Howland Piscataquis River Bridge Design-Build Replacement Project
The RFQ for this project has been revised as of May 8, 2009 (web page)
This project carries Coffin Street over the Piscataquis River in Howland. The bridge is located .1 miles from Route 6.
In order to be registered for any follow up mailings and be allowed to submit an SOQ, a Letter of Interest must be submitted via U.S. Mail, E-mail, or facsimile to:
Scott Bickford, Contracts and Specifications Engineer
Maine Department of Transportation
Bureau of Project Development
16 State House Station
Augusta, ME 04333-0016
E-mail: scott.bickford@maine.gov
Facsimile: 207-624-3431
Preliminary Project Schedule
Please note: The Project schedule dates have been updated. The updated dates are shown below in red.
- MaineDOT issues Draft RFP: October 28, 2009
- Deadline for Design-Builders to submit Supplemental Boring Requests: November 4, 2009 at 3:00 PM (EST)
- MaineDOT begins Supplemental Exploration Program: on or about November 9, 2009
- Deadline for Design-Builders to submit Comments and Questions on Draft RFP: November 18, 2009 at 3:00 PM (EST)
- MaineDOT Issues Responses to Questions Received on Draft RFP: December 9, 2009
MaineDOT completes Final Supplemental Geotechnical Data Report: December 30, 2009
- MaineDOT Issues final RFP: December 16, 2009
- Deadline for Design-Builders to submit questions on final RFP:
December 23, 2009 at 3:00 PM (EST)
- MaineDOT issues Responses to Questions Received on Final RFP: January 6, 2010
- Deadline for Design-Builders to Submit Proposals: February 18, 2010 at 3:00 PM (EST)
- Price Proposal Bid Opening: March 31, 2010 at 11:00 AM (EDT)
- MaineDOT Awards Contract: April-May, 2010
- Begin Construction: August-September, 2010
- Complete Construction: October, 2012