Lane Closures Continue On I-295 Northbound Project Through October 8

 

Starting Monday, September 28, there will be lane closures on I-295 Northbound from approximately 1 mile north of Exit 28 in Brunswick to Exit 31 in Topsham. This lane closure will begin on September 28 and continue until Thursday, October 8. This lane closure will be in place 24 hours a day. Additional daytime lane closures will occur on I-295 Northbound and Southbound between Topsham and Gardiner as finishing work is completed on the I-295 Northbound Rehabilitation project.

Work is also scheduled for the Exit 28 on- and off-ramps on both I-295 Northbound and Southbound. This work will not necessitate lane closures but may delay traffic due to construction activity. The ramp work schedule is as follows:

  • September 25 through October 3: Exit 28 off-ramp (northbound) & Exit 28 on-ramp (southbound)
  • September 26: Exit 28 on-ramp (northbound)

When driving through these work zones, please curtail cell phone use and be aware of changing traffic patterns, slow moving construction vehicles and construction personnel.

For more information, please visit www.mainedot.gov.


# # #