOT Issues Responses to Final RFP Questions and/or Comments: November 2, 2011
  • Anticipated NEPA Complete Date: On or about mid to late November 2011
  • Anticipated Date for Receipt of Permit: On or about late November to early December 2011
  • MaineDOT Issues Supplemental Geotechnical Data Report (SGDR): On or about December 21, 2011
  • Final Deadline for Design-Builders to Submit ATC Proposals: Janaury 25, 2012 at 3:00 PM (EDT)
  • MaineDOT Issues Final Responses to ATC Proposals: February 1, 2012
  • MaineDOT Issues Revised RFP: March 2, 2012
  • Deadline for Design-Builders to Submit Revised RFP Questions and/or Comments on Revisions: March 9, 2012 at 3:00 PM (EST)
  • MaineDOT Issues Responses to Revised RFP Questions and/or Comments on Revisions: March 16, 2012
  • Deadline for Design-Builders to Submit Technical and Price Proposal Packages: April 2, 2012 at 3:00 PM (EDT)
  • MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders: April 9, 2012
  • Deadline for Design-Builders to Submit Cure for Technical Responsiveness (if applicable): April 17, 2012
  • MaineDOT’s Scoring Committees Evaluate and Score Technical Proposals: April-May 2012
  • Deadline for Design-Builders to Submit Proposal Guaranty Package: May 9, 2012 at 11:00 AM (EDT)
  • MaineDOT Opens Price Proposals and Final Technical Scores and Calculates Best Value Score:  May 16, 2012 at 11:00 AM (EDT)
  • MaineDOT Awards Contract: Late May-Early June 2012
  • Design-Builder Begins Construction: Fall 2012
  • Design-Builder Completes Construction: December 31, 2014