Drinking Water State Revolving Loan Fund (DWSRF)
Project Guide For ALL Projects
Before Construction Starts
Before a water system receiving DWSRF money begins construction, the following items must be completed:
- The water system has had a meeting with DWSRF staff to discuss the timeline of the project and any requirements by the DWSRF program and the Drinking Water Program
- An Environmental Review had been performed by the project engineer and approved by DWSRF staff and any other funding agencies involved in the project. Environmental determination categories are:
- Categorical Exclusion (CE)
- Finding of No Significant Impact (FNSI)
- Environmental Impact Statement (EIS)
- A loan application has been submitted and approved by the Maine Municipal Bond Bank.
- Plans and specifications have been reviewed and approved by DWSRF staff and other interested parties.
- A capacity review of the water system has been performed by DWSRF staff.
- Conduct a pre-construction meeting with the contractor, funding agencies and other interested parties.
If the above steps are not completed before construction starts, payment and construction could be delayed.