Skip Maine state header navigation

Agencies | Online Services | Help

Skip First Level Navigation | Skip All Navigation

South Bristol "Gut Bridge" Replacement Project


Navigation Channel Closure

The Maine Department of Transportation and Cianbro Corporation will be closing the navigation channel under The Gut Bridge in South Bristol Maine on the following dates:

December 2014 Closure Dates and Times
   
  • Thursday December 11th 9:00am - 3:00pm
  • Friday December 12th 9:00am - 3:00pm
  • Saturday December 13th 9:00am - 3:00pm
  • Sunday December 14th None
  • Monday December 15th 9:00am - 3:00pm
  • Tuesday December 16th 9:00am - 3:00pm
  • Wed December 17th 9:00am - 3:00pm
  • Thursday December 18th 9:00am - 3:00pm
  • Friday December 19th 9:00am - 3:00pm
  • Saturday December 20th 9:00am - 3:00pm
  • Sunday December 21st None

Weekly updated closure schedules with specific dates and times will be posted at the following locations in South Bristol, ME; Gamage Shipyard, Osier’s Wharf, and the South Bristol Fisherman’s Co-Op. Weekly updated closure schedules will also be posted this project website.

 


Weekly Highlights
: December 12, 2014

  • Cianbro completed stripping formwork from wall 4A and worked on fabricating a work platform for the drill rig for the rock anchor installation.
  • Sheet pile were installed for cofferdams 1 & 3.
  • Some excavation was started behind the cofferdams to assist with the installation of sheet pile and tiebacks.
  • Plain riprap was trucked in and placed temporarily for access and will be placed in front of the cofferdam in its final position as work progresses.

 

General Project Information

The contract to build the Gut Bridge was awarded to Cianbro Corporation, Pittsfield, Maine on June 30, 2014.  Their bid for the project came in at $10,995,622. The project includes the bridge replacement and construction of an operator’s house, new traffic warning systems, and some approach work.   

Cianbro will begin to mobilize to the site Sept 8, 2014 and will be constructing the new retaining walls/abutments that are adjacent to the existing bridge.  This will, at times, require alternating, one-way traffic. Motorists should expect delays. The project will shut down in mid-January, 2015 due to federal in-water work restrictions.  The project will re-mobilize in 2015 after the community weekend celebration scheduled for July 17-19th. At that time, the contractor will complete preparations for installing the temporary bridge and implement the channel closure which is scheduled to begin September 10, 2015.

During the 213 days allowed for the channel closure, we will open the temporary bridge to traffic, demo the existing bridge, construct the new bridge and remove the temporary bridge.  It is anticipated that the new Gut Bridge will open it to traffic in April, 2016.  After that time, work will continue including constructing the approaches, dirt work, paving, etc.   The contract completion date is November 15, 2016, though MaineDOT is optimistic that it will be completed during the summer months.

For more information, please contact Stephen Bodge.

 

This page last updated on 12/11/14

free document readers

 

If your web browser or screen reader cannot view the documents that are listed on this page, please visit the Contact Page.