Project Advertising Schedule (12 month period)

(Updated July 13, 2009, and sorted by date. To see list sorted by town, click here.)

This report lists construction projects expected to advertise in the indicated month. It is subject to revision as projects are more fully developed. Any problems with this web page may be reported to Larry at 207·624·3331 / larry.childs@maine.gov.

Search Tip: You can quickly find projects containing certain words by using your web browser's Edit/Find function from the menu or Ctrl+F from your keyboard.


FORECAST  TOWN(S) &                                                                                          ESTIMATED
ADVERTISE PIN                   SCOPE           ROUTE/LOCATION  DESCRIPTION                                       COST
========= ===================== =============== =============== ======================================== =============
Jul 2009  PIN 017611.00         Other Highway   Acadia National Pavement Preservation; Shim, Overlay;               $0  
Maintenance Park Resurface parking lots for Ikes Beach;
Acadia Mtn, Thompson Isle Info Center;
St Sauveur Mountain; Beech Mtn and Bass
Harbor Light House. Acadia NPS Rtes
227(0-0.47),230(0-0.41),231(0-0.33), 237
(0-0.41),245(0-0.25).


Jul 2009 Auburn Other Highway State Route 136 Auburn, Route 136, Highway Realignment $1,009,000
PIN 016637.20 Maintenance and upgrade: including subbase, shoulder
construction, minor span installation,
and riverbank slope stabilization,
located 0.25 miles north of
Durham/Auburn TL & extending ½ mile
northerly on Route 136. Smith


Jul 2009 Augusta Striping US 202 Striping and Delineation on Western $100,000
PIN 017567.00 Avenue and on Western Avenue at the I-95
Ramp.


Jul 2009 Bowdoinham Bridge Removal Harwards Bowdoinham, Harwards Crossing Br. # $3,000,000
PIN 015091.00 Crossing 3273, located 4.6 miles NE of JCT. Route
125 on Route 24


Jul 2009 Brooks Reconstruction St Rte 139 Beginning at Route 7 extending westerly $275,000
PIN 012717.00 0.35 miles to 0.13 miles west of School
Street


Jul 2009 Brooks Strut Route 139 Brooks, Route 139, Strut widening $116,500
PIN 014309.00 Replacement (within limits of PIN 12717.00 Brooks,
Route 139 CIP project which is to be
constructed in 2007.) Located approx.
0.09 mile westerly of the intersection
of Route 7


Jul 2009 Brunswick New Off Safe Routes to School sidewalk $70,000
PIN 016339.00 Construction improvements on Richards Drive near the
Coffin Elementary School and the
Brunswick Junior High School.


Jul 2009 Durham Bridge Culvert Runaround Runaround Bridge (6006) over Runaround $383,256
PIN 015603.00 Replacement Pd Outlet, located 1.16 miles northerly
of Pownal town line.


Jul 2009 Fort Kent Reconstruction US Route 1 This project will rehabilitate the $275,000
PIN 011673.00 highway surface at the Route 1
Highway/Railway Crossing (#051157V)
located approximately 1.5 miles west of
the Frenchville town line on the
Montreal, Maine & Atlantic Railway
System.


Jul 2009 Gray New Other Safe Routes to School pedestrian and $20,000
PIN 016342.00 Construction bicycle improvements. Audible
Pedestrian Coundown Signals and
Duratherm Crosswalk at Gray
Intersection.


Jul 2009 Naples Bridge Deck Naples Bay Naples, Naples Bay Bridge # 2047, Fiber $400,000
PIN 011060.01 Replacement Reinforced Polymer Bridge Deck


Jul 2009 North Yarmouth New Off Safe Routes to School improvements. $38,900
PIN 016344.00 Construction School Zone flashing lights at North
Yarmouth Memorial k-8 school on Route 9
in North Yarmouth. Duratherm Crosswalks
at two locations. One Pedestrian
Activated Flashing Light.


Jul 2009 Orono New Off New Section of bike/ped path a distance $280,000
PIN 016134.00 Construction of q.85 miles from Stewart Commons to
Park Street.


Jul 2009 Portland, South Bridge Veterans South Portland, On US 1, Veterans $50,000,000
Portland Replacement Memorial Memorial Bridge # 3945, located on the
PIN 015106.00 townline over the Fore River & PTRR


Jul 2009 Rockport Miscellaneous X US route 1 traffic calming intersection $50,000
PIN 015700.03 Safety improvements and mobile radar speed sign
Improvements purchase


Jul 2009 Sidney Rest Area Other Lengthening the ramp to allow WIM $880,000
PIN 013142.00 Construction/Im screening on commercial vehicles.
provements


Jul 2009 Unity New Off-System This project will design and construct $325,000
PIN 010234.00 Construction 0.81 KM (0.50 MI) of a shared-use path
from the Unity College Campus to
Downtown Unity.


