Plymouth Pond Dam Fishway Installation Project
 
Click on picture for large view

 

Plymouth Pond Dam Fish Passage Contributors
 


Plymouth Pond Dam view from downstream

 
 
View upstream towards ledge drop (Plymouth Dam in the background) 8-28-02
 

 

Side channel to be cleared of material 8-28-02

 

L-R  downstream passage 2 upstream fish ladders 9-5-02

  

Installing the coffer dam (box) downstream view 9-5-02
 

 

Chipping away behind coffer dam (box) 9-10-02

 

Side channel cleared of material 9-10-02

 

Slot in dam for fishway installation 9-11-02

 

 

Slot cut into ledge drop for fishway installation 9-11-02

 

 

Plunge pool for downstream passage 9-13-02

 

 

Upstream passage at dam 9-17-02

 

Downstream bypass (left) and upstream passage 9-18-02

 

Building forms for concrete wall at site of ledge passage 9-18-02
 

 

View downstream at slot for fishway 9-27-02
 

 

View upstream towards slot for fishway 9-27-02

 

Trash rack at lower fishway 10-2-02



Repositioning the lower fishway 10-2-02

 

Field trial upper fishway 10-3-02 (photo courtesy of NRCS)



Field trial lower fishway 10-3-02 (photo courtesy of NRCS)

 

Taking water velocity readings at lower fishway 10-3-02 (photo courtesy of NRCS)

 

Completed lower fishway (upper fishway in background) 10-16-02

 



Completed upper fishway 10-16-02

  Read about the - SEBASTICOOK RIVER FISH PASSAGE PROJECTS