Freeport RT 125/136 Design Build Project

The RFP has been amended as of May 29, 2009 (web page)

The Freeport – Route 125/136 Project, MaineDOT PIN: 012782.00, includes the design and reconstruction of 3.03 miles of Major Urban Collector in the Town of Freeport.

The Project starts at the intersection of Durham Rd. and Rte. 136/Mallet Dr. and continues 3.03 miles northerly to the Durham Town line. The Project includes intersection improvements at Durham Rd. and Rte. 136/Mallet Dr., intersection improvements at Rte. 136/Durham Rd. and Rte. 125/Griffin Rd., minor vertical and horizontal corrections throughout the Project length, and drainage improvements.

The Collins Mill Bridge (#2167) is contained within the Project limits; replacement of the Collins Mill Bridge is not required as part of the Project. Alignment corrections are anticipated in the area of the Collins Mill Bridge, these corrections may require modifications to the structure.

Project Schedule

  • Draft RFP Issue for Comment February 18, 2009
  • Identify Supplemental Boring Locations March 4, 2009
  • Submit Questions March 4, 2009
  • Final RFP Issue Date March 18, 2009
  • Results of Supplemental Borings March-April 2009
  • Deadline for Proposer Questions May 8, 2009
  • Technical Proposal Preliminary Submission & Design Exception Submission May 13, 2009
  • Notice of Technical Proposal Responsiveness & Design Exception Notification May 29, 2009
  • Cure Deadline for Technical Defects (Final Submission of Technical Proposal) June 19, 2009
  • Price Proposal Due Date June 19, 2009
  • Opening of Price Proposals & Technical Scores, Determination of Best-Value Rating, Determination of Apparent Successful Proposer July 22, 2009
  • Final Determination of Responsiveness, Award of Contract August 14, 2009
  • Construction to Begin on August 24, 2009

After proposers have been notified and prior to draft RFP issue, the Department will hold a joint meeting with the selected proposers to discuss the Project.

 

This page last updated on 10/22/09