Jul 2009 Weston Strut Maint C560i Div REPLACE STRUCTURE AT TROUT BROOK ON THE $115,160
PIN 015968.00 Replacement 1 BANCROFT RD ( C560I
)AT RLM 12.82.


Jul 2009 Winslow New Off Winslow Connector Trail from the Mill $325,000
PIN 016132.00 Construction Road, adjacent to the 2 Cent Bridge to
Benton Avenue.


Jul 2009 Woolwich Signal Old Meadow Rd Installation of warning lights and gate $151,424
PIN 015962.00 Improvements(Ra at the MERR railroad crossing on Meadow
il/Highway Road. Crossing Number 364963.
Xing)


Jul 2009 Yarmouth Mill And Fill St Rte 88 Highway resurfacing and widening: $998,550
PIN 013124.00 Plus Beginning at Princes Point Road and
extending 1.63 miles to Route 1.


Jul 2009 Yarmouth New St Rte 88 Sidewalk Rehabilitation: Lafayette $70,000
PIN 013125.00 Construction Street from Pleasant Street to Main
Street, and on East Main Street from
Main Street to Spring Street. New
sidewalk Construction: Spring Street
from East Main Street to Bayview Street.
Jul 2009 New St Rte 88 Sidewalk Rehabilitation: Lafayette $70,000
Construction Street from Pleasant Street to Main
Street, and on East Main Street from
Main Street to Spring Street. New
sidewalk Construction: Spring Street
from East Main Street to Bayview Street.


Jul 2009 Yarmouth New Off Safe Routes to School bicycle and $71,000
PIN 016347.00 Construction pedestrian improvements. Shared use
path from Oakwoods Dr to McCartney St
including a connection between Yarmouth
Elem and Harrison Middle School.


Aug 2009 Bangor Intersection Summer St Bangor, Route 1A, Intersection $1,285,000
PIN 015117.00 Improvements Reconstruction - Realignment of Main,
W/O Signal Cedar and Summer St. DEMO ID ME 069


Aug 2009 Bethel New Off Safe Routes to School pedestrian $96,460
PIN 016353.00 Construction improvements near Crescent Park School
on Crescent Street and Mason street.


Aug 2009 Carmel Bridge Norton Improvements to Norton Br. # 5102 in $840,000
PIN 015092.00 Replacement Carmel, located on Fuller Road, .6 mile
west of townline.


Aug 2009 Freeport New US 1 Sidewalk construction: Beginning at $60,000
PIN 013096.00 Construction Library Drive and extending 0.175 miles
(925 feet) northerly to Kendall Street.
The project will include new shoulders,
ledge removal, under drain and curbing.




Aug 2009 Fryeburg Strut St Rte 5 Strut located at RLM 58.297. $215,341
PIN 015965.00 Replacement


Aug 2009 Fryeburg New Off Safe Routes to School bicycle and $47,752
PIN 016341.00 Construction pedestrian improvements in the vicinity
of Molly-Ockett School. Installation
of Crosswalk Signal Lights on 302


Aug 2009 Gray Strut St Rte 100 Rte. 100 Gray RLM 13.63 Near Richard's $107,670
PIN 015980.00 Replacement Way.


Aug 2009 Hiram Bridge Culvert Burbank Bridge Culvert Rehabilitation, Invert $250,000
PIN 015606.00 Rehabilitation Lining: Burbank Bridge (#3879) at
Hancock Brook, located 1.02 miles
northerly of the Baldwin town line.


Aug 2009 Hiram Bridge Culvert Mill Pond Replace bridge culvert #5923 in the $250,000
PIN 015607.00 Replacement community of Hiram which carries Route
160/SA 2 over Ridlon Brook.


Aug 2009 Island Falls Bridge Iron Island Falls, on US 2, Iron Bridge # $4,000,000
PIN 015097.00 Replacement 2403, located 300 ft south of the
Junction of Route 159


Aug 2009 Mechanic Falls New Off Safe Routes to School bicycle and $21,844
PIN 016343.00 Construction pedestrian improvements near the Elm
Street School. Flashing School Zone
Signs lights and 2 raised crosswalks
including duratherm.


Aug 2009 Poland, Mechanic Intersection St Rte 26 Located at the intersection of Route 11 $1,050,000
Falls Improvements and Route 26 on the Poland - Mechanic
PIN 011189.00 W/O Signal Falls town line.


Aug 2009 Sanford New Off Safe Routes to School bicycle and $45,556
PIN 016346.00 Construction pedestrian improvements. Main St: bike
lanes 4 miles., Storm drain covers. 20
bike racks, 2 pedestrian signals.


Aug 2009 Standish Bridge Culvert Tucker Brook Tucker Brook Bridge (3093) over Tucker $275,000
PIN 012698.00 Rehabilitation Brook, located 0.10 mile northerly of
Route 113.


Aug 2009 Standish Bridge Sebago Lake Standish, Route 35, Sebago Lake Road $3,500,000
PIN 015107.00 Replacement Road Crossing Crossing Br. # 3907, located .6 mile
north of 114 over MCRR


Aug 2009 Thomaston Signal Elliott St Grade Crossing Improvement Program, $150,000
PIN 012971.00 Improvements(Ra Maine Eastern Railroad Install new gates
il/Highway and signals at Elliott Street.
Xing)


Aug 2009 Thomaston Signal Green St Grade Crossing Improvement Program, $145,000
PIN 012972.00 Improvements(Ra Install New half-gates and signals at
il/Highway Green Street.
Xing)


Aug 2009 Thomaston Reconstruction Mechanic St Grade Crossing Improvement Program, $125,000
PIN 012973.00 Investigate closing the at-grade
crossing on Mechanic Street located
approximately 0.03 mile north of Eliot
Street.


Aug 2009 Turner Intersection St Rte 4 Intersection Improvement Without a $260,000
PIN 012760.00 Improvements Signal at the intersection of Route 4
W/O Signal and Route 219


Aug 2009 Waterville New Other Preliminary Engineering for Future $320,000
PIN 011839.00 Construction Improvements, bicycle and pedestrian
facility: located between Alfond Sports
Complex along the Messalonskee Stream
and local streets to the Two Cent
Bridge.


Aug 2009 Waterville Intersection Rd Inv 11 50078 Intersection Improvement: Located at the $145,000
PIN 015683.00 Improvements intersection of Chase Avenue and First
W/O Signal Rangeway.


Aug 2009 Westbrook Intersection Rd Inv 05 90035 Intersection Improvements: Located at $80,000
PIN 015677.00 Improvements W/ the intersection of Cumberland Street
Signal and Pierce Street.


Sep 2009 Bangor Intersection Rd Inv 19 A0329 Modify traffic signals/Intersection $110,000
PIN 015688.00 Improvements W/ Improvement: Located at the intersection
Signal of the Interstate 95 south bound off
ramp and Union Street.


Sep 2009 Blue Hill New Off Safe Routes to School pedestrian $65,000
PIN 016357.00 Construction improvements in the vicinity of Blue
Hill Consolidated and the Bay Schools.
New sidewalk on High Street from Union
Street along the south side to Pleasant
Street. Mill Brook foot bridge
improvements for pedestrians.


Sep 2009 Boothbay Bridge Knickerbocker Bridge replacement project for #2438 $5,160,000
PIN 012630.00 Replacement Knickerbocker Bridge in Boothbay.


Sep 2009 Bowdoin Intersection St Rte 125 Flashing Beacon installation at the $21,500
PIN 015679.00 Improvements W/ intersection of Main Street and Meadow
Signal Road.


Sep 2009 Brewer Reconstruction St Rte 15 To construct improvements at second $1,273,000
PIN 014871.10 location on Route 15 with High Priority
funds


Sep 2009 Falmouth Bridge RR Crossing Falmouth, RR Crossing Br # 2702, on $17,700,000
PIN 015094.00 Replacement route 26 located 0.1 mile S of Turnpike
Ramp 10


Sep 2009 Howland Bridge Piscataquis .1 MI NE RTE 6, CARRIES COFFIN ST/RTE $9,000,000
PIN 015635.00 Replacement 116 OVER THE PISCATAQUIS RIVER. -
Preliminary Engineering for Future
Replacement:


Sep 2009 Kittery Bridge Dennett Rd Kittery, Eliot Road Overpass Bridge # $3,900,000
PIN 015099.00 Replacement Overpass 1362, located on the Route 1 Bypass over
Route 103


Sep 2009 Patten Bridge Removal B.A.RR Station Patten, on Station Street, Barr Station $140,000
PIN 015104.00 Br. # 3626, located 100 ft south of
Station Road over Fish Stream


Sep 2009 Windham Intersection US 202 Intersection Improvement Without a $25,000
PIN 012767.00 Improvements Signal at the intersection of Route
W/O Signal 4/202 and Falmouth Road


Oct 2009 Auburn Intersection Rd Inv 01 10480 Intersection Improvement Without a $245,000
PIN 012740.00 Improvements Signal at the intersection of Hotel Road
W/O Signal and Young's Corner Road


Oct 2009 Benton Mill And Fill St Rte 11 Highway Resurfacing: Beginning 0.07 of $1,442,257
PIN 012852.00 Plus a mile south of River Road and extending
northerly 1.75 miles to Route 100A.


Oct 2009 Gouldsboro Reconstruction St Rte 186 Beginning 0.13 miles south of Armory $1,200,000
PIN 012784.01 Court in Gouldsboro and extending
northerly 1.5 miles to end,
approximately 0.11 miles south of the
Clinic Road.


Oct 2009 Livermore Falls New Off-System This project will design and construct a $242,541
PIN 011850.00 Construction shared-use path adjacent to Foundry
Road.


Oct 2009 Mexico Other Highway US 2 Mexico, Route 2. Highway improvements $950,000
PIN 015143.00 Maintenance to Route 2 in Mexico adjacent to Webb
River Bridge beginning at Webb River
Bridge on Route 2, 0.22 miles west
towards Rumford.


Oct 2009 Mexico, Dixfield Bridge Webb River Webb River Bridge (2917) over Webb $2,320,000
PIN 015620.00 Replacement River, located on the Mexico and
Dixfield town line.


Oct 2009 Portland Reconstruction Rd Inv 05 60621 Intersection improvements with signal $753,000
PIN 005136.30 at Warren Avenue and extending northerly
0.10 of a mile.


Oct 2009 Rangeley Rest Area Bathroom Imps DESIGN & CONSTRUCTION OF BATHROOM & $210,910
PIN 012526.00 Construction/Im OTHER BYWAY IMPROVE RANGELEY VILLAGE &
provements OQUOSSOC


Oct 2009 Regional Signing Other Statewide non interstate truss $3,200,000
PIN 013023.00 replacement on Falmouth spur, south
Portland Route 1, Bath Route 1,
Scarborough connector and state route
703


Oct 2009 Statewide Signing State Preliminary Engineering for Statewide $1,980,000
PIN 013022.10 truss replacement on the interstate
system I-95, I-295 and I-395.


Oct 2009 Waldoboro Environmental Other A cooperative project between IFW and $75,000
PIN 012824.00 Improvements MaineDOT to restore brook trout to the
(Misc.) upper reaches of Farnsworth Brook under
Route 220 in Waldoboro. Habitat
restoration demonstration project.



Oct 2009 Wells Sidewalk Road On RTE 1, Beginning at Harbor Road and $301,360
PIN 011845.00 Construction extending northerly along 1250 feet to
the Congregational Church.


Oct 2009 Wells Intersection US 1 Intersection Improvements - Intersection $569,134
PIN 011921.00 Improvements W/ of Route 1 and Route 109.
Signal


Oct 2009 Wells Sidewalk Other Continue sidewalk improvements as part $425,000
PIN 013354.00 Construction of the towns master sidewalk plan
project. Continue sidewalk construction
on RTE 109 from Wells Town Office to
Route 1.


Oct 2009 Westbrook New Rd Inv 05 90150 Construciton of 550' sidewalk from $75,000
PIN 013118.00 Construction Eisenhower Drive to condominiums.


Oct 2009 Westbrook Highway St Rte 25 Westbrook, Route 25 highway improvements $5,012,674
PIN 015234.00 Widening And from Westbrook Connector to Saco St.
Overlay


Oct 2009 Windham Intersection US 202 Intersection Improvement Without a $320,000
PIN 012766.00 Improvements Signal at the intersection of Route
W/O Signal 4/202 and Route 115


Nov 2009 Grand Lake Stream Plt Bridge Milford Street Grand Lake Stream Plt., on Milford St., $780,000
PIN 015096.00 Replacement Bridge # 3584 located 6.8 mile West of
Indian Township town line


Nov 2009 Portland New Other Marine bulkhead replacement at the Gulf $700,000
PIN 016003.00 Construction of Maine Research Institute in Portland.


Nov 2009 Swanville Bridge Culvert Swanville Replace bridge culvert #5282 which $158,976
PIN 015617.00 Replacement carries SA 5/Curtis Road over the Goose
River in the community of Swanville.


Dec 2009 Winslow Bridge Mile Brook Bridge Replacement to Mile Brook Bridge $6,690,000
PIN 011048.00 Replacement (#3228) over Outlet Brook, located 0.57
of a mile northerly of the Bertchester
Road.


Dec 2009 Woolwich Intersection US 1 Safety improvements for motorists and $1,000,000
PIN 015695.00 Improvements emergency vehicle access at the
W/O Signal intersection of Route #1 and Nequasset
Road. .


Jan 2010 Canaan, Pittsfield Bridge Sibley Pond REPLACE STRUCTURE #2767 IN THE TOWNS OF $11,000,000
PIN 015618.00 Replacement CANAAN AND PITTSFIELD WHICH CARRIES US 2
OVER SIBLEY POND.


Jan 2010 Ellsworth Roadside Other High Street Beautification of sidewalks $400,000
PIN 012811.00 Improvements and streetscape improvements. The
project on east side of High Street from
Cadillac Mt. Sports to DOT garage, west
side from Washington St to Mcdonalds.


Jan 2010 Fryeburg Bridge Charles River Fryeburg, Charles River # 2151, located $1,715,000
PIN 015095.00 Replacement 2.6 mile westerly Junction of Route 5 on
Harbor Road.


Jan 2010 Gardiner Bridge New Mills Gardiner, New Mills Br. # 2605, Steel $400,000
PIN 012633.01 Rehabilitation Sandwich panel bridge deck


Jan 2010 Kennebunk Bridge Kennebunk Kennebunk, US 1, Kennebunk Bridge # $1,449,000
PIN 015098.00 Replacement 2431, located 0.2 mile N 9A/99 over the
Mousam River


Jan 2010 Lisbon Reconstruction Rd Inv 01 30122 Beginning at the Urban Compact limit and $1,730,000
PIN 013064.00 extending easterly 1.48 miles to Route
9.


Feb 2010 Bar Harbor, Mount Miscellaneous St Rte 3 Project will assess potential solutions $250,000
Desert Safety and begin design of preferred solution
PIN 012786.00 Improvements to improve safety because of a failing
retaining wall.




Feb 2010 Brewer Reconstruction US 1a Highway Reconstruction: Beginning at $1,550,000
PIN 013077.00 Greenpoint Road and extending 0.45 of
mile to Walmart.


Feb 2010 Brunswick Intersection St Rte 24 Brunswick, Realigning Maine St. & Bath $0
PIN 016533.00 Improvements Road intersection to improve safety and
W/O Signal mobility.


Feb 2010 Carmel Bridge Mcrr Crossing Mcrr Crossing Bridge (2976) over Mcrr, $3,000,000
PIN 015622.00 Replacement located 0.11of a mile easterly of the
Hinkley Road.


Feb 2010 Greenville 3/4" Overlay Maint C413k Div Highway Resurfacing: Beginning 0.03 of $120,000
PIN 015769.00 3 a mile north of Shoals Road and
extending northerly 0.92 of a mile.


Feb 2010 Leeds Reconstruction St Rte 219 Preliminary Engineering for future $3,365,000
PIN 012669.00 highway reconstruction: Beginning 0.31
mi east of the Leeds-Turner town line
and extending easterly 1.58 miles.


Feb 2010 Newport Bridge Main Street REPLACE THE MAIN STREET BRIDGE #2501 IN $3,955,000
PIN 015625.00 Replacement NEWPORT WHICH CARRIES ROUTES US 2-100
OVER THE EAST BRANCH OF THE SEBASTICOOK
RIVER.


Feb 2010 South Portland Bridge Removal Interchange Bridge Removal: South Portland $1,600,000
PIN 011062.00 Overpass Interchange Overpass Bridge (#6199),
located 0.16 of a mile northerly of Main
Street.


Feb 2010 West Gardiner, 1 1/4" Overlay St Rte 9 WPMT Preliminary Engineering for Future $750,839
Gardiner Plus Reconstruction: Beginning at the West
PIN 011352.00 Gardiner town line and extending
easterly 0.72 of a mile.


Mar 2010 Auburn Intersection St Rte 11 Construction of opposing left turn lanes $716,720
PIN 015668.00 Improvements W/ located at the intersection of Minot
Signal Avenue and Hotel Road.


Mar 2010 Augusta Bridge Deck I-95 NB/New Augusta, I-95 NB New Belgrade Br. # $1,350,000
PIN 015088.00 Replacement Belgrade Rd 5793, located at mile 105.8 on I-95 NB


Mar 2010 Bar Harbor Sidewalk Other SCENIC BYWAY ENHANCEMENTS RETAINING WALL $221,000
PIN 012487.00 Construction & SIDEWALK IMPR WEST ST. FERRY TERMINAL



Mar 2010 Belfast Mill And Fill US 1 Highway Resurfacing: Beginning at the $1,145,570
PIN 016802.00 Belfast/Northport town line, and
extending northerly 3.92 miles to
Veterans Memorial Bridge


Mar 2010 Blue Hill Reconstruction St Rte 15 DEFERRED Beginning at the Sedgwick town $1,711,075
PIN 012779.00 line and extending northerly 2.10 miles.


Mar 2010 Brunswick Mill And Fill US 1 SB Highway Resurfacing: Beginning at the $854,570
PIN 016794.00 intersection of Cooks
corner/US-1-Southbound and extending
1.68 miles to the intersection of US-1
Southbound and Route 196


Mar 2010 Brunswick Mill And Fill US 1 SB Highway Resurfacing: Beginning at the $556,780
PIN 016795.00 intersection of US-1-Southbound and
Route 196, and extending 1.17 miles to
the intersection of US-1 Southbound and
Maine St.


Mar 2010 Canaan, Skowhegan 3/4" Overlay US 2 Highway Resurfacing: Beginning at the $1,114,821
PIN 016808.00 Plus Wesserunsett Stream Bridge and extending
easterly 5.02 miles to the
Skowhegan/Canaan town line.


Mar 2010 Caribou Mill And Fill St Rte 164 Highway Resurfacing: Beginning at the $1,418,140
PIN 016812.00 Plus intersection of Hatch Dr./ Record St.
extending Southerly 1.81 mi to 0.37 mi
south of Wilbur Ave.


Mar 2010 Caribou Mill And Fill St Rte 89 Highway Resurfacing: Beginning 0.05 mi $1,475,370
PIN 016813.00 from the intersection of County Rd/Old
Cross Rd, extending northerly 4.88 mi to
0.04 mi East of the Caribou/Limestone
town line.


Mar 2010 Caswell, Limestone 3/4" Overlay US 1a Highway Resurfacing: Beginning at the $961,464
PIN 016814.00 intersection of Pond Vew St/ and rte.
1A, extending northerly 3.8 mi to 0.01
mi south of the intersection of Route 1A
/ Willard Crossing Rd.


Mar 2010 Clifton, Eddington Structural St Rte 9 Highway Resurfacing: Beginning 0.29 mi $5,512,170
PIN 016810.00 Overlay easterly from the intersection of Eddy
Heights Rd./Main Rd. and extending
easterly 9.4 miles to a point 1.0 miles
westerly of the Chick Hill Road.


Mar 2010 Durham 3/4" Overlay St Rte 9 Highway Resurfacing: Beginning at the $714,020
PIN 016801.00 intersection of Newell Brook Road and
Royalsborough Road and extending 3.755
miles to the intersection of Newell
Brook Road and Pinkham Brook Road.


Mar 2010 Ellsworth New Off-System This project will design approximately $700,000
PIN 009636.00 Construction 2.0 miles of shared-use path, a portion
of the Downeast Trail, from Ellsworth
Falls to High Street.


Mar 2010 Frankfort 3/4" Overlay Maint C322m Div Highway Resurfacing: Beginning 0.04 of $117,238
PIN 015740.00 5 a mile east of Hamm Road and extending
easterly 1.3 miles to 0.09 of a mile
west of West Hill Road.


Mar 2010 Frankfort, Prospect Mill And Fill US 1a Highway Resurfacing: Beginning 0.34 mi $770,180
PIN 016804.00 north of Muskrat Farm Rd. and extending
northerly 2.31 mi to 0.03 mi north of
the Frankfort/Prospect town line.


Mar 2010 Madison Intersection US 201 Install left turn lane at the $450,000
PIN 015685.00 Improvements W/ intersection of Route 201 and Route 148.
Signal


Mar 2010 Madison, Skowhegan Mill And Fill US 201 Highway Resurfacing: Beginning at $1,962,310
PIN 016806.00 Plus Russell Street (Commercial Street) and
extending northerly 1.861 miles to 0.091
mile north of the Skowhegan/Madison town
line.


Mar 2010 Naples Bridge Naples Bay Bridge Replacement: Naples Bay Bridge $15,200,240
PIN 011060.00 Replacement (#2047) over the Chutes River, located
0.30 of a mile northerly of Route 35.
Placeholder for higher level, fixed
bridge; final project scope subject to
outcome of pending study.


Mar 2010 New Sweden 1 1/4" Overlay St Rte 161 Highway Resurfacing: Beginning 0.09 mi $1,809,050
PIN 016811.00 Plus south of Station Rd, extending northerly
5.95 mi to 0.05 mi south of the New
Sweden/Stockholm town line.


Mar 2010 Oxford Mill And Fill St Rte 26 Highway Resurfacing: Beginning 0.10 $564,540
PIN 016807.00 mile east of the Norway/Oxford town line
and extending westerly 0.890 mile to
0.026 mile east of Grove Street.


Mar 2010 Palermo 1 1/4" Overlay St Rte 3 Highway Resurfacing: Beginning 0.12 mi $971,009
PIN 016805.00 west of Jones/Paremter Rd intersection,
extending easterly 3.26 mi to 0.13 mi
east of Arthur Plummer Rd.


Mar 2010 Portland Reconstruction Int 295 NB Highway Reconstruction: I-295, Add $1,810,160
PIN 015634.00 southbound auxiliary lane between Exit 7
and Exit 8 with additional lanes added
to both the northbound and southbound
off ramps.


Mar 2010 Prospect, Stockton Mill And Fill US 1a Highway Resurfacing: Beginning at the $1,291,070
Springs intersection of US 1/US 1A and extending
PIN 016803.00 northerly 3.72 mi to 0.34 mi north of
Muskrat Farm Rd.


Mar 2010 Searsport New US 1 Intersection improvements at Rte 1 & $200,000
PIN 013136.00 Construction Trundy Road.


Mar 2010 York 1 1/4" Overlay US 1 Highway Resurfacing: Beginning 0.11 of $1,961,977
PIN 015822.00 a mile south of Spur Road and extending
northerly 6.96 miles to the
York-Ogunquit town line.


Mar 2010 York 1 1/4" Overlay Maint D001n Div Highway Resurfacing: On the Spur Road $270,550
PIN 015823.00 6 beginning at Chases Pond Road and
extending northerly 0.51 of a mile to
Route 1.


Apr 2010 Auburn Reconstruction St Rte 11 Highway Reconstruction: To allow 2 way $4,725,000
PIN 011599.00 traffic along the Minot Ave leg of the
rotary on Minot Avenue.


Apr 2010 Augusta Full Depth St Rte 9 Highway Resurfacing - From the $455,000
PIN 016827.00 Reclaim Chelsea/Augusta Town Line, extending to
W/Cement .03 miles North of Kelton Rd.


Apr 2010 Berwick, North 3/4" Overlay St Rte 4 Highway Resurfacing: Beginning 0.17 mi $1,358,000
Berwick, South from Portland St./S. Gate Rd and
Berwick extending 6.29 miles to 0.16 mi. from
PIN 016799.00 Lebanon Rd.


Apr 2010 Carmel, Newburgh, Mill And Fill Int 95 NB Highway Resurfacing: Beginning 2.70 $2,965,000
Hampden, Hermon Plus miles north of the Carmel town Line and
PIN 016821.00 extending northerly 5.93 miles.Includes
all Ramps


Apr 2010 Cumberland, Falmouth, Mill And Fill Int 295 NB Falmouth-Cumberland-Yarmouth-Freeport, $4,425,000
Freeport, Yarmouth I-295NB, Mill & Fill Pavement Treatment,
PIN 016774.00 Guardrail updates. Begins at the
Portland/Falmouth TL & extends north
11.91 miles to the Desert Road off Ramp.
Guardrail and Drainage will be done
under PIN 16774.10.


Apr 2010 Etna, Plymouth, Mill And Fill Int 95 SB Mill and Fill Pavement Treatment $19,000,000
Newport, Bangor, Plus Guardrail updates Drainage updates
Hermon, Hampden,
Newburgh, Carmel,
Palmyra, Pittsfield
PIN 016784.00


Apr 2010 Falmouth 3/4" Overlay Rd Inv 05 40203 Highway Resurfacing: Beginning 0.06 of a $258,990
PIN 016798.00 mile easterly of Merrill Rd. and
extending westerly 1.23 miles to 0.30 of
a mile westerly of Sunnyfield Lane.


Apr 2010 Farmington, New 1 1/4" Overlay St Rte 27 Highway Resurfacing: Beginning at $3,850,000
Vineyard, New Fairbanks Rd. and extending northerly
Portland 13.88 mi to 0.15 mi north of the
PIN 016828.00 intersection of Chick Rd./Lemon Stream
Rd./River Rd.


Apr 2010 Fryeburg New Off Rail with Trail from the Visitors Center $1,380,000
PIN 016130.00 Construction at the New Hampshire Town Line to the
intersection of Route 113 near
Brownfield, including parking area(s)


Apr 2010 Fryeburg, Lovell 3/4" Overlay St Rte 5 Highway Resurfacing: Beginning 1.04 mile $364,500
PIN 016815.00 south of the Fryeburg/Lovell town line
and extending 1.695 mile to 0.39 mile
north of Shave Hill Rd.



Apr 2010 Hampden Reconstruction US 1a Highway reconstruction: Beginning 0.26 $1,469,500
PIN 014796.00 of a mile north of Wheelden Heights and
extending 0.5 of a mile to Hillside
Drive.


Apr 2010 Howland, Enfield Bridge Wearing Penobscot River .3 MI.W. US#2, CARRIES RTE 155 OVER $185,000
PIN 012675.00 Surface PENOBSCOT RIVER - WEARING SURFACE
Replacement REPLACEMENT


Apr 2010 Island Falls, Dyer Mill And Fill Int 95 NB Highway Resurfacing - Includes Ramps $19,000,000
Brook, Oakfield, Plus
Sherman, Crystal,
Smyrna, Ludlow, New
Limerick, Houlton
PIN 016819.00


Apr 2010 Kingfield, New 3/4" Overlay St Rte 27 Highway Resurfacing: Beginning 0.15 mi $740,292
Portland north of the intersection of Chick
PIN 016809.00 Rd/Lemon Stream Rd/River Rd. and
extending northerly 5.56 mi to 0.07 mi
south of High St.


Apr 2010 Livermore Falls, Jay Reconstruction St Rte 4 Preliminary Engineering for future $6,205,419
PIN 010018.00 highway improvements: Beginning at
Bridge Street and extending northerly
1.11 miles to Pineau Street.


Apr 2010 Milo 3/4" Overlay St Rte 11 Highway Resurfacing: Beginning at Elm $204,700
PIN 015788.00 Street and extending northerly 1.96
miles to 0.36 of a mile north of Dusty
Lane.


Apr 2010 Orrington Reconstruction St Rte 15 DEFERRED Reconstruction: Beginning 0.10 $11,025,000
PIN 009204.10 of a mile northerly of Railroad Crossing
#365453 and extending northerly 2.75
miles to 0.21 of a mile southerly of RR
Crossing #365455.



Apr 2010 Portland Ramp Int 295 NB HPP FUNDS ADJ. RAMPS & ISLANDS TO $1,095,200
PIN 010557.01 Improvements IMPROVE TRAFFIC OPERATIONS I-295 AT
FORREST AVE.
Apr 2010 Ramp Int 295 NB HPP FUNDS ADJ. RAMPS & ISLANDS TO $1,095,200
Improvements IMPROVE TRAFFIC OPERATIONS I-295 AT
FORREST AVE.


Apr 2010 Rumford Intersection St Rte 108 Rumford, Rumford Business Park, Widen $465,000
PIN 014407.00 Improvements State Route 108 westbound approach to
W/O Signal provide a dedicated 12 ft. wide
left-turn lane. widen State Route 108
eastbound approach to provide a 12 ft.
wide exclusive right turn lane.


Apr 2010 Rumford Intersection St Rte 108 Rumford, Wyman Hill Road, Realign Wyman $0
PIN 014408.00 Improvements Hill Road reducing the skew approach
W/O Signal angle to State Route 108


Apr 2010 Rumford Reconstruction St Rte 108 Rumford, Remove ledge and other material $135,000
PIN 014409.00 along the southwest side of State Route
108 to provide a 10 ft. snow storage
area behind the existing curb.


Apr 2010 Sidney Pmrap St Rte 104 Beginning 0.30 miles northerly of $2,832,000
PIN 012793.00 Augusta town line and extending
northerly to the intersection of rte.
104 and Lions rd. Sidney


Apr 2010 South Portland Structural Rd Inv 05 80055 Highway Rehabilitation: Beginning at $1,425,000
PIN 016800.00 Overlay Lincoln St. and extending 1.29 mi to
Anthoine St.


Apr 2010 Stockton Springs New Off Safe Routes to School pedestrian $251,300
PIN 016350.00 Construction improvements in the vicinity of Stockton
Springs Elem School. New and upgraded
sidewalks on Main Street from US Route 1
to the Health Center on the Cape
Jellison Road. New sidewalks on Church
St from Maine St to school.


May 2010 Bangor Structural Rd Inv 19 10208 2-inch mill and overlay: Beginning at $639,800
PIN 014792.00 Overlay Griffin Road and extending 1.08 miles to
Blue Hill. Scope calls for providing new
sidewalk at all existing locations, and
new bitumimous curb where existing.


May 2010 Biddeford Reconstruction US 1 Preliminary engineering for highway $3,400,000
PIN 014814.00 reconstruction: Beginning at Beaudoin
Avenue and extending 0.54 of a mile to
Grayson Street.


May 2010 Easton Intersection US 1a Intersection widening to allow 53 foot $272,240
PIN 015988.00 Improvements trailers to turn without encroaching
W/O Signal over centerline


May 2010 Falmouth Reconstruction Int 295 NB Highway Reconstruction: Lengthen $1,715,160
PIN 015633.00 acceleration lane on I-295 northbound at
the Falmouth Spur on-ramp.


May 2010 Houlton New Off Houlton Sidewalk Improvements to include $170,000
PIN 016135.00 Construction four new sidewalks on North Street,
Putnam Ave, Columbia Street and Military
Street.


May 2010 Molunkus Twp Slope St Rte 157 Located 0.09 of a mile westerly of the $20,287
PIN 012701.00 Stabilization/P Mattawamkeag town line.
rotection


May 2010 Plymouth, Newport Reconstruction St Rte 7 Segment 1) Beginning at the intersection $129,240
PIN 012790.00 with Clark Road in Plymouth aned
extending north 2.45 miles to the
northbound ramps of I-95. Segment 2)
Beginning at the southbound ramps of
I-95 and extending north 1.14 miles to
Route 2 in Newport.
May 2010 Reconstruction St Rte 7 Segment 1) Beginning at the intersection $129,240
with Clark Road in Plymouth aned
extending north 2.45 miles to the
northbound ramps of I-95. Segment 2)
Beginning at the southbound ramps of
I-95 and extending north 1.14 miles to
Route 2 in Newport.


Jun 2010 Portland Reconstruction US 302 Highway Reconstruction: Beginning at $3,410,000
PIN 013107.00 Riverside Industrial Parkway and
extending 0.37 of a mile to Riverside
Street.


Jun 2010 T4 Indian Purchase Bridge Culvert Grant Brook Rehab bridge culvert #3780 which carries $191,424
Twp Rehabilitation Route 11 over Grant Brook in the T4
PIN 015646.00 Indian Purchase.


Jun 2010 T4 Indian Purchase Bridge Culvert Partridge Rehab culvert (#3778) that carries Route $180,608
Twp Rehabilitation 11 over Partridge Brook in the T4 Indian
PIN 015647.00 Purchase